A business analyst is defining the solution scope for a project replacing a legacy claims system. The sponsor wants to include every capability the claims department might eventually need, while the operations manager wants to limit the release to core adjudication only. The analyst must recommend an approach that keeps the project deliverable while preserving future options. Which action best applies business analysis scope principles?

⚠ Common exam trap

The trap here is equating accommodation of a powerful sponsor with good scope practice, when the disciplined response is to defer unprioritized capabilities into a managed backlog rather than into the baseline.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Define the release scope around core adjudication and record the future capabilities in a backlog for later prioritization and release planning.

Effective solution scoping separates what the current release will deliver from capabilities that may be needed later. Anchoring the release on core adjudication keeps the project deliverable, while a prioritized backlog preserves the sponsor's future capabilities without committing the baseline. Inflating scope, mechanically extending timelines, or rejecting future needs outright all violate the principle that scope must be deliberate, value-driven, and managed across releases.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Expand the scope to include all capabilities but extend the timeline by an equal percentage to absorb the added work.

    Why it's wrong here

    Proportionally extending the timeline assumes effort scales linearly and ignores integration risk, which grows faster than the sum of parts in a legacy replacement. It also accepts the sponsor's maximalist position without evaluating value. Committing to capabilities no one has prioritized ties up budget and delays the core adjudication benefits the operation actually needs first.

  • ✓

    Define the release scope around core adjudication and record the future capabilities in a backlog for later prioritization and release planning.

    Why this is correct

    Solution scope should cover what the current release will deliver, while deferred capabilities belong in a managed backlog where they retain visibility without inflating the baseline. This satisfies the sponsor's concern that future options are not lost and the operations manager's need for a deliverable release. The backlog can be prioritized and scheduled in subsequent releases as value and capacity allow.

  • ✗

    Document all requested capabilities as in-scope and rely on change control to remove items that prove too costly during execution.

    Why it's wrong here

    Loading the baseline with speculative capabilities inflates scope, distorts estimates, and forces change control to remove work that should never have been committed. Change control is designed to manage genuine new needs, not to clean up an overbroad baseline. This approach guarantees schedule pressure on the core adjudication work and undermines the project's ability to deliver on time.

  • ✗

    Reduce scope to core adjudication and formally reject the sponsor's future capabilities so they cannot resurface.

    Why it's wrong here

    Rejecting the future capabilities outright discards legitimate business needs and damages the relationship with a key sponsor. Business analysis scope principles call for managing what is out of scope for this release, not for erasing future demand. Recording deferred items preserves their value for later prioritization and avoids forcing stakeholders to relitigate rejected needs from scratch.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.