CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which THREE of the following are recognized process groups in the PMBOK Guide? (Choose three)
⚠ Common exam trap
CAPM often tests the five process groups versus knowledge areas or general terms; candidates must not confuse 'Reviewing' or 'Analyzing' with the formal process groups.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Executing
The PMBOK Guide defines exactly five Process Groups that organize the project management processes: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. Option E (Initiating) is correct because it is the Process Group that authorizes the project or phase and defines its high-level scope and stakeholders. Option D (Planning) is correct because it establishes the project scope, objectives, and the course of action required to attain them. Option C (Executing) is correct because it is the Process Group where the work defined in the project management plan is carried out to satisfy project specifications. Options A (Reviewing) and B (Analyzing) are not recognized PMBOK Process Groups; reviewing and analyzing are activities that occur within Monitoring and Controlling and other processes, but they are not standalone Process Groups.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reviewing
Why it's wrong here
Reviewing describes an activity carried out inside processes, not a PMBOK process group; the recognised groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing. It is tempting because reviews occur throughout the lifecycle, but the exam distinguishes the five grouping categories from the work performed within them.
- ✗
Analyzing
Why it's wrong here
Analyzing is a technique performed within processes such as Monitor and Control Project Work, not one of the five PMBOK process groups: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. It is tempting because analysis activities pervade project work, yet the question asks for the grouping structure, not the actions inside it.
- ✓
Executing
Why this is correct
Executing is a recognised PMBOK process group comprising processes performed to complete the work defined in the project management plan. It follows Planning and satisfies the stem's constraint by being one of the five formal process groups, not a knowledge area.
- ✓
Planning
Why this is correct
Planning is one of the five PMBOK process groups, encompassing processes that establish scope, refine objectives, and define the course of action. It sits between Initiating and Executing, and the stem's constraint of recognised process groups is met precisely by this classification.
- ✓
Initiating
Why this is correct
Initiating is a recognised PMBOK process group containing processes that define a new project or phase and authorise it to proceed. It precedes Planning and satisfies the stem's requirement for a genuine process group rather than a knowledge area.
Go deeper
Related to this question
About these practice questions
One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PMI exam blueprint
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.