Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project is in the executing phase, and the team is frequently reworking deliverables due to defects. Which process is most likely inadequate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Quality management

Rework indicates issues with quality management. Scope verification is about formal acceptance, not preventing defects. Risk management might identify potential defects but doesn't prevent them directly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Quality management

    Why this is correct

    Rework is a sign that quality standards are not being met and quality control is insufficient.

  • Scope verification

    Why it's wrong here

    Scope verification is about accepting completed deliverables, not preventing rework.

  • Communications management

    Why it's wrong here

    Communication issues may cause misunderstandings but not necessarily specific defects.

  • Risk management

    Why it's wrong here

    Risk management identifies potential problems but does not directly control quality.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.