Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Drag and drop the steps for performing risk management planning in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Plan Risk Management, then Identify Risks, then Perform Qualitative Risk Analysis, then Perform Quantitative Risk Analysis, then Plan Risk Responses

Risk management follows the sequence: planning, identification, qualitative analysis, quantitative analysis, and response planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Plan Risk Management, then Identify Risks, then Perform Qualitative Risk Analysis, then Perform Quantitative Risk Analysis, then Plan Risk Responses

    Why this is correct

    This is the correct order as per PMBOK: risk management starts with planning the process, then identifying risks, performing qualitative analysis to prioritize, optionally performing quantitative analysis if needed, and finally planning responses.

  • Identify Risks, then Plan Risk Management, then Perform Qualitative Risk Analysis, then Perform Quantitative Risk Analysis, then Plan Risk Responses

    Why it's wrong here

    This is incorrect because you cannot identify risks before planning how the risk management process will be conducted. The plan defines roles, budgets, and schedules for the subsequent steps.

  • Plan Risk Management, then Identify Risks, then Perform Quantitative Risk Analysis, then Perform Qualitative Risk Analysis, then Plan Risk Responses

    Why it's wrong here

    This is incorrect because qualitative analysis should precede quantitative. Qualitative analysis prioritizes risks based on probability and impact, helping decide which risks need further quantitative analysis. Reversing the order is inefficient.

  • Plan Risk Management, then Identify Risks, then Plan Risk Responses, then Perform Qualitative Risk Analysis, then Perform Quantitative Risk Analysis

    Why it's wrong here

    This is incorrect because you must analyze risks before planning responses. Planning responses without knowing the priority or numerical impact of risks would lead to ineffective or misallocated responses.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.