Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project is behind schedule and over budget. The sponsor asks the project manager to reduce costs without affecting the end date. Which constraint should the project manager consider adjusting?

⚠ Common exam trap

CAPM often tests the misconception that you can independently reduce cost without touching scope or time — candidates forget the triple constraint's interdependency and pick 'Resources' or 'Quality' as if they were standalone levers.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Scope

The triple constraint (scope, time, cost) means you cannot change one without affecting the others. Since the sponsor explicitly wants to reduce costs without moving the end date, time is fixed and cost must decrease — the only remaining lever is scope. Reducing scope (descoping features or deliverables) lowers the work required, which in turn lowers cost while preserving the schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Scope

    Why this is correct

    Reducing scope removes deliverables or features from the project, which lowers cost and effort while preserving the fixed end date. Adjusting scope is the constraint that can absorb the budget reduction without extending the schedule.

  • ✗

    Quality

    Why it's wrong here

    Reducing quality does not lower cost or shorten duration; it accepts defects and rework, which typically increases both. It is tempting because cutting inspection and testing appears to save money immediately, and trading quality is legitimate only when the sponsor explicitly accepts degraded scope or performance.

  • ✗

    Time

    Why it's wrong here

    Time is the constraint the sponsor explicitly said must not move, so extending or compressing the schedule contradicts the instruction. It is tempting because crashing the schedule is a familiar cost-reduction response, yet here the fixed end date rules it out as the adjustable constraint.

  • ✗

    Resources

    Why it's wrong here

    Adjusting resources changes who and how much capacity performs the work, but the sponsor's constraint is cost reduction with the end date fixed; adding or removing resources does not by itself resolve the budget overrun. It is tempting because resource levelling is a standard schedule-compression lever.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.