Courseiva
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project is behind schedule and over budget. The sponsor asks the project manager to reduce costs without affecting the end date. Which constraint should the project manager consider adjusting?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Scope

Reducing scope can lower costs without extending time, though it may affect quality. Option B is wrong because reducing quality directly may violate standards. Option C is wrong because extending time would not reduce costs. Option D is wrong because resources increase costs.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope

    Why this is correct

    Reducing scope can lower costs while maintaining schedule.

  • Quality

    Why it's wrong here

    Reducing quality may not be acceptable or ethical.

  • Time

    Why it's wrong here

    Extending time typically increases costs.

  • Resources

    Why it's wrong here

    Adding resources increases costs.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.