CAPM Practice Question: Project Management Fundamentals and Core Concepts
Exhibit
Refer to the exhibit. ERROR 2025-03-10 14:32:01 Deployment script failed: Missing config file /etc/app/config.yaml INFO 2025-03-10 14:32:02 Rollback initiated
A project team encounters this error during deployment. Which project document should be updated first?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Issue log
An error during deployment is an issue that has already occurred, so it should be logged in the issue log for tracking and resolution. Option A is wrong because the change log is for approved changes, not for unexpected errors. Option C is wrong because the lessons learned register is updated after the project or phase, not immediately. Option D is wrong because the risk register is for uncertain events that may occur, but this error has already happened.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Change log
Why it's wrong here
The change log records approved changes, not incidents.
- ✓
Issue log
Why this is correct
The error is an issue that has occurred.
- ✗
Lessons learned register
Why it's wrong here
Lessons learned are captured after resolution.
- ✗
Risk register
Why it's wrong here
The risk register is for potential events, not realized ones.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on CAPM
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Refer to the exhibit. The project manager is reviewing deployment logs. Which statement best describes the event?
easy- A.The database remained unavailable after retries
- B.The deployment succeeded without any issues
- C.A warning was logged but no error occurred
- ✓ D.A temporary error occurred and was automatically resolved
Why D: The deployment log shows a temporary error (e.g., database unavailable) that was resolved automatically after a retry. The event indicates an error occurred but was successfully mitigated, not a success or permanent failure. Options A, B, and C are incorrect: A is wrong because the database became available after retries; B is wrong because an error did occur; C is wrong because no warning was logged and an error did occur.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.