Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager notices that the project's cost performance index (CPI) is 0.85. What does this indicate?

⚠ Common exam trap

CAPM often tests the confusion between CPI and SPI — candidates may incorrectly associate CPI with schedule performance, but CPI is strictly a cost efficiency metric.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The project is over budget

A CPI of 0.85 indicates that the project is over budget. CPI is calculated as Earned Value (EV) divided by Actual Cost (AC). A value less than 1.0 means that for every dollar spent, less than a dollar of value was earned, indicating cost overrun. Therefore, the project is over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The project is under budget

    Why it's wrong here

    A CPI of 0.85 means every unit of planned value costs 1.18 units, so the project is over budget, not under. Confusing CPI with a favourable variance is tempting because values below 1.0 can look like a threshold breach rather than an efficiency ratio; CPI above 1.0 would indicate under-budget performance.

  • ✗

    The project is behind schedule

    Why it's wrong here

    CPI measures cost efficiency against earned value, not time; schedule position comes from the schedule performance index (SPI) or schedule variance. The confusion arises because earned value metrics share the same EVM framework, so a poor CPI often accompanies slippage, but only SPI below 1.0 indicates being behind schedule.

  • ✗

    The project is ahead of schedule

    Why it's wrong here

    CPI compares earned value to actual cost, carrying no timing information; being ahead of schedule is shown by SPI above 1.0. The temptation is that EVM metrics are often reported together, so a low CPI may coincide with schedule variance, yet CPI 0.85 itself says nothing about schedule position.

  • ✓

    The project is over budget

    Why this is correct

    A CPI of 0.85 means earned value is 85% of actual cost, so every unit of work delivered costs more than planned. Since CPI below 1.0 indicates cost inefficiency, the project is over budget, matching the stem's stated value.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.