Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager notices that the project's cost performance index (CPI) is 0.85. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget

CPI < 1 indicates that the project is over budget, as the value earned is less than the cost incurred.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is under budget

    Why it's wrong here

    Under budget would be CPI > 1.

  • The project is behind schedule

    Why it's wrong here

    Schedule performance is measured by SPI, not CPI.

  • The project is ahead of schedule

    Why it's wrong here

    CPI measures cost efficiency, not schedule.

  • The project is over budget

    Why this is correct

    Correct: CPI less than 1 means cost overrun.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.