Courseiva
Project Management Fundamentals and Core ConceptsmediumMultiple SelectObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which TWO of the following are considered key constraints in project management that form the traditional 'triple constraint'?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Time

The triple constraint traditionally includes scope, time, and cost. Quality is often added but not part of the original triple. Risk and resources are separate knowledge areas.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Quality

    Why it's wrong here

    Quality is often considered an additional constraint, not part of the original triple.

  • Resources

    Why it's wrong here

    Resources are part of cost or separate, not in the traditional triple.

  • Time

    Why this is correct

    Time is a core constraint of the triple constraint.

  • Scope

    Why this is correct

    Scope is a core constraint of the triple constraint.

  • Risk

    Why it's wrong here

    Risk is a separate knowledge area, not a constraint in the triple.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.