Which TWO are outputs of the Initiating process group?

⚠ Common exam trap

CAPM often tests process-group-to-output mapping, tricking candidates into selecting Planning outputs like the scope statement, WBS, or risk register as Initiating outputs.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stakeholder register

The Initiating process group produces the project charter (D) via the Develop Project Charter process, which formally authorizes the project and names the project manager; it is the key output that launches the project. It also produces the stakeholder register (C) via the Identify Stakeholders process, which records stakeholder identification, assessment, and classification information. The project scope statement (A) is an output of the Planning process group (Define Scope), not Initiating. The work breakdown structure (B) is created in Planning (Create WBS). The risk register (E) is also a Planning output (Identify Risks).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project scope statement

    Why it's wrong here

    The project scope statement is produced during Planning in Define Scope, not Initiating. It is tempting because scope feels like an early, foundational artefact, yet Initiating outputs only the project charter and stakeholder register; scope definition requires the charter as input first.

  • ✗

    Work breakdown structure

    Why it's wrong here

    The work breakdown structure is created during Planning in Create WBS, not Initiating. It is tempting because decomposition feels preliminary, but Initiating yields only the project charter and stakeholder register; the WBS depends on the scope statement produced later in planning.

  • ✓

    Stakeholder register

    Why this is correct

    The stakeholder register is created during Initiating through stakeholder identification and analysis, so it qualifies as an Initiating output. It records each stakeholder's interests, influence and engagement needs, distinguishing it from Planning documents such as the communications management plan.

  • ✓

    Project charter

    Why this is correct

    The project charter formally authorises the project and names the project manager, making it a primary output of the Initiating process group. It is produced before planning begins, satisfying the stem's requirement for an Initiating output rather than a Planning artefact.

  • ✗

    Risk register

    Why it's wrong here

    The risk register is created during Planning, specifically in Identify Risks, not Initiating. It is tempting because risk identification feels foundational, but Initiating produces only the project charter and stakeholder register; the risk register follows once planning begins.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.