Courseiva
Project Management Fundamentals and Core ConceptsmediumMultiple SelectObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which TWO are outputs of the Initiating process group?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stakeholder register

The correct answers are C (Stakeholder register) and D (Project charter). Both are key outputs of the Initiating process group. Option A (Project scope statement) is an output of Planning. Option B (Work breakdown structure) is also from Planning. Option E (Risk register) is created during Planning as well.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project scope statement

    Why it's wrong here

    Output of Define Scope (Planning).

  • Work breakdown structure

    Why it's wrong here

    Output of Create WBS (Planning).

  • Stakeholder register

    Why this is correct

    Output of Identify Stakeholders.

  • Project charter

    Why this is correct

    Output of Develop Project Charter.

  • Risk register

    Why it's wrong here

    Output of Identify Risks (Planning).

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.