CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which TWO are outputs of the Initiating process group?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Stakeholder register
The correct answers are C (Stakeholder register) and D (Project charter). Both are key outputs of the Initiating process group. Option A (Project scope statement) is an output of Planning. Option B (Work breakdown structure) is also from Planning. Option E (Risk register) is created during Planning as well.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project scope statement
Why it's wrong here
Output of Define Scope (Planning).
- ✗
Work breakdown structure
Why it's wrong here
Output of Create WBS (Planning).
- ✓
Stakeholder register
Why this is correct
Output of Identify Stakeholders.
- ✓
Project charter
Why this is correct
Output of Develop Project Charter.
- ✗
Risk register
Why it's wrong here
Output of Identify Risks (Planning).
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.