Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

← People — Leading Projects practice sets

PMP People — Leading Projects • Complete Question Bank

PMP People — Leading Projects — All Questions With Answers

Complete PMP People — Leading Projects question bank — all 0 questions with answers and detailed explanations.

372
Questions
Free
No signup
Certifications/PMP/Practice Test/People — Leading Projects/All Questions
Question 1easymultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that two senior developers have conflicting work styles, causing delays. What is the best approach to resolve this?

Question 2mediummultiple choice
Read the full NAT/PAT explanation →

A project team member is consistently late with deliverables, affecting the critical path. The project manager has had informal conversations, but performance hasn't improved. What should the project manager do next?

Question 3hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team expresses frustration about unclear requirements from the product owner. The project manager wants to improve the situation. Which action aligns with the Agile principle of self-organizing teams?

Question 4easymultiple choice
Read the full People — Leading Projects explanation →

A new project manager is assigned to a project where the team is geographically distributed across three time zones. Which communication method is most effective for ensuring alignment?

Question 5mediummultiple choice
Read the full NAT/PAT explanation →

A project manager is leading a team with diverse cultural backgrounds. Some members are reluctant to speak up in meetings. What is the best strategy to promote inclusive participation?

Question 6mediummulti select
Read the full People — Leading Projects explanation →

A project team is experiencing low morale due to high workload and unclear priorities. The project manager wants to improve motivation. Which TWO actions are most effective according to motivational theories?

Question 7hardmulti select
Read the full People — Leading Projects explanation →

A project manager is building a new team from scratch. To maximize team performance, which THREE actions should the project manager take during the forming stage?

Question 8mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a cross-functional team where two key members have conflicting priorities. One member insists on following a strict process, while the other wants to expedite delivery. The project manager needs to resolve the conflict to keep the project on track. Which approach is most effective?

Question 9easymultiple choice
Read the full People — Leading Projects explanation →

During a team meeting, a junior developer hesitates to share an innovative idea due to fear of criticism. The project manager notices this and wants to foster a culture of psychological safety. What should the project manager do first?

Question 10hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is assigned to a complex project with a team distributed across three time zones. The project requires high collaboration and frequent decision-making. The project manager wants to select a team structure that maximizes communication and efficiency. Which organizational structure is most suitable?

Question 11easymultiple choice
Read the full People — Leading Projects explanation →

A project team is in the performing stage of development. The project manager is leaving for a two-week vacation. What is the best way to ensure the team remains productive?

Question 12mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that the team's velocity has decreased over the last two sprints. Retrospectives have not identified clear causes. The project manager suspects that team members are overworked and possibly experiencing burnout. What should the project manager do first?

Question 13mediummulti select
Read the full People — Leading Projects explanation →

A project manager is building a new project team. Which TWO actions are most effective for establishing a high-performing team?

Question 14hardmulti select
Read the full People — Leading Projects explanation →

During project execution, a project manager discovers that a key stakeholder is dissatisfied with the team's communication. The stakeholder feels left out of decisions and receives information too late. Which THREE actions should the project manager take to address this?

Question 15easymultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that two senior developers are in constant disagreement about the technical approach for a critical feature. The conflict is causing delays and lowering team morale. What should the project manager do first?

Question 16easymultiple choice
Read the full People — Leading Projects explanation →

A project team is distributed across three time zones. The project manager wants to improve team collaboration and ensure effective communication. Which tool or technique would best help achieve this?

Question 17mediummultiple choice
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies that many tasks were delayed because team members were unsure of their responsibilities. What is the most effective way for the project manager to prevent this in future projects?

Question 18mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a multicultural team where some members are from high-context cultures (e.g., Japan) and others from low-context cultures (e.g., Germany). Misunderstandings have occurred due to differing communication styles. What should the project manager do?

Question 19hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager observes that a team member is consistently missing deadlines and producing low-quality work. The project manager suspects it is due to personal issues but the team member is reluctant to discuss. What is the best course of action?

Question 20easymulti select
Read the full People — Leading Projects explanation →

Which TWO of the following are recognized benefits of using a team charter in project management?

Question 21mediummulti select
Read the full People — Leading Projects explanation →

Which THREE of the following are effective techniques for motivating a project team according to PMI?

Question 22mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a globally distributed team. Two team members from different time zones have conflicting work styles, leading to missed deadlines and tension. What is the best first step for the project manager to resolve this?

Question 23hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is forming a new team for a complex software development project. The sponsor insists on using a co-located team for better communication. However, the best available resources are located in different countries. What should the project manager do?

Question 24easymultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that a team member consistently submits deliverables late. The project manager suspects the team member is overburdened. What should the project manager do first?

Question 25hardmultiple choice
Read the full People — Leading Projects explanation →

Based on the resource histogram exhibit, what is the most likely impact on the project if no corrective action is taken?

Exhibit

Refer to the exhibit.

```
Resource Histogram (Hours per Week)
Week 1: 120 (actual)
Week 2: 150 (actual)
Week 3: 180 (planned)
Week 4: 200 (planned)
Team Capacity: 160 hours per week
```
Question 26mediummultiple choice
Read the full People — Leading Projects explanation →

During a project, a key team member resigns unexpectedly. The project manager needs to fill the role quickly. What is the first action the project manager should take?

Question 27mediummulti select
Read the full People — Leading Projects explanation →

Which TWO actions are effective for improving team performance in a virtual environment? (Choose two.)

Question 28hardmulti select
Read the full People — Leading Projects explanation →

Which THREE factors are most critical when selecting a conflict resolution technique for a project team? (Choose three.)

Question 29hardmultiple choice
Read the full NAT/PAT explanation →

You are the project manager for a large infrastructure project to upgrade a legacy network system across 50 remote sites. The project is in its second month, and the team consists of 12 members: 6 network engineers, 3 site coordinators, 2 QA testers, and 1 procurement specialist. The team is co-located at the headquarters except for the site coordinators who are at various locations. Recently, you have noticed that the weekly status meetings are dominated by the network engineers, and the QA testers rarely speak. The site coordinators have missed the last two meetings due to 'scheduling conflicts.' Deliverables from QA are consistently late, and there have been three incidents where network configurations were deployed without QA approval, causing outages at two sites. When you asked the lead network engineer about it, he said, 'QA is too slow; we had to move fast.' The QA lead is frustrated and feels marginalized. The sponsor has expressed concern about the increasing number of outages. The organizational culture is hierarchical, but the project charter gives you authority to manage the team. What should you do first to address this situation?

Question 30easymultiple choice
Read the full People — Leading Projects explanation →

During a project's execution phase, the project manager notices that two senior team members are in frequent conflict over technical approaches, causing delays. What is the BEST course of action for the project manager?

Question 31mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is forming a new project team. The team includes members from diverse cultural backgrounds and different functional areas. Which team development model should the project manager use to guide the team through forming, storming, norming, performing, and adjourning?

Question 32hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a virtual team distributed across three time zones. The team has been performing well, but recently two team members have missed deadlines and seem disengaged. The project manager suspects the cause is related to team member motivation. According to the PMBOK Guide, which theory suggests that people are motivated by achievement, recognition, and growth opportunities?

Question 33easymultiple choice
Read the full People — Leading Projects explanation →

A project team is in the storming stage of development. The project manager wants to help the team move to the norming stage. Which action would BEST support this transition?

Question 34mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a cross-functional team that includes members from different departments with conflicting priorities. The project is at risk of delays due to team members not collaborating effectively. What is the best approach for the project manager to resolve this issue?

Question 35hardmulti select
Read the full People — Leading Projects explanation →

A project manager is leading a globally distributed team with members in different time zones. The team is experiencing communication breakdowns and missed deadlines. Which TWO actions should the project manager take to improve team performance? (Choose two)

Question 36hardmultiple choice
Read the full People — Leading Projects explanation →

Based on the exhibit, what is the MOST likely cause of the resource issue?

Exhibit

Refer to the exhibit.

```
Resource Name: John Doe
Role: Senior Developer
Allocation: 100% (40 hrs/week) to Project Alpha
Actual Hours (last 2 weeks): 55 hrs/week
Project Health: On schedule, but developer reports burnout
```
Question 37easymultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using an agile methodology. The team is co-located and has been working together for three months. Recently, you notice that during daily stand-up meetings, the product owner often interrupts the team members to ask detailed technical questions, causing the meetings to run over the 15-minute timebox. Additionally, the team seems hesitant to share progress openly, and some members have started arriving late to the stand-up. The sprint backlog shows that velocity has dropped by 20% in the last two sprints. The product owner insists that the stand-up is the only time they have to get technical updates. What should the project manager do FIRST?

Question 38mediumdrag order
Read the full People — Leading Projects explanation →

Arrange the steps for developing a project charter in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 39mediumdrag order
Read the full People — Leading Projects explanation →

Arrange the steps for controlling project changes.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 40mediumdrag order
Read the full People — Leading Projects explanation →

Sequence the steps for managing stakeholder engagement.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 41mediummatching
Read the full People — Leading Projects explanation →

Match each project management process group to its primary purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Define a new project or phase

Establish scope, objectives, and course of action

Complete work defined in the project management plan

Track, review, and regulate progress and performance

Finalize all activities to formally close the project

Question 42mediummatching
Read the full People — Leading Projects explanation →

Match each project management artifact to its typical content.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Describes project deliverables and acceptance criteria

Lists all schedule activities with identifiers and descriptions

Structured tool to verify that a set of required steps has been performed

Describes the procurement item in sufficient detail for sellers

Identifies strategies to effectively engage stakeholders

Question 43mediummultiple choice
Read the full People — Leading Projects explanation →

During the execution phase of a construction project, two senior engineers have a heated disagreement over the technical approach for a critical structural component. The conflict is causing delays and affecting team morale. As the project manager, what should you do FIRST?

Question 44easymultiple choice
Read the full People — Leading Projects explanation →

You are managing an agile software development team. In the last three sprints, the team's velocity has dropped from 30 to 22 story points. The team members are experienced but seem demotivated. What is the BEST action to take?

Question 45hardmultiple choice
Read the full NAT/PAT explanation →

Your project is in the middle of execution when a key vendor informs you that they will be unable to deliver a critical component on time due to a raw material shortage. The component is on the critical path. The risk was identified and logged in the risk register with a mitigation plan. What should you do FIRST?

Question 46mediummultiple choice
Read the full People — Leading Projects explanation →

A project team member has been consistently missing deadlines for the past two weeks, causing delays for dependent tasks. When you speak with them, they mention personal issues but assure you they will catch up. What is the BEST approach?

Question 47easymultiple choice
Read the full NAT/PAT explanation →

Your project team consists of members from different cultural backgrounds, and you notice that some team members are not voicing their opinions during meetings, while others dominate discussions. What is the BEST way to foster an inclusive environment?

Question 48mediummultiple choice
Read the full People — Leading Projects explanation →

During a hybrid project, the product owner frequently bypasses you and gives direct instructions to the development team. The team is confused about priorities, and scope creep is occurring. What should you do FIRST?

Question 49mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The team is working hard, but you suspect the original estimates were too optimistic. What is the BEST action to take?

Question 50hardmultiple choice
Read the full People — Leading Projects explanation →

A new regulatory requirement has been discovered that will affect your project's deliverables. The requirement is mandatory and must be implemented before the project can close. Your team has the skills to implement it, but it will add two months to the schedule. The sponsor is pushing for the original deadline. What should you do FIRST?

Question 51easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a virtual team across four time zones. Team members report feeling disconnected and communication is becoming fragmented. What is the BEST way to improve team cohesion?

Question 52mediummultiple choice
Read the full People — Leading Projects explanation →

In a Scrum project, the development team consistently fails to meet the sprint goal. The product owner is frustrated, and the team is demotivated. During the retrospective, the team identifies that the sprint backlog is too ambitious. What is the BEST action for the Scrum Master?

Question 53mediummultiple choice
Read the full People — Leading Projects explanation →

Your project sponsor asks you to skip the testing phase to save time and meet the deadline, arguing that the team is experienced and the product is simple. What should you do?

Question 54hardmultiple choice
Read the full NAT/PAT explanation →

You are managing a project using a hybrid approach. The team has a mix of senior and junior members. A senior developer is consistently dominating pair programming sessions, leaving the junior developer passive. The junior's performance is declining. What is the BEST action?

Question 55mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a distributed team where members are in different time zones and have varying levels of experience. The team is struggling with knowledge sharing and collaboration. Which TWO tools or techniques should the project manager consider to improve the situation? (Choose two.)

Question 56mediummulti select
Read the full People — Leading Projects explanation →

During a project transition, a key team member resigns unexpectedly. The project manager needs to ensure knowledge transfer and minimize impact. Which THREE actions should the project manager take? (Choose three.)

Question 57hardmulti select
Read the full People — Leading Projects explanation →

An agile project team is in the middle of a sprint when the product owner introduces a high-priority change that was not part of the sprint backlog. The team is concerned about their ability to deliver the sprint goal. Which TWO options align with the Scrum framework? (Choose two.)

Question 58mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a hybrid project. During the last two sprints, velocity has dropped significantly. The team members complain about unclear priorities and frequent context switching. What should you do first?

Question 59hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a global virtual team. A conflict arises between two senior developers from different cultures. One feels the other is not respecting their time zone, while the other accuses the first of micromanaging. What is the best approach to resolve this conflict?

Question 60easymultiple choice
Read the full People — Leading Projects explanation →

A project team member, who is a key technical expert, has been consistently missing deadlines. The project manager has already discussed the issue informally, but performance has not improved. What should the project manager do next?

Question 61mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner expresses dissatisfaction with the delivered increment because it does not meet their expectations. The team followed the agreed-upon acceptance criteria. What should the project manager do?

Question 62mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a large, distributed team. Several team members have expressed feeling isolated and disconnected from the project's goals. The project manager wants to improve team cohesion and motivation. What should the project manager do first?

Question 63hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is managing a hybrid project with both fixed-price and agile components. The sponsor asks the project manager to skip the testing phase for the agile portion to save time, assuring that the team is highly skilled and can deliver quality code without testing. What should the project manager do?

Question 64easymultiple choice
Read the full People — Leading Projects explanation →

A new project manager is assigned to an ongoing project. The team seems demotivated because the previous PM did not recognize their contributions. What can the new PM do to motivate the team?

Question 65mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a team in a country with a high power distance culture. The team members are reluctant to speak up in meetings or challenge the project manager's ideas. How should the project manager foster an inclusive environment?

Question 66hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a Scrum team. The product owner frequently changes priorities mid-sprint, causing the team to lose focus and miss sprint goals. The team is frustrated. What should the project manager do?

Question 67mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is building a new project team. Several team members have never worked together before. The project manager wants to accelerate team development and improve collaboration. Which approach is most effective?

Question 68easymultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that two junior team members are struggling with a new technology required for the project. They are frustrated and their productivity is low. What should the project manager do?

Question 69mediummultiple choice
Read the full NAT/PAT explanation →

A project manager is managing a large infrastructure project. The lead engineer has a strong personality and often dismisses ideas from other team members during meetings, causing some to withdraw from participation. What should the project manager do?

Question 70mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a hybrid project. The team is co-located but the project manager observes that some team members are reluctant to share opposing views during discussions, leading to groupthink. Which TWO actions should the project manager take to foster a culture of constructive debate?

Question 71hardmulti select
Read the full People — Leading Projects explanation →

A project manager is assigned to a troubled project. The team is divided into two factions: one supports a technical solution A, the other solution B. The conflict is causing delays. The project manager wants to resolve this using a collaborative approach. Which THREE actions should the project manager take?

Question 72mediummulti select
Read the full NAT/PAT explanation →

A project manager is leading a global virtual team with members in three different time zones. The project manager wants to improve collaboration and ensure equitable participation. Which TWO actions are most effective?

Question 73easymultiple choice
Read the full People — Leading Projects explanation →

Two senior developers on your project have a heated disagreement about the technical approach for implementing a key feature. They both have strong arguments, and the conflict is delaying the sprint. As the project manager, what is the BEST first step to resolve this conflict?

Question 74mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner requests a significant change to a feature that was just completed. The change would improve user experience but would require reworking two sprints' worth of work. The project is already behind schedule. What should the project manager do first?

Question 75hardmultiple choice
Read the full People — Leading Projects explanation →

Your hybrid project team consists of five local members and three remote members in different time zones. Recently, the remote team members have been missing daily stand-up meetings, and their task completion rate has dropped. When you ask, they say they feel disconnected and their input is often overlooked during the meetings. What should the project manager do FIRST?

Question 76easymultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a construction project. A risk event that was identified in the risk register has just occurred: a key supplier is unable to deliver critical materials on time. The risk response plan includes a contingency reserve. What should you do FIRST?

Question 77mediummultiple choice
Read the full People — Leading Projects explanation →

A team member has been consistently missing deadlines for the past three sprints. Their work quality is also declining. You have had informal conversations with them, but the problem persists. What is the BEST next step for the project manager?

Question 78hardmultiple choice
Read the full People — Leading Projects explanation →

In a large-scale digital transformation project, the executive sponsor has been bypassing you and giving direct instructions to the development team. The team is confused about priorities and feels caught between the sponsor's requests and the project plan. What should the project manager do FIRST?

Question 79mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The project sponsor asks you to reduce costs by cutting the quality assurance phase. As a servant leader, what is the BEST response?

Question 80easymultiple choice
Read the full People — Leading Projects explanation →

A new government regulation has been announced that will affect your project's deliverables. The regulation will take effect in three months, and your project is scheduled to complete in six months. What should the project manager do FIRST?

Question 81mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team's velocity has dropped for three consecutive sprints. The team says they are overwhelmed by the number of user stories and that the definition of 'done' keeps changing. As the Scrum Master (project manager), what should you do FIRST?

Question 82mediummultiple choice
Read the full NAT/PAT explanation →

During a project status meeting, a stakeholder requests a change that would improve the product but significantly impact the critical path. The project manager has not yet evaluated the change. What should the project manager do?

Question 83hardmultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual project team with members in four countries. A team member from one location complains that another team member from a different location is not responding to emails and messages promptly, causing delays. Upon investigation, you find that the second team member feels their work hours are not respected and they are expected to respond outside their working hours. The team charter does not address communication hours. What should the project manager do FIRST?

Question 84mediummultiple choice
Read the full NAT/PAT explanation →

Your project team includes members from diverse cultural backgrounds. During a team meeting, you notice that some members are not speaking up, while others dominate the conversation. The meeting is not productive. What should the project manager do to promote inclusion and improve meeting effectiveness?

Question 85mediummulti select
Read the full People — Leading Projects explanation →

Your project team is co-located, but you have noticed a lack of collaboration and trust among members. Which TWO actions would BEST help build a high-performing team? (Choose two)

Question 86hardmulti select
Read the full People — Leading Projects explanation →

As a project manager in an agile environment, you need to empower the development team to self-organize. Which THREE practices support this goal? (Choose three)

Question 87mediummulti select
Read the full People — Leading Projects explanation →

Your project is in the execution phase and a key vendor has notified you that they will be unable to deliver a critical component on time due to a labor strike. Which TWO actions should the project manager take? (Choose two)

Question 88mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a global software development project with team members in three different time zones. Recently, two senior developers from different locations have been in conflict over the design approach for a critical component. The conflict has started to affect team morale and productivity. What should you do FIRST?

Question 89mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner expresses dissatisfaction with a feature delivered by the team, stating it does not meet the acceptance criteria. The team insists they followed the requirements as written. What should the project manager do FIRST?

Question 90hardmultiple choice
Read the full People — Leading Projects explanation →

Your project uses a hybrid approach with a fixed-price contract. Midway through, the client requests a significant scope change that would increase project duration by two months. The project manager has assessed the impact and believes the change is beneficial. However, the sponsor is reluctant because of the schedule extension. What should the project manager do?

Question 91easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a project where a team member consistently misses deadlines, affecting the team's velocity. You have had informal conversations with the team member, but the behavior continues. What is the BEST next step?

Question 92mediummultiple choice
Read the full People — Leading Projects explanation →

During a risk review meeting, a risk that was identified and registered occurs. The risk response plan is implemented, but it does not fully mitigate the impact, and the project is now behind schedule. What should the project manager do NEXT?

Question 93mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team is distributed across four countries, and you notice that communication is breaking down, leading to misunderstandings and rework. The team members are not using the collaboration tools effectively. What should the project manager do FIRST?

Question 94hardmultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder has been directly contacting your team members and assigning them work that is not in the sprint backlog. The team is feeling pressured and confused about priorities. What should the project manager do?

Question 95easymultiple choice
Read the full NAT/PAT explanation →

Your team has been working together for three months and has started to gel. However, you notice that the team is not openly sharing differing opinions during meetings, and decisions are being made too quickly without considering alternatives. What stage of team development is the team likely in, and what should you do?

Question 96mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile project has seen a consistent drop in velocity over the last three sprints. The team is demotivated and blaming external dependencies. Retrospectives have not yielded actionable improvements. What should the project manager do FIRST?

Question 97easymultiple choice
Read the full People — Leading Projects explanation →

A new regulation is announced that will affect your project's deliverables. The compliance team has determined that the project must adapt to the new regulation before completion. What should the project manager do FIRST?

Question 98hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The variance is due to higher-than-expected costs for raw materials. The sponsor is concerned and wants to know how you will bring the project back on budget. What is the BEST response?

Question 99mediummultiple choice
Read the full NAT/PAT explanation →

A key vendor informs you that they will be unable to deliver a critical component on time due to a production issue. This component is on the critical path. What should the project manager do FIRST?

Question 100mediummulti select
Read the full People — Leading Projects explanation →

Your project team is struggling with collaboration due to cultural and language differences. As project manager, you want to foster a more inclusive and effective team environment. Which TWO actions should you take?

Question 101mediummulti select
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies that low morale is affecting productivity. As a servant leader, which THREE actions should the project manager take to address this?

Question 102hardmulti select
Read the full People — Leading Projects explanation →

Your project is using a hybrid approach. The client has requested a change that would significantly alter the product's core functionality. The change is not aligned with the project's business case. Which TWO actions should the project manager take?

Question 103mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a hybrid project to develop a new mobile app. During the daily stand-up, two senior developers get into a heated argument about the technical approach for integrating a third-party API. The disagreement is causing tension and delaying progress. What should you do FIRST?

Question 104easymultiple choice
Read the full People — Leading Projects explanation →

Your agile team has been working remotely for the past three months. You notice that sprint velocity has dropped significantly over the last two sprints. Team members seem disengaged during daily stand-ups and collaboration has decreased. What should you do FIRST?

Question 105mediummultiple choice
Read the full People — Leading Projects explanation →

In a large-scale project using a predictive approach, you discover that a key team member, who is critical for the next deliverable, has been consistently missing deadlines and producing low-quality work. The project is already behind schedule. What should you do FIRST?

Question 106hardmultiple choice
Read the full People — Leading Projects explanation →

You are leading a globally distributed team with members in three time zones. During a virtual sprint retrospective, team members express frustration that decisions are often made without their input, leading to rework. What is the BEST action to improve team empowerment and collaboration?

Question 107easymultiple choice
Read the full People — Leading Projects explanation →

Your project team includes members from diverse cultural backgrounds. A team member from a high-context culture is perceived by others as not being direct enough, causing misunderstandings. What should you do to improve team cohesion?

Question 108mediummultiple choice
Read the full People — Leading Projects explanation →

During a project status meeting, a sponsor mentions that they have been directly assigning tasks to a team member without going through you. The team member is now confused about priorities. What should you do FIRST?

Question 109hardmultiple choice
Read the full NAT/PAT explanation →

Your agile team has been self-organizing, but recently a team member with strong technical skills has been dominating discussions and decisions, causing others to feel disengaged. The sprint velocity is starting to drop. What is the BEST approach to address this?

Question 110easymultiple choice
Read the full People — Leading Projects explanation →

Your team is about to start a new project. To ensure a common understanding of rules and expectations, you want to create a team charter. When should this be developed?

Question 111mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a construction project using a predictive approach. A key vendor informs you that they will not be able to deliver a critical component for another two weeks, which will delay the project. What should you do FIRST?

Question 112mediummultiple choice
Read the full People — Leading Projects explanation →

In a hybrid project, the product owner wants to add a high-priority feature to the current sprint, but the team has already committed to the sprint backlog. The product owner insists it is critical for the upcoming release. What should the project manager do?

Question 113hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is in the execution phase when a new government regulation is announced that could affect your project's compliance requirements. The regulation is not yet in effect but will be before project completion. What should you do FIRST?

Question 114easymultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, stakeholders express disappointment with the product increment, stating it does not meet their expectations. The team believed they were on track based on the user stories. What should the project manager do to prevent this in the future?

Question 115mediummulti select
Read the full People — Leading Projects explanation →

You are managing a virtual team where several members have expressed feeling isolated and disconnected from the project goals. Which TWO actions would BEST improve team cohesion and alignment?

Question 116hardmulti select
Read the full People — Leading Projects explanation →

Your project team is experiencing conflict due to different working styles: some members prefer detailed plans, while others prefer flexibility. The conflict is affecting morale and productivity. Which THREE actions should you take to resolve the situation?

Question 117mediummulti select
Read the full People — Leading Projects explanation →

As a project manager, you want to motivate your team to achieve high performance. Which TWO techniques are most aligned with PMI's recommended practices for motivating team members?

Question 118mediummultiple choice
Read the full People — Leading Projects explanation →

You are a project manager overseeing a 12-month ERP implementation. During sprint 6 of 20, the product owner informs you that a key stakeholder wants to add a new reporting module that was not in the original scope. The team estimates this would add 3 weeks to the schedule. What should you do FIRST?

Question 119mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a globally distributed team with members in four time zones. During a virtual sprint retrospective, two senior developers accuse each other of not completing tasks on time, causing delays. Emotions are high, and the rest of the team is watching. What should the project manager do FIRST?

Question 120hardmultiple choice
Read the full People — Leading Projects explanation →

In an agile software project, the sprint velocity has dropped from 30 story points to 18 over the last two sprints. The team members report that they are spending too much time on unplanned technical debt. The product owner is pushing for more features. What should the project manager do FIRST?

Question 121easymultiple choice
Read the full People — Leading Projects explanation →

A project team member from a different culture consistently remains silent during daily stand-ups and rarely contributes ideas. Other team members are frustrated because they feel the person is not engaged. What should the project manager do FIRST?

Question 122mediummultiple choice
Read the full People — Leading Projects explanation →

During a large infrastructure project, the sponsor requests that the project manager skip the final round of user acceptance testing (UAT) to meet the regulatory deadline, stating that the system has passed all previous tests. What should the project manager do?

Question 123mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a hybrid project where the team uses Scrum for development but has a fixed end date for regulatory compliance. Halfway through, a key vendor informs you that they will be unable to deliver a critical component on time. What should the project manager do FIRST?

Question 124easymultiple choice
Read the full People — Leading Projects explanation →

A project manager notices that one team member has been consistently missing deadlines, and their work quality is declining. The team member is otherwise talented and has been with the company for years. What should the project manager do FIRST?

Question 125hardmultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder bypasses the project manager and directly assigns tasks to a team member, causing confusion about priorities. The team member is unsure which tasks to work on. What should the project manager do FIRST?

Question 126easymultiple choice
Read the full People — Leading Projects explanation →

A project manager is forming a new virtual team with members from different countries. During the kick-off, the PM wants to build trust and establish norms. Which of the following actions should the PM take FIRST?

Question 127mediummultiple choice
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies that a major risk was not properly mitigated because the contingency plan was not executed on time. The risk event caused a two-week delay. What should the project manager do FIRST?

Question 128mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a cross-functional team that includes members from marketing, engineering, and finance. The team is struggling with collaboration because each department has different priorities and jargon. What should the project manager do to improve team cohesion?

Question 129hardmultiple choice
Read the full People — Leading Projects explanation →

In a Scrum team, the product owner frequently changes priorities within a sprint, causing the team to abandon work mid-task. The team is becoming demotivated. What should the scrum master do?

Question 130mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a distributed team with members in three different countries. The team has been struggling with miscommunication and missed deadlines. The project manager wants to improve team performance. Which TWO actions should the project manager take? (Choose two.)

Question 131hardmulti select
Read the full People — Leading Projects explanation →

A project manager is leading a complex software development project using a hybrid approach. A new regulatory requirement has been discovered that affects the project's scope. The requirement is mandatory and must be implemented before the project can close. Which THREE actions should the project manager take? (Choose three.)

Question 132mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a team that is newly formed and includes members from different functional areas. The team is experiencing low trust and reluctance to share ideas. The project manager wants to build a high-performing team. Which THREE actions should the project manager take? (Choose three.)

Question 133mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using a hybrid approach. Two senior developers, Maria and John, have a disagreement about the technical approach for implementing a critical feature. Their conflict is causing delays and affecting team morale. What should you do first?

Question 134easymultiple choice
Read the full People — Leading Projects explanation →

Your agile team has been experiencing declining velocity over the last three sprints. Retrospectives have not identified a clear cause. Several team members mention feeling fatigued and demotivated. As the project manager, what should you do first?

Question 135hardmultiple choice
Read the full People — Leading Projects explanation →

During a project status meeting, an executive stakeholder interrupts and instructs a team member to change a deliverable without going through change control. The team member looks to you for guidance. What should you do?

Question 136mediummultiple choice
Read the full NAT/PAT explanation →

Your project team is distributed across three time zones. You notice that team members from one location often dominate discussions during daily stand-ups, while others remain silent. As a result, collaboration is suffering. What should you do first?

Question 137easymultiple choice
Read the full People — Leading Projects explanation →

A team member has been consistently missing deadlines, causing delays in dependent tasks. During a one-on-one meeting, you discover they are struggling with a new technology. What is the best course of action?

Question 138hardmultiple choice
Read the full NAT/PAT explanation →

In the middle of a project, a new regulation is introduced that impacts your project's deliverables. The team needs to make adjustments, but the change will affect the critical path. What should you do first?

Question 139mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team has a high turnover rate. New members are joining frequently, and the team's performance is declining. What should you do as a servant leader?

Question 140easymultiple choice
Read the full People — Leading Projects explanation →

Your project team includes members from diverse cultural backgrounds. You notice that some team members are reluctant to share their ideas in group settings due to cultural norms. What is the best approach to foster inclusion?

Question 141hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner rejects a completed user story because it does not meet their expectations, even though it meets the acceptance criteria defined in the sprint planning. The team is frustrated. What should you do?

Question 142mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The sponsor asks you to cut costs by reducing the testing phase. What should you do?

Question 143easymultiple choice
Read the full People — Leading Projects explanation →

A key vendor informs you that they cannot deliver a critical component on time due to a supply chain disruption. This risk was identified and included in the risk register. What should you do first?

Question 144mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a project using a hybrid approach. A team member has been underperforming for several weeks. You have had informal conversations and provided coaching, but there has been no improvement. What should you do next?

Question 145mediummulti select
Read the full People — Leading Projects explanation →

You are leading a virtual team across multiple time zones. Team members report feeling disconnected and communication is becoming less effective. Which TWO actions should you take to improve team cohesion and collaboration?

Question 146hardmulti select
Read the full People — Leading Projects explanation →

Your project team is experiencing conflict between two senior members who have different opinions on the technical approach. The conflict is starting to affect the entire team's morale. Which THREE actions should you take to resolve the conflict effectively?

Question 147easymulti select
Read the full People — Leading Projects explanation →

You are building a new project team for a complex initiative. To set the team up for success, you want to establish a high-performing team environment from the start. Which TWO actions should you take?

Question 148mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using Scrum. During the daily standup, two senior developers engage in a heated argument about the technical approach for a user story. The argument is consuming valuable time and escalating. What should you do FIRST?

Question 149easymultiple choice
Read the full NAT/PAT explanation →

Your project team is distributed across three time zones. A team member from the India office has been consistently delivering tasks late, impacting the critical path. When you discuss this, they mention feeling isolated and unmotivated due to lack of interaction with the rest of the team. What is the BEST action to take?

Question 150hardmultiple choice
Read the full People — Leading Projects explanation →

During a hybrid project, the project sponsor asks you to skip the testing phase in the next release to save time and meet an aggressive market deadline. The team is concerned about quality risks. What should you do FIRST?

Question 151mediummultiple choice
Read the full People — Leading Projects explanation →

Your Agile team's velocity has dropped for the third consecutive sprint. The team cites increasing technical debt and unclear requirements. As a servant leader, what is the BEST course of action?

Question 152easymultiple choice
Read the full People — Leading Projects explanation →

A new regulation impacting your construction project was announced. The compliance team says the project must incorporate additional safety inspections, which will require extra resources and extend the schedule. What should you do FIRST?

Question 153mediummultiple choice
Read the full NAT/PAT explanation →

A key vendor informs you that due to raw material shortages, they cannot deliver a critical component on time. This component is on the critical path. The risk register included this as a high-probability risk with a contingency plan to use an alternative supplier. What should you do FIRST?

Question 154easymultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, a stakeholder expresses dissatisfaction with a deliverable's feature, claiming it does not meet their needs. The product owner disagrees, stating the feature was built exactly as specified. What is the BEST next step?

Question 155hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is 50% complete and 15% over budget. Earned value analysis shows CPI = 0.85 and SPI = 0.95. The team is demoralized due to recent layoffs in the company. An executive suggests reducing the project scope to cut costs. What should you do FIRST?

Question 156mediummultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder has been giving direct instructions to your team members, bypassing you as the project manager. This has caused confusion and conflicting priorities. What is the BEST action to take?

Question 157mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team has members from diverse cultural backgrounds. During a conflict resolution session, you notice that some team members are hesitant to express their opinions due to cultural norms. What is the BEST approach to foster an inclusive environment?

Question 158hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint, you observe that a team member is consistently underperforming, missing tasks, and producing low-quality work. They have been a reliable performer in the past. What should you do FIRST?

Question 159mediummultiple choice
Read the full People — Leading Projects explanation →

Your project uses a hybrid approach. The team has been working remotely for six months, and you notice a decline in collaboration and an increase in misunderstandings. What is the BEST action to improve team cohesion?

Question 160mediummulti select
Read the full People — Leading Projects explanation →

Your project team is struggling with low morale due to a heavy workload and unclear priorities. As a project manager, which TWO actions would BEST help improve team motivation? (Choose two)

Question 161hardmulti select
Read the full People — Leading Projects explanation →

You are managing a large, distributed project using a hybrid methodology. The team is experiencing communication breakdowns and conflict between onshore and offshore members. Which THREE actions should you take to improve team collaboration and performance? (Choose three)

Question 162easymulti select
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies that unclear roles and responsibilities have caused confusion and rework. Which TWO documents or tools would BEST help address this issue? (Choose two)

Question 163mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using Scrum. During the daily stand-up, two senior developers get into a heated argument about the technical approach for a user story. The sprint goal is at risk. What should you do FIRST?

Question 164easymultiple choice
Read the full People — Leading Projects explanation →

A project team is distributed across three time zones. Communication delays are causing misunderstandings and rework. What is the BEST way to improve team collaboration?

Question 165hardmultiple choice
Read the full People — Leading Projects explanation →

Midway through a construction project, a key vendor notifies you that they cannot deliver critical steel beams on time due to a factory fire. This risk was identified and included in the risk register. What should the PM do FIRST?

Question 166mediummultiple choice
Read the full People — Leading Projects explanation →

A team member has been consistently missing deadlines, causing the team to pick up the slack. The PM has had informal conversations, but the behavior persists. What should the PM do NEXT?

Question 167mediummultiple choice
Read the full NAT/PAT explanation →

A project manager is leading a hybrid project. During a sprint review, the product owner requests a significant scope change that would increase the product's value. The change does not affect the project's critical path. What should the PM do?

Question 168easymultiple choice
Read the full NAT/PAT explanation →

A project manager notices that during virtual team meetings, only a few members participate actively while others remain silent. The team is diverse and geographically distributed. What technique should the PM use to encourage participation?

Question 169hardmultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder bypasses the project manager and directly instructs a team member to work on a new feature not in the project scope. The team member is confused. What should the project manager do FIRST?

Question 170mediummultiple choice
Read the full People — Leading Projects explanation →

A project is running 15% over budget at the midpoint. The sponsor is concerned and asks the PM to reduce costs by cutting team training and team-building activities. What should the PM do?

Question 171mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team identifies that communication breakdowns are causing delays. They propose a new collaboration tool. The project manager supports the idea but it requires additional budget. What should the PM do FIRST?

Question 172easymultiple choice
Read the full People — Leading Projects explanation →

A new team member joins a high-performing agile team. The existing team members are concerned that the new member's pace is slower. What should the project manager do to integrate the new member effectively?

Question 173hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager discovers that a team member has been taking credit for another teammate's work during stakeholder meetings. This has created tension within the team. What should the PM do?

Question 174mediummultiple choice
Read the full People — Leading Projects explanation →

A project team is composed of members from diverse cultural backgrounds. The PM notices that some team members are not voicing their opinions in meetings due to cultural norms. What is the BEST approach to foster inclusion?

Question 175mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a virtual team that has never worked together. To build a high-performing team, which TWO actions should the PM take? (Choose two)

Question 176hardmulti select
Read the full People — Leading Projects explanation →

A project manager is leading a software development project in an organization that uses a hybrid methodology. The team's sprint velocity has dropped for three consecutive sprints. Which THREE actions should the PM take to address this? (Choose three)

Question 177mediummulti select
Read the full People — Leading Projects explanation →

A new regulatory requirement has been discovered mid-project. The change will affect the project scope and schedule. Which TWO actions should the project manager take FIRST? (Choose two)

Question 178mediummultiple choice
Read the full People — Leading Projects explanation →

You are a project manager on a software development project using a hybrid approach. Two senior developers have a strong disagreement on the technical implementation of a critical feature. They have been arguing for three days, causing the team to fall behind schedule. What should you do first?

Question 179easymultiple choice
Read the full People — Leading Projects explanation →

Your project team is spread across three continents. You notice that the daily stand-ups are becoming less interactive, and team members are not raising blockers. What should you do first to improve team collaboration?

Question 180hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, several team members express frustration that the project manager often overrides their decisions, contradicting the agile principle of self-organization. The project manager believes the team lacks experience and needs guidance. What should the project manager do?

Question 181mediummultiple choice
Read the full People — Leading Projects explanation →

A key stakeholder insists on bypassing the change control process and demands that a minor scope change be implemented immediately to meet a regulatory deadline. What should the project manager do?

Question 182easymultiple choice
Read the full People — Leading Projects explanation →

Your project team is newly formed, and you notice that members are hesitant to share ideas during meetings. To build a high-performing team, what should you do first?

Question 183hardmultiple choice
Read the full NAT/PAT explanation →

A project is in execution phase, and a team member consistently misses deadlines, impacting the critical path. The project manager has had informal conversations, but the behavior continues. What should the project manager do next?

Question 184mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner expresses dissatisfaction with the feature delivered, stating it does not meet the acceptance criteria. The team disagrees, claiming it meets the definition of done. What should the project manager do first?

Question 185mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a virtual team where members are in different time zones. Some team members feel left out of decision-making because meetings are scheduled at times convenient for the majority. What should you do?

Question 186hardmultiple choice
Read the full People — Leading Projects explanation →

The project sponsor asks you to skip the quality testing phase to meet an aggressive deadline, arguing that the team is experienced and can deliver without it. What should you do?

Question 187easymultiple choice
Read the full People — Leading Projects explanation →

A new team member joins your agile project. They have no experience with Scrum and seem overwhelmed. What should you do to onboard them effectively?

Question 188mediummultiple choice
Read the full People — Leading Projects explanation →

During a project, you discover that a team member is being excluded from social interactions by others because of cultural differences. The team member has not complained, but you sense low morale. What should you do?

Question 189mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The team is motivated, but the sponsor is concerned. What should you do first?

Question 190mediummulti select
Read the full People — Leading Projects explanation →

Your project team is experiencing low sprint velocity for three consecutive sprints. The team cites unclear requirements and frequent interruptions. Which TWO actions should you take to address this?

Question 191hardmulti select
Read the full People — Leading Projects explanation →

A key vendor informs you that they cannot deliver a critical component on time, which will delay the project. You need to decide on next steps. Which THREE actions are most appropriate?

Question 192hardmulti select
Read the full People — Leading Projects explanation →

You are leading a distributed agile team. Team members have expressed that they feel disconnected and unclear about project goals. Which THREE actions should you take to improve team cohesion and alignment?

Question 193mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a software development project using a hybrid approach. During a sprint review, two senior developers get into a heated argument about the technical design of a feature. The argument is causing tension and delaying the review. What should you do first?

Question 194easymultiple choice
Read the full NAT/PAT explanation →

You are leading a globally distributed agile team. During the daily stand-up, you notice that the team member in India consistently speaks little compared to others, while the US-based members dominate the conversation. What should you do to foster inclusion?

Question 195hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The sponsor asks you to skip the testing phase in the next sprint to save costs. The project follows a hybrid approach with both predictive and agile elements. What should you do?

Question 196mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a construction project. A key vendor notifies you that they cannot deliver a critical component on time, which will delay the project by at least two weeks. The vendor was already on the risk register with a contingency plan. What should you do first?

Question 197easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a project using a predictive approach. A team member has been consistently missing deadlines, causing delays for the rest of the team. You have already had an informal conversation about expectations. What should you do next?

Question 198hardmultiple choice
Read the full People — Leading Projects explanation →

You are leading a distributed Scrum team. The product owner consistently interrupts the development team during sprints with new requirements, causing scope creep and reduced velocity. The team is frustrated. What should you do?

Question 199mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team is co-located, but you notice that collaboration has decreased recently. Team members are working in silos, and communication is minimal. You suspect the team is not functioning as a high-performing team. What should you do first?

Question 200easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a project where a key executive stakeholder bypasses you and gives direct orders to the development team. The team is confused about priorities. What should you do first?

Question 201mediummultiple choice
Read the full People — Leading Projects explanation →

In an agile project, the sprint velocity has been dropping for three consecutive sprints. The team is demotivated and blaming each other during retrospectives. What should you do as the project manager?

Question 202mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team includes members from different cultural backgrounds. You notice that some team members are uncomfortable challenging ideas during meetings, which you attribute to cultural norms. How can you best promote a culture of open communication?

Question 203hardmultiple choice
Read the full People — Leading Projects explanation →

You are managing a project that is on schedule and under budget. A key stakeholder requests a significant scope change that would improve the product's value but also extend the schedule by 20%. The change has not been through change control. What should you do?

Question 204mediummultiple choice
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies several obstacles that are slowing them down, including unclear requirements and lack of access to a testing environment. As a servant leader, what should you do?

Question 205mediummulti select
Read the full People — Leading Projects explanation →

Your agile project team is experiencing conflicts between two developers regarding coding standards. The conflict is affecting team morale and productivity. As the project manager, which TWO actions should you take?

Question 206hardmulti select
Read the full People — Leading Projects explanation →

Your project is in the execution phase when a new regulatory requirement is discovered that impacts the project scope. The change is mandatory and must be implemented immediately. Which THREE actions should you take?

Question 207mediummulti select
Read the full People — Leading Projects explanation →

You are leading a virtual team across three time zones. Team members have expressed feeling isolated and disconnected. Which THREE actions would best improve team cohesion and collaboration?

Question 208mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a software development project using a hybrid approach. During a sprint review, two senior developers have a heated argument about the technical implementation of a feature. The disagreement is causing tension among the team. What should you do FIRST?

Question 209easymultiple choice
Read the full People — Leading Projects explanation →

You manage a global project team with members in three different time zones. Several team members have expressed feeling isolated and disconnected from the project. Communication has become sporadic. What is the BEST way to address this?

Question 210hardmultiple choice
Read the full People — Leading Projects explanation →

During a project to develop a new mobile app, a key team member has been consistently underperforming, missing deadlines, and delivering low-quality work. The team is becoming demotivated. You have had informal conversations with the team member, but performance has not improved. What should you do NEXT?

Question 211mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a construction project using a traditional approach. The sponsor asks you to skip the quality inspection phase to save two weeks and meet an aggressive deadline. What should you do FIRST?

Question 212mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team's velocity has dropped for the past three sprints. During the retrospective, team members mention they are overburdened with work from other departments. The project manager is not the team's direct manager. What should you do FIRST?

Question 213easymultiple choice
Read the full People — Leading Projects explanation →

A new regulatory requirement has been discovered that affects your project's deliverables. The project is halfway through its schedule. What should the project manager do FIRST?

Question 214mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a large project with multiple stakeholders. One executive stakeholder has been bypassing you and giving direct instructions to the team, causing confusion. What should you do FIRST?

Question 215hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The variance is due to unforeseen technical challenges. You have identified a potential solution that would reduce costs but might affect scope. What should you do FIRST?

Question 216mediummultiple choice
Read the full People — Leading Projects explanation →

In a Scrum project, the product owner wants to add a new high-priority story to the current sprint, but the sprint is already full. The team is concerned about overcommitment. What should the Scrum Master do?

Question 217easymultiple choice
Read the full People — Leading Projects explanation →

You are forming a new project team with members from different departments. To ensure a shared understanding of team values and expectations, what should you do FIRST?

Question 218mediummultiple choice
Read the full People — Leading Projects explanation →

A risk that was identified and in the risk register has occurred. The risk response plan involves outsourcing a component, but the vendor is now unable to deliver on time. What should the project manager do FIRST?

Question 219hardmultiple choice
Read the full NAT/PAT explanation →

Your agile team is distributed across four countries. During the daily stand-up, some team members are not speaking, and others dominate the conversation. The project manager wants to improve collaboration. What is the BEST approach?

Question 220mediummulti select
Read the full People — Leading Projects explanation →

You are leading a project to develop a new product. The marketing department requests a last-minute change that would increase the project's scope significantly. The project is on track and within budget. Which TWO actions should the project manager take?

Question 221hardmulti select
Read the full People — Leading Projects explanation →

Your project team is experiencing low morale due to unclear roles and responsibilities. As a project manager using a servant leadership approach, which THREE actions would BEST address this issue?

Question 222mediummulti select
Read the full People — Leading Projects explanation →

Your project is using a hybrid approach. The development team has completed the deliverables, but the testing team is overwhelmed and behind schedule. The project manager needs to address this resource constraint. Which THREE actions are most appropriate?

Question 223mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a software development project using a hybrid approach. Two senior developers have a recurring conflict about coding standards, which is causing delays in code reviews and affecting team morale. What should you do FIRST?

Question 224hardmultiple choice
Read the full People — Leading Projects explanation →

Your project team is distributed across three time zones. You notice that the daily stand-up meetings are poorly attended, and team members complain about meeting fatigue. What is the BEST way to address this situation?

Question 225easymultiple choice
Read the full People — Leading Projects explanation →

A junior team member consistently misses deadlines, affecting the project schedule. You have spoken to them twice about the issue, but performance has not improved. What should you do NEXT?

Question 226mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team expresses frustration that they are frequently interrupted by unplanned support requests from the operations department. The product owner agrees this is impacting velocity. What should the project manager do FIRST?

Question 227mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team that includes members from different cultural backgrounds. Several team members have expressed that they feel left out of decision-making because most discussions happen in the project manager's time zone. What is the BEST action to foster inclusion?

Question 228hardmultiple choice
Read the full People — Leading Projects explanation →

A key stakeholder has been bypassing the project manager and giving direct instructions to team members, causing confusion about priorities. What should the project manager do FIRST?

Question 229easymultiple choice
Read the full People — Leading Projects explanation →

During a project, you notice that a team member with specialized skills is becoming demotivated because their work is not being recognized. What is the BEST way to address this?

Question 230mediummultiple choice
Read the full People — Leading Projects explanation →

A team member has informed you that they are feeling burnt out due to the high pace of the project. The project is on schedule and within budget. What should the project manager do?

Question 231mediummultiple choice
Read the full People — Leading Projects explanation →

In a Scrum team, the product owner frequently changes priorities during the sprint, causing the team to lose focus. The team has raised this concern in the retrospective. What should the scrum master do?

Question 232hardmultiple choice
Read the full People — Leading Projects explanation →

Your project is in the execution phase when a new regulation is passed that affects the project's deliverables. The team is already working at full capacity. What should the project manager do FIRST?

Question 233mediummultiple choice
Read the full People — Leading Projects explanation →

A project team has low trust and poor collaboration. The project manager wants to build a high-performing team. Which of the following is the MOST effective first step?

Question 234easymultiple choice
Read the full People — Leading Projects explanation →

During a project, the sponsor asks you to skip the testing phase to save time and meet the deadline. What should you do FIRST?

Question 235mediummulti select
Read the full People — Leading Projects explanation →

Your project team is experiencing a conflict between two members that is affecting the entire team's productivity. As the project manager, which TWO actions should you take to resolve the situation?

Question 236hardmulti select
Read the full People — Leading Projects explanation →

Your agile team's velocity has been declining for the past three sprints. The team cites increasing technical debt and unclear requirements. As the project manager, which THREE actions should you take to address this?

Question 237mediummulti select
Read the full People — Leading Projects explanation →

A project team member from a different cultural background tends to avoid direct confrontation during disagreements, which frustrates other team members who prefer direct communication. As the project manager, which TWO actions should you take to improve team dynamics?

Question 238mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a hybrid project team consisting of both colocated and remote members. During a daily stand-up, two senior developers have a heated argument about the technical approach for a critical feature. The argument disrupts the meeting and creates tension. What should you do first?

Question 239hardmultiple choice
Read the full People — Leading Projects explanation →

Your agile team has been consistently delivering high-quality increments, but the product owner recently started bypassing you and giving direct instructions to the development team. The team is confused and some have started working on unapproved features. What should you do first?

Question 240easymultiple choice
Read the full People — Leading Projects explanation →

A new team member from a different cultural background joins your global project team. Some team members are struggling to adapt to his communication style, and misunderstandings are increasing. As the project manager, what should you do first?

Question 241mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner rejects a user story because it does not meet the acceptance criteria. The developer who worked on it becomes defensive and argues that the implementation is technically superior to what was requested. What should the project manager do?

Question 242hardmultiple choice
Read the full People — Leading Projects explanation →

You are managing a large-scale project with multiple vendors. One vendor is consistently late in delivering critical components, jeopardizing the project schedule. The vendor blames the delays on your team's incomplete specifications. What should you do first?

Question 243mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team's velocity has dropped for the third consecutive sprint. The team members report feeling burned out and demotivated due to excessive overtime. What should the project manager do first?

Question 244mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a project in a virtual environment. A team member from a different time zone misses an important deadline because he was not aware of the priority due to a language barrier. What should you do first?

Question 245easymultiple choice
Read the full People — Leading Projects explanation →

During a project status meeting, you notice that one team member consistently interrupts others and dismisses their ideas. This behavior is affecting team morale and collaboration. What should you do first?

Question 246mediummultiple choice
Read the full NAT/PAT explanation →

Your project is using a hybrid approach. A key stakeholder requests a significant scope change that would affect the critical path. The change request has been submitted and approved. What should the project manager do next?

Question 247hardmultiple choice
Read the full People — Leading Projects explanation →

You are managing a project where the sponsor has asked the team to skip testing to save time. The team is against it because they believe it will compromise quality. What should the project manager do?

Question 248easymultiple choice
Read the full People — Leading Projects explanation →

A project team member has been underperforming for several weeks. You have had informal conversations with them, but performance has not improved. What should you do next?

Question 249mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The team is working well, but the variance is due to inaccurate cost estimates. What should the project manager do first?

Question 250mediummulti select
Read the full People — Leading Projects explanation →

You are leading a virtual team across three continents. Team members have expressed feeling isolated and disconnected from the project. Which TWO actions would best help build team cohesion and trust?

Question 251hardmulti select
Read the full People — Leading Projects explanation →

A conflict has arisen between two functional managers whose teams are working on your project. They disagree on resource allocation and priorities, and the conflict is delaying progress. Which THREE actions should the project manager take to resolve the situation?

Question 252mediummulti select
Read the full NAT/PAT explanation →

Your project team includes members from diverse cultural backgrounds. You notice that some team members are hesitant to speak up during meetings due to cultural norms about hierarchy. Which TWO approaches would best promote inclusive participation?

Question 253mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a software development project using a hybrid approach. Two senior developers have a technical disagreement that has escalated into a personal conflict, causing delays. What should you do FIRST?

Question 254easymultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team across multiple time zones. During daily stand-ups, you notice that team members from one region are consistently quiet and not contributing. What should you do FIRST?

Question 255mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team expresses frustration that they are frequently interrupted by ad-hoc requests from stakeholders. Scrum Master role you are also the PM. What should you do FIRST?

Question 256hardmultiple choice
Read the full People — Leading Projects explanation →

A team member has been consistently underperforming, missing deadlines, and delivering low-quality work. You have had informal conversations but no improvement. What should you do NEXT?

Question 257mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is halfway through its planned 18-month schedule. The sponsor has asked you to skip the final testing phase to meet a regulatory deadline, citing that the team is experienced and testing is unnecessary. What should you do FIRST?

Question 258mediummultiple choice
Read the full NAT/PAT explanation →

You are managing a project using a predictive approach. A key vendor informs you that they will be unable to deliver a critical component on time, which will impact the critical path. What should you do FIRST?

Question 259easymultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a team that recently transitioned to remote work. You notice that team morale is declining and collaboration has decreased. What is the BEST action to improve team cohesion?

Question 260hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner rejects a user story because it does not meet their expectations, even though the team followed the acceptance criteria. The team is frustrated. What should you do FIRST?

Question 261mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team includes members from diverse cultural backgrounds. During a meeting, you notice that some team members are uncomfortable with the direct communication style of others. How should you address this?

Question 262easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a project where the team has been working overtime for several weeks to meet a milestone. The milestone is achieved, but the team is exhausted. What should you do to sustain the team's performance?

Question 263mediummultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder has been bypassing you and giving direct instructions to your team, causing confusion and scope creep. What should you do FIRST?

Question 264hardmultiple choice
Read the full People — Leading Projects explanation →

Your agile project has seen sprint velocity drop for the past three sprints. The team attributes it to increasing technical debt. As the project manager, what should you do FIRST?

Question 265mediummulti select
Read the full People — Leading Projects explanation →

You are the project manager for a large infrastructure project. Two key stakeholders have conflicting requirements that cannot both be satisfied within the current budget. Which TWO actions should you take to resolve this conflict?

Question 266hardmulti select
Read the full People — Leading Projects explanation →

A new regulatory requirement has been discovered mid-project. This requirement will affect the project scope and schedule. Which THREE actions should you take?

Question 267mediummulti select
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The sponsor asks you to reduce costs by cutting team training. Which TWO actions should you take?

Question 268mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a hybrid project with a critical deliverable due in two weeks. Two senior developers on your team have a strong disagreement over the technical approach. They have stopped speaking to each other, and the team's progress has stalled. What should you do FIRST?

Question 269easymultiple choice
Read the full People — Leading Projects explanation →

Your agile team has been working together for three months, and you notice that sprint velocity has been steadily declining. During the retrospective, team members mention they feel overworked and unclear about priorities. What is the BEST action to take?

Question 270hardmultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team across three time zones. During a video conference, you notice that one team member from the Asia-Pacific region has not spoken for the entire meeting. After the meeting, they email you saying they felt unheard and that their ideas were dismissed by a dominant team member from the US. What should you do FIRST?

Question 271mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The sponsor asks you to reduce costs by cutting the testing phase from three weeks to one week. What should you do FIRST?

Question 272easymultiple choice
Read the full People — Leading Projects explanation →

A new team member from a different cultural background joins your project. They seem hesitant to share opinions during meetings and prefer written communication. Some team members perceive this as disengagement. As the project manager, what is the BEST approach?

Question 273mediummultiple choice
Read the full People — Leading Projects explanation →

During a sprint review, the product owner rejects a user story because it does not meet the acceptance criteria. The developer who completed the story argues that the functionality is sufficient and that the criteria were too strict. Both parties escalate to you. What should you do FIRST?

Question 274mediummultiple choice
Read the full People — Leading Projects explanation →

Your project team has been working remotely for the past six months. You notice that collaboration has decreased, and team members seem isolated. What is the BEST action to improve team cohesion?

Question 275hardmultiple choice
Read the full People — Leading Projects explanation →

You are managing a large project with multiple vendors. One vendor has delivered a critical component two weeks late, jeopardizing the project schedule. The vendor claims that the delay was caused by unclear specifications from your team. Your team insists the specifications were clear. What should you do FIRST?

Question 276easymultiple choice
Read the full NAT/PAT explanation →

A team member consistently misses deadlines, causing delays for the rest of the team. When you discuss this with them, they cite personal issues but assure you they will improve. However, the pattern continues. What is the BEST next step?

Question 277mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team has a low-performing member who is struggling with the technology stack. The rest of the team is becoming frustrated because they have to cover for them. What is the BEST approach to handle this situation?

Question 278hardmultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder bypasses you and gives direct instructions to a team member to add a new feature immediately. The team member is confused and asks you what to do. What should you do FIRST?

Question 279mediummultiple choice
Read the full People — Leading Projects explanation →

During a project, a new regulation is introduced that affects your project's compliance requirements. The team will need to complete additional documentation and training. What is the FIRST thing you should do?

Question 280mediummulti select
Read the full People — Leading Projects explanation →

You are the project manager for a global team with members from different cultures. You want to build a high-performing team. Which TWO actions are MOST effective for fostering collaboration and trust?

Question 281hardmulti select
Read the full People — Leading Projects explanation →

Your project is in the execution phase when a key risk event from the risk register occurs: a critical team member resigns unexpectedly. You need to minimize the impact on the project. Which THREE actions should you take?

Question 282mediummulti select
Read the full People — Leading Projects explanation →

Your agile team has been experiencing a decline in sprint velocity over the past three sprints. During the retrospective, the team identifies unclear requirements and frequent interruptions as root causes. Which TWO actions should you take to address these issues?

Question 283mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a hybrid software development project. During a sprint review, two senior developers get into a heated argument about the technical approach for a critical feature. The argument is delaying the review and making other team members uncomfortable. What should you do FIRST?

Question 284easymultiple choice
Read the full People — Leading Projects explanation →

Your agile project team has been consistently delivering high-quality work, but sprint velocity has dropped over the last three sprints. The team reports feeling overworked and demotivated. What should you do FIRST?

Question 285hardmultiple choice
Read the full NAT/PAT explanation →

You are managing a global project with team members in three time zones. A key team member from the India office has been consistently missing deadlines, impacting the project's critical path. In a one-on-one meeting, you discover she is struggling with the work-from-home setup and lack of collaboration tools. What should you do FIRST?

Question 286mediummultiple choice
Read the full People — Leading Projects explanation →

During a project status meeting, an executive stakeholder bypasses you and directly instructs a team member to add a new feature to the current sprint. The team member looks confused. What should you do FIRST?

Question 287easymultiple choice
Read the full People — Leading Projects explanation →

Your agile team has recently formed and is struggling to agree on work methods and communication norms. Several team members are frustrated with the lack of consistency. What should you do as the project manager?

Question 288mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is halfway through its timeline and is running 15% over budget due to unexpected vendor price increases. The sponsor is concerned and asks you to cut costs by reducing the number of quality tests. What should you do?

Question 289mediummultiple choice
Read the full NAT/PAT explanation →

A key vendor informs you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The risk was identified and documented in the risk register. What should you do FIRST?

Question 290easymultiple choice
Read the full NAT/PAT explanation →

Your project team includes members from diverse cultural backgrounds. You notice that some team members are not contributing ideas during brainstorming sessions, while others dominate the conversation. What should you do to promote inclusion?

Question 291hardmultiple choice
Read the full People — Leading Projects explanation →

During a sprint planning meeting, the product owner proposes a user story that the team believes is too vague and lacks clear acceptance criteria. The product owner insists it must be included in the sprint to meet a stakeholder deadline. What should the scrum master do?

Question 292mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is in the execution phase, and a new regulatory requirement has been discovered that will affect the project scope. The change is mandatory and must be implemented within two weeks. What should you do FIRST?

Question 293mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a distributed team with members in different time zones. A team member complains that they feel isolated and uninformed about project decisions. What should you do FIRST to address this?

Question 294hardmultiple choice
Read the full People — Leading Projects explanation →

During a retrospective, the team identifies that the root cause of low morale is the project manager's micromanagement style. The team wants more autonomy. What should the PM do?

Question 295mediummulti select
Read the full People — Leading Projects explanation →

Your agile team has been experiencing conflict between two developers over coding standards. The conflict is affecting team morale and productivity. Which TWO actions should you take to resolve the conflict? (Choose TWO)

Question 296hardmulti select
Read the full People — Leading Projects explanation →

Your project is in the planning phase, and you are building a virtual team across five countries. Which THREE factors are most important to address to ensure high team performance? (Choose THREE)

Question 297easymulti select
Read the full People — Leading Projects explanation →

A new team member has joined your project and seems reluctant to share ideas during meetings. You suspect they are experiencing cultural adjustment issues. Which TWO actions would best help integrate them into the team? (Choose TWO)

Question 298easymultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using a hybrid approach. Two senior developers have a heated disagreement about the best technical solution for a critical feature. The disagreement is causing delays and affecting team morale. What should you do first?

Question 299easymultiple choice
Read the full People — Leading Projects explanation →

During the execution phase of a construction project, you notice that a junior team member is consistently missing deadlines and producing work of lower quality. Other team members have expressed frustration. What is the best approach to address this?

Question 300easymultiple choice
Read the full People — Leading Projects explanation →

You are managing a distributed team across three time zones. A team member from the Asia office reports that they feel excluded from decision-making because key meetings are held during their late evening hours. What should you do first?

Question 301mediummultiple choice
Read the full People — Leading Projects explanation →

Your agile team's velocity has dropped for three consecutive sprints. Upon investigation, you discover that the product owner has been adding unplanned work directly to the sprint backlog without consulting you or the team. What is the most appropriate action?

Question 302mediummultiple choice
Read the full People — Leading Projects explanation →

During a project status meeting, the sponsor asks you to skip the final round of testing to meet the original deadline, stating that the product is already 'good enough.' What is your best response?

Question 303mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team using a hybrid methodology. A team member from another country consistently arrives late to daily stand-ups, disrupting the flow. The team member has not responded to private messages about the issue. What should you do next?

Question 304mediummultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. Upon review, you find that the cost overrun is due to an underestimation of hardware costs. The sponsor is concerned and asks for a plan to get back on track. What should you do first?

Question 305mediummultiple choice
Read the full People — Leading Projects explanation →

An executive stakeholder has been directly assigning tasks to your agile team members without going through you or the product owner. Team members are confused about priorities and the sprint goal is at risk. What is the best first step?

Question 306mediummultiple choice
Read the full NAT/PAT explanation →

A key vendor has informed you that they cannot deliver a critical component for another two weeks, which will delay your project. The component is on the critical path. What should you do first?

Question 307hardmultiple choice
Read the full People — Leading Projects explanation →

You are the project manager on a large infrastructure project. During execution, a new government regulation is announced that will affect your project's compliance requirements. The change is mandatory and must be implemented within 60 days, or the project will be shut down. What should you do first?

Question 308hardmultiple choice
Read the full People — Leading Projects explanation →

Your agile team has been self-organizing and performing well, but during the last two retrospectives, the team has raised concerns about the product owner not providing clear acceptance criteria for user stories. As the project manager, what is the most effective way to address this?

Question 309hardmultiple choice
Read the full People — Leading Projects explanation →

You are managing a project using a predictive approach. A key team member has expressed that they feel micromanaged by you and wants more autonomy. The team member's performance is satisfactory. How should you respond?

Question 310mediummulti select
Read the full NAT/PAT explanation →

You are the project manager for a multinational project with team members from diverse cultural backgrounds. You notice that some team members are hesitant to speak up during meetings due to cultural norms. Which TWO actions would best foster an inclusive environment?

Question 311mediummulti select
Read the full People — Leading Projects explanation →

Your agile team has been struggling with low morale and lack of motivation. As a project manager using servant leadership, which THREE actions would be most effective in improving the situation?

Question 312hardmulti select
Read the full People — Leading Projects explanation →

Your project team is distributed across four countries with significant time zone differences. Communication has been challenging, leading to misunderstandings and delays. Which THREE actions would most effectively improve collaboration?

Question 313mediummultiple choice
Read the full People — Leading Projects explanation →

You are the project manager for a software development project using a hybrid approach. Two senior developers have a disagreement about the technical approach for a critical feature. The conflict is causing delays and affecting team morale. What should you do first?

Question 314easymultiple choice
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team expresses frustration that they are frequently interrupted by unplanned work from other departments. The project manager wants to improve team focus. What should the project manager do?

Question 315mediummultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a virtual team across four time zones. The project has entered the execution phase, and the project manager notices that team members are not collaborating effectively, and communication is becoming fragmented. What should the project manager do first?

Question 316hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a large construction project. The sponsor requests that the team skip a mandatory quality inspection to save two weeks on the schedule. The project manager knows that skipping the inspection could compromise safety and violate regulations. What should the project manager do?

Question 317easymultiple choice
Read the full People — Leading Projects explanation →

A project manager is forming a new project team. To build a high-performing team, the project manager wants to establish clear expectations for behavior and communication. What should the project manager do?

Question 318mediummultiple choice
Read the full People — Leading Projects explanation →

During a project, a key team member consistently misses deadlines, causing delays. The project manager has had informal conversations with the team member, but the situation has not improved. What should the project manager do next?

Question 319hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a global team with diverse cultural backgrounds. Two team members from different cultures have a misunderstanding that is causing tension. The project manager wants to promote inclusivity and resolve the issue. What should the project manager do?

Question 320easymultiple choice
Read the full People — Leading Projects explanation →

A project manager is using a servant leadership approach. During a sprint, the team is struggling to complete their tasks due to unclear requirements. What should the project manager do?

Question 321mediummultiple choice
Read the full People — Leading Projects explanation →

You are a project manager for a marketing campaign project. A team member has proposed a new approach that could improve the campaign's effectiveness but would require additional budget and extend the timeline. What should you do?

Question 322hardmultiple choice
Read the full People — Leading Projects explanation →

A project manager discovers that a team member has been working overtime for weeks to meet a deadline. The team member appears stressed and burnt out. The project manager is concerned about the team member's well-being and the sustainability of the project. What should the project manager do?

Question 323mediummultiple choice
Read the full People — Leading Projects explanation →

In a large-scale project, the project manager notices that sprint velocity has been declining over the last three sprints. The team is demotivated and blaming each other for missed commitments. What should the project manager do first?

Question 324easymultiple choice
Read the full People — Leading Projects explanation →

A project manager is leading a team that includes members from different departments. One team member frequently misses team meetings and fails to update task status. What should the project manager do?

Question 325mediummulti select
Read the full People — Leading Projects explanation →

A project manager is leading a hybrid project. The team has members in three countries, and communication has been challenging. The project manager wants to improve collaboration and build trust among remote team members. Which TWO actions should the project manager take?

Question 326mediummulti select
Read the full People — Leading Projects explanation →

During project execution, the project manager notices that two team members are in frequent conflict, which is affecting the team's overall performance. The project manager wants to resolve the conflict effectively. Which THREE actions align with PMI's recommended approach?

Question 327hardmulti select
Read the full People — Leading Projects explanation →

A project manager is leading an agile team that has been self-organizing for several sprints. Recently, the team's performance has declined, and the project manager suspects the team is not fully empowered to make decisions. The project manager wants to empower the team. Which TWO actions should the project manager take?

Question 328mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a hybrid software development project. During the daily stand-up, two senior developers get into a heated argument about the best technical approach for a critical feature. The argument is delaying the meeting and causing tension. As the project manager, what should you do first?

Question 329easymultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team across three time zones. A team member from the offshore location has been consistently missing deadlines, causing delays. When you inquire, the member says they are overloaded with work from another project. What is the best course of action?

Question 330hardmultiple choice
Read the full People — Leading Projects explanation →

Your agile project is in its third sprint. The product owner has been pressuring the team to deliver more features each sprint to meet stakeholder expectations. Sprint velocity has dropped for two consecutive sprints, and the team seems demotivated. As the project manager, what should you do?

Question 331mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a project to develop a mobile app. The sponsor asks you to skip user acceptance testing (UAT) to meet an aggressive launch date. The team is concerned about quality risks. What should you do?

Question 332mediummultiple choice
Read the full People — Leading Projects explanation →

A risk event that was identified and included in the risk register has occurred. The impact on the project schedule is moderate. What should the project manager do first?

Question 333easymultiple choice
Read the full NAT/PAT explanation →

Your project team includes members from diverse cultural backgrounds. During a meeting, you notice that some team members are not contributing ideas, while others dominate the discussion. What should you do to foster inclusive participation?

Question 334hardmultiple choice
Read the full People — Leading Projects explanation →

During a hybrid project, an executive stakeholder bypasses you and directly instructs a team member to add a new feature. The team member is now confused about priorities. What should you do first?

Question 335mediummultiple choice
Read the full People — Leading Projects explanation →

You are leading a Scrum team. For the past three sprints, the team has consistently completed all committed user stories. The product owner wants to increase the team's velocity by 20%. What should you do?

Question 336mediummultiple choice
Read the full NAT/PAT explanation →

A key vendor has notified you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the project's critical path. What should you do first?

Question 337easymultiple choice
Read the full People — Leading Projects explanation →

Your project is running 15% over budget at the midpoint. The cost variance is due to higher-than-expected material costs. What should you do?

Question 338mediummultiple choice
Read the full People — Leading Projects explanation →

A new government regulation has been enacted that affects your project's deliverables. The regulation requires additional compliance checks that were not in the original scope. What should you do first?

Question 339hardmultiple choice
Read the full People — Leading Projects explanation →

On a large-scale project, you have a team member who is technically skilled but consistently fails to complete tasks on time, affecting the team's morale. You have had informal conversations about this, but there has been no improvement. What should you do next?

Question 340mediummulti select
Read the full People — Leading Projects explanation →

You are managing a global virtual team. Team members have reported feeling isolated and disconnected from the project's goals. Which TWO actions would best help improve team cohesion and engagement?

Question 341hardmulti select
Read the full People — Leading Projects explanation →

During a project retrospective, the team identifies that their velocity has plateaued due to excessive context switching and unclear priorities. Which THREE actions should the project manager take to address these issues?

Question 342mediummulti select
Read the full People — Leading Projects explanation →

You are transitioning a traditional project team to an agile framework. Some team members are resistant to the change. Which THREE strategies should you employ to facilitate the transition?

Question 343mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a hybrid project using Scrum for development and a predictive approach for regulatory deliverables. During the daily standup, two senior developers disagree strongly on the technical approach to implement a user story. The disagreement is causing tension and slowing progress. As the project manager, what should you do FIRST?

Question 344hardmultiple choice
Read the full NAT/PAT explanation →

Your project is in execution phase, and a key vendor informs you that they will be unable to deliver a critical component on time due to a supply chain disruption. This risk was identified in the risk register and a contingency plan was developed. The project timeline is tight, and any delay will impact the critical path. What should you do FIRST?

Question 345easymultiple choice
Read the full People — Leading Projects explanation →

You are leading a virtual team across three time zones. During a video conference, you notice that one team member from a remote location has not spoken for the entire meeting. In previous meetings, this team member has also been quiet. What should you do to ensure effective collaboration?

Question 346mediummultiple choice
Read the full People — Leading Projects explanation →

In a Scrum project, the team's velocity has been dropping over the last three sprints. The team members seem demotivated and are complaining about too many meetings and unclear priorities. As the agile project manager, what should you do FIRST?

Question 347mediummultiple choice
Read the full People — Leading Projects explanation →

You are managing a project where an executive stakeholder has been bypassing you and directly giving instructions to the team members. This has caused confusion and rework. What should you do FIRST?

Question 348easymultiple choice
Read the full People — Leading Projects explanation →

A new team member joins your project and is struggling to understand the technical domain and the team's culture. Their productivity is low, and they seem hesitant to ask questions. As project manager, what is the BEST way to support this team member?

Question 349hardmultiple choice
Read the full People — Leading Projects explanation →

Your predictive project is halfway through execution. A team member has been consistently missing deadlines, and their work quality is declining. You suspect personal issues but are unsure. The project is at risk of schedule delays. What should you do FIRST?

Question 350mediummulti select
Read the full People — Leading Projects explanation →

You are the project manager for a global, virtual team. Which TWO actions would be MOST effective in building trust and collaboration among team members?

Question 351hardmulti select
Read the full People — Leading Projects explanation →

During a project review, you discover that the project is 15% over budget at the midpoint. After analysis, you find that the cost overrun is due to underestimation of testing effort and one team member's inefficiency. Which TWO actions should you take to address the situation?

Question 352easymulti select
Read the full People — Leading Projects explanation →

As an agile project manager, you want to empower the development team to self-organize. Which TWO practices would BEST support self-organization?

Question 353mediummulti select
Read the full People — Leading Projects explanation →

You are leading a project with a diverse team including members from different cultures and backgrounds. Which THREE actions should you take to promote an inclusive team environment?

Question 354hardmulti select
Read the full People — Leading Projects explanation →

Your project is in the planning phase, and you are developing the team charter. Which THREE elements should be included in the team charter to promote high performance?

Question 355mediummulti select
Read the full People — Leading Projects explanation →

During a sprint retrospective, the team identifies that unclear requirements from the product owner are causing rework. The team suggests improvements. Which THREE actions should the project manager (Scrum Master) take?

Question 356easymulti select
Read the full People — Leading Projects explanation →

You are managing a project where a key stakeholder requests a scope change that would add significant value but also increase risk and cost. Which TWO actions should you take FIRST?

Question 357hardmulti select
Read the full People — Leading Projects explanation →

Your project team includes members from different departments, and there is a conflict between two team leaders over resource allocation. One leader insists their tasks are higher priority. Which THREE actions should you take to resolve this conflict?

Question 358hardmulti select
Read the full People — Leading Projects explanation →

You are managing a hybrid project with a co-located core team and remote subject matter experts. Two senior developers argue daily about the technical approach for a critical module. The conflict is delaying sprint planning and affecting team morale. Which TWO actions should you take first?

Question 359hardmulti select
Read the full People — Leading Projects explanation →

During a sprint review, the product owner requests a significant scope change that would add two new features. The team estimates this would extend the sprint by one week. You are the Scrum Master. Which THREE actions should you take?

Question 360mediummulti select
Read the full People — Leading Projects explanation →

You are leading a global virtual team across four time zones. Recently, team members have complained about unclear task assignments and lack of collaboration tools. Which THREE actions would best improve team performance?

Question 361easymulti select
Read the full People — Leading Projects explanation →

A project team member with critical technical skills has been consistently delivering work late and with errors. You have had informal conversations with them, but performance hasn't improved. Which TWO actions should you take next?

Question 362mediummulti select
Read the full People — Leading Projects explanation →

Your project has a diverse team with members from different cultural backgrounds. A conflict arises because some team members feel their ideas are not being heard during meetings. Which THREE actions should you take to foster inclusion and collaboration?

Question 363hardmulti select
Read the full NAT/PAT explanation →

You are the project manager for a construction project. A key vendor notifies you that they cannot deliver a critical component for another two months, which would delay the critical path. Which TWO actions should you take first?

Question 364easymulti select
Read the full People — Leading Projects explanation →

You are leading an agile team that has experienced a drop in velocity over the last three sprints. The team attributes this to unclear requirements and frequent changes during the sprint. Which TWO actions would best address this?

Question 365mediummulti select
Read the full People — Leading Projects explanation →

An executive stakeholder has been bypassing you and directly assigning tasks to team members. The team is confused about priorities and some tasks conflict with the project plan. Which THREE actions should you take?

Question 366mediummulti select
Read the full People — Leading Projects explanation →

During a project audit, a new regulatory requirement is discovered that affects your project's deliverables. The compliance team says it must be implemented immediately. Your project is already behind schedule. Which THREE actions should you take?

Question 367hardmulti select
Read the full People — Leading Projects explanation →

Your project is 50% complete, and you realize it is 15% over budget due to unforeseen material cost increases. The sponsor is concerned about the budget variance. Which TWO actions should you take?

Question 368mediummulti select
Read the full People — Leading Projects explanation →

Your agile team is self-organizing, but a team member is consistently missing sprint commitments. The rest of the team is frustrated. As a Scrum Master, which THREE actions should you take?

Question 369easymulti select
Read the full People — Leading Projects explanation →

A risk event that was identified in the risk register has occurred. The risk response plan involves implementing a contingency plan. Which TWO actions should you take?

Question 370mediummulti select
Read the full People — Leading Projects explanation →

Your project team includes members from different generations (Baby Boomers, Gen X, Millennials). Some younger team members feel their contributions are not valued equally. Which TWO actions would best promote an inclusive environment?

Question 371hardmulti select
Read the full People — Leading Projects explanation →

Your project is using a hybrid approach. Mid-project, the sponsor asks you to skip the testing phase to save time and meet the deadline. The team is concerned about quality. Which THREE actions should you take?

Question 372easymulti select
Read the full People — Leading Projects explanation →

A new team member from a different country joins your project. They seem hesitant to speak up during meetings and often defer to others. Which TWO actions would best help them integrate?

Practice tests

Scored 10-question sessions with instant feedback and explanations.

PMP Practice Test 1 — 10 Questions→PMP Practice Test 2 — 10 Questions→PMP Practice Test 3 — 10 Questions→PMP Practice Test 4 — 10 Questions→PMP Practice Test 5 — 10 Questions→PMP Practice Exam 1 — 20 Questions→PMP Practice Exam 2 — 20 Questions→PMP Practice Exam 3 — 20 Questions→PMP Practice Exam 4 — 20 Questions→Free PMP Practice Test 1 — 30 Questions→Free PMP Practice Test 2 — 30 Questions→Free PMP Practice Test 3 — 30 Questions→PMP Practice Questions 1 — 50 Questions→PMP Practice Questions 2 — 50 Questions→PMP Exam Simulation 1 — 100 Questions→

Practice by domain

Each domain maps to a weighted exam section. Focus on the domain where you are weakest.

People — Leading ProjectsProcess — Managing Technical AspectsBusiness Environment — Strategy and ValueBusiness Environment: strategy and project benefits

Practice by scenario

Filter questions by type — troubleshooting, exhibit, drag-and-drop, PBQ, ACLs, OSPF, and more.

Browse scenarios→

Continue studying

All People — Leading Projects setsAll People — Leading Projects questionsPMP Practice Hub