A project manager is managing a large infrastructure project. The lead engineer has a strong personality and often dismisses ideas from other team members during meetings, causing some to withdraw from participation. What should the project manager do?

⚠ Common exam trap

Test-takers frequently choose Option D (team meeting) because it seems inclusive and non-confrontational, but the PMP exam expects the project manager to address the specific individual privately first, as public discussions can embarrass the engineer and fail to resolve the underlying issue.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Speak privately with the lead engineer about the impact of their behavior and set expectations for collaboration

The project manager should address the disruptive behavior directly and privately with the lead engineer, focusing on the impact on team collaboration and setting clear expectations for respectful communication. This aligns with the PMP's focus on conflict resolution and team leadership, as direct, constructive feedback is the most effective way to change behavior without escalating conflict or undermining the engineer's authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Redistribute the lead engineer's tasks to reduce their influence

    Why it's wrong here

    Redistributing a lead engineer's tasks to diminish their influence is a punitive and indirect management action that fails to address the problematic behavior directly. This approach can severely damage team morale, erode trust, and create resentment, potentially escalating conflict rather than resolving it. Such a move disrupts project structure and roles, signaling a lack of direct leadership and potentially leading to further disengagement or even retaliation from the affected individual.

  • Ignore the behavior and hope the team members will stand up for themselves

    Why it's wrong here

    Ignoring disruptive behavior and hoping team members will self-correct is an abdication of the project manager's responsibility to foster a healthy team environment. This inaction tolerates a toxic atmosphere, signaling to the team that such behavior is acceptable, which can lead to decreased psychological safety, reduced productivity, and increased team conflict. Ultimately, it erodes trust in leadership and jeopardizes the project's success by allowing negative dynamics to fester unchecked.

  • Speak privately with the lead engineer about the impact of their behavior and set expectations for collaboration

    Why this is correct

    Speaking privately with the lead engineer about the impact of their behavior and setting clear expectations for collaboration is the most professional and effective approach. This direct, yet respectful, conversation allows the project manager to provide constructive feedback, ensuring the engineer understands the specific impact of their actions on the team and project. It offers an opportunity for the individual to acknowledge the issue and commit to behavioral adjustments, fostering accountability and preserving working relationships while promoting a more collaborative environment.

  • Schedule a team meeting to discuss meeting etiquette without singling out the engineer

    Why it's wrong here

    Scheduling a general team meeting to discuss etiquette without singling out the engineer is an indirect and often ineffective strategy for addressing specific behavioral issues. While promoting general team norms is valuable, this approach fails to directly confront the individual whose actions are causing the problem, allowing the behavior to persist unaddressed. The problematic engineer might not recognize their own actions as the target, or they might feel indirectly accused without the opportunity for a direct, constructive dialogue, thus failing to achieve the desired behavioral change.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.