Question 308 of 892
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

An executive stakeholder bypasses the project manager and directly instructs a team member to work on a new feature not in the project scope. The team member is confused. What should the project manager do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Tell the executive stakeholder that they must go through the PM for all requests

Option C is correct because the project manager must first address the governance breach by directly communicating with the executive stakeholder to reinforce the established communication management plan. This aligns with the PMBOK Guide's principle that all formal requests should flow through the project manager to maintain scope control and prevent unauthorized work. The immediate action is to clarify the process, not to escalate or submit a change request without understanding the stakeholder's intent.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reprimand the team member for following instructions without consulting the PM

    Why it's wrong here

    The team member was put in a difficult position; blaming them is not productive.

  • Instruct the team member to ignore the executive's request

    Why it's wrong here

    Ignoring an executive's request could create conflict; the PM should address the issue directly.

  • Tell the executive stakeholder that they must go through the PM for all requests

    Why this is correct

    A private conversation with the stakeholder to reinforce the project's governance is appropriate.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Submit a change request for the new feature

    Why it's wrong here

    Submitting a change request without first discussing with the stakeholder may not address the bypass issue.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may choose Option D (submit a change request) because it seems proactive, but the PM must first address the communication process violation before formalizing any scope change.

Detailed technical explanation

How to think about this question

Under the PMBOK Guide's 'Manage Communications' process, the project manager is the single point of accountability for all formal communications to and from the project team. The 'Direct and Manage Project Work' process requires that any work outside the scope baseline must be preceded by a change request approved through the integrated change control process. In practice, a senior stakeholder bypassing the PM often indicates a lack of awareness of the project's governance framework, so the PM's first step is to educate and reinforce the process, not to assume the request is valid or to punish the team.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Tell the executive stakeholder that they must go through the PM for all requests — Option C is correct because the project manager must first address the governance breach by directly communicating with the executive stakeholder to reinforce the established communication management plan. This aligns with the PMBOK Guide's principle that all formal requests should flow through the project manager to maintain scope control and prevent unauthorized work. The immediate action is to clarify the process, not to escalate or submit a change request without understanding the stakeholder's intent.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.