Question 95 of 892
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor informs you that they cannot deliver a critical component on time due to a supply chain disruption. This risk was identified and included in the risk register. What should you do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the contingency plan that was defined for this risk

Since the risk was identified and included in the risk register, a contingency plan should have been defined. The correct first action is to implement that pre-planned contingency plan to address the supply chain disruption, as it is the most efficient and proactive response to a known risk.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the steering committee for guidance

    Why it's wrong here

    The PM should first act on the contingency plan before escalating.

  • Implement the contingency plan that was defined for this risk

    Why this is correct

    Since the risk was identified and planned for, executing the contingency plan is the appropriate response.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Brainstorm new solutions with the team since the risk was not anticipated

    Why it's wrong here

    The risk was anticipated; a contingency plan should already exist.

  • Wait to see if the vendor can resolve the issue before taking action

    Why it's wrong here

    Delaying action may worsen the impact on the project schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may confuse a contingency plan with a fallback plan or assume that all risks require escalation, leading them to choose escalation or unnecessary brainstorming instead of executing the pre-planned response.

Detailed technical explanation

How to think about this question

In risk management, a contingency plan is a predefined set of actions to be executed when a specific risk event occurs, ensuring a swift and coordinated response. This aligns with the PMBOK Guide's 'Plan Risk Responses' process, where risk owners are assigned and trigger conditions are defined. In a real-world scenario, implementing the contingency plan immediately can prevent cascading delays and maintain the project schedule, as opposed to reactive measures.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement the contingency plan that was defined for this risk — Since the risk was identified and included in the risk register, a contingency plan should have been defined. The correct first action is to implement that pre-planned contingency plan to address the supply chain disruption, as it is the most efficient and proactive response to a known risk.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.