Courseiva
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

You are managing a project that is on schedule and under budget. A key stakeholder requests a significant scope change that would improve the product's value but also extend the schedule by 20%. The change has not been through change control. What should you do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Ask the stakeholder to submit a formal change request for evaluation

The project manager must ensure that all changes go through the formal change control process to assess impacts on scope, schedule, budget, and quality. Option A is correct because it follows proper change management procedures. Option B is incorrect because outright refusal ignores potential value and proper process. Option C is incorrect because delaying to a follow-up project may not be justified without evaluation. Option D is incorrect because implementing without change control bypasses governance and could have unforeseen risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the stakeholder to submit a formal change request for evaluation

    Why this is correct

    Asking the stakeholder to submit a formal change request is the correct and most professional action, as it adheres strictly to the Integrated Change Control process. This formal submission triggers a structured evaluation of the change's potential impact on the project's scope, schedule, cost, resources, and quality baselines. It ensures that all decisions are informed, documented, and approved by the appropriate authority, thereby maintaining project integrity and governance.

  • Refuse the change to protect the original schedule and budget

    Why it's wrong here

    Refusing a change outright, even with the intent to protect baselines, is a critical deviation from proper project governance. This action bypasses the essential Integrated Change Control process, preventing any formal assessment of the proposed change's potential value or impact on project objectives. A Project Manager's role is to facilitate evaluation, not to unilaterally dismiss stakeholder requests without due diligence and a structured review.

  • Suggest the stakeholder request the change in a follow-up project

    Why it's wrong here

    Suggesting a stakeholder defer a change to a future project without first evaluating its current relevance or impact is an inappropriate and premature response. This preemptive rejection neglects the opportunity to assess if the change could deliver significant value or address critical needs within the current project's scope and objectives. Proper procedure dictates that all change requests undergo formal analysis and impact assessment before any decision to accept, reject, or defer is made.

  • Implement the change since it adds value and the project has contingency

    Why it's wrong here

    Implementing a change without formal approval, despite perceived value or available contingency, fundamentally undermines the project's established governance framework. This unauthorized action risks uncontrolled scope creep, invalidates project baselines, and sets a dangerous precedent that can lead to project instability and stakeholder misalignment. Formal approval through the change control process is mandatory to ensure all impacts are assessed, documented, and officially sanctioned.

Go deeper

Related to this question

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.