Courseiva

PMP People — Leading Projects Practice Question

Your project is running 15% over budget at the midpoint. The cost variance is due to higher-than-expected material costs. What should you do?

⚠ Common exam trap

PMP often tests the sequence of analyze-before-act: candidates may choose to immediately request more funding or cut scope instead of first performing variance analysis and updating forecasts.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Perform a variance analysis, update the cost forecast, and consider corrective actions such as finding cost savings

When a project is over budget due to higher material costs, the project manager should first perform variance analysis to understand the root cause, then update the cost forecast (e.g., EAC) and evaluate corrective actions such as negotiating lower prices or finding cost savings elsewhere. This aligns with PMP's analyze-then-act principle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Perform a variance analysis, update the cost forecast, and consider corrective actions such as finding cost savings

    Why this is correct

    A 15% budget overrun at the midpoint necessitates a thorough variance analysis to identify the root causes of the deviation from the cost baseline. Following this, the project manager must update the cost forecast (e.g., Estimate at Completion - EAC) to reflect the new reality and provide an accurate projection of the final project cost. Only after this analysis should corrective actions, such as identifying cost savings or process improvements, be considered and implemented to bring the project back within acceptable limits or to manage stakeholder expectations effectively. This systematic approach is a core component of the Control Costs process.

  • ✗

    Reduce the project scope to bring costs back in line

    Why it's wrong here

    Unilaterally reducing the project scope to address a cost overrun is an inappropriate first response. Scope changes have significant implications for project deliverables, stakeholder expectations, and the overall business case, requiring a formal change request. Such a decision must undergo a thorough impact analysis, be documented, and approved through the integrated change control process, rather than being an immediate, unanalyzed corrective action for a budget issue. This approach bypasses critical governance and could jeopardize project success.

  • ✗

    Continue as planned since the project is only 15% over budget

    Why it's wrong here

    Ignoring a 15% budget overrun at the project's midpoint is a critical failure in cost control and risk management. This significant variance indicates a potential systemic issue or an inaccurate initial estimate that requires immediate attention and investigation. Failing to address such a deviation proactively will almost certainly lead to further budget depletion, potential project failure, and a loss of stakeholder confidence, contradicting the principles of effective project monitoring and control.

  • ✗

    Request additional funding from the sponsor immediately

    Why it's wrong here

    Immediately requesting additional funding from the sponsor without first conducting a comprehensive variance analysis and exploring internal mitigation strategies is unprofessional and demonstrates a lack of due diligence. The project manager's responsibility is to understand the root cause of the overrun, assess its impact, and develop a justified plan, which may include corrective actions or a revised forecast, before escalating to the sponsor for financial assistance. A well-prepared case is essential for securing additional resources.

About these practice questions

One of 820 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.