Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

During a project status meeting, a sponsor mentions that they have been directly assigning tasks to a team member without going through you. The team member is now confused about priorities. What should you do FIRST?

⚠ Common exam trap

Test-takers frequently choose Option B (escalation) because they assume the sponsor is acting maliciously, but the PMP exam emphasizes first attempting direct, respectful communication to resolve the issue before escalating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a meeting with the sponsor to review the communication management plan and roles

The first step in resolving a communication breakdown is to address the root cause: the sponsor is bypassing the project manager's authority and the established communication management plan. By scheduling a meeting with the sponsor to review the plan and their roles, you reaffirm the agreed-upon escalation and task assignment processes, which is a proactive, professional approach aligned with PMBOK's principles of managing stakeholder expectations and enforcing the project's governance framework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule a meeting with the sponsor to review the communication management plan and roles

    Why this is correct

    This option represents a proactive and professional approach to address a deviation from the established communication management plan. By scheduling a direct meeting, the project manager can respectfully remind the sponsor of the agreed-upon communication channels and roles, reinforcing the importance of adhering to these processes for project efficiency and control. This aims to resolve the issue collaboratively without escalating or creating conflict, ensuring future communications follow the defined protocol.

  • Report the sponsor's behavior to the PMO or senior management

    Why it's wrong here

    Reporting the sponsor's behavior to the PMO or senior management is a premature and potentially damaging action. Such an escalation, without first attempting a direct, professional conversation with the sponsor, can severely strain the project manager-sponsor relationship and undermine trust. It bypasses the opportunity for direct conflict resolution and might be perceived as confrontational, making future collaboration more challenging.

  • Tell the team member to ignore the sponsor's requests

    Why it's wrong here

    Instructing a team member to ignore requests from the project sponsor places the team member in an untenable position and directly creates conflict. This approach fails to address the root cause of the communication breakdown, which is the sponsor bypassing established channels, and instead shifts the burden onto the team member. It also risks alienating the sponsor and does not reinforce the project's defined communication protocols.

  • Update the team member's task list to include the sponsor's assignments

    Why it's wrong here

    Updating the team member's task list to incorporate assignments directly given by the sponsor effectively condones and legitimizes the bypassing of established communication channels. This action undermines the project manager's authority, compromises project control, and sets a dangerous precedent where stakeholders can circumvent defined processes. It fails to address the process violation and can lead to scope creep or unmanaged work.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.