- A
Ignore the requirement because the project is already underway
Why wrong: Ignoring regulatory requirements can lead to non-compliance.
- B
Inform the team to start incorporating the new requirement immediately
Why wrong: Implementing changes without approval bypasses change control.
- C
Update the project management plan directly to include the change
Why wrong: Changes must be approved before updating the plan.
- D
Submit a change request to assess the impact on scope, schedule, and cost
The change control process is the correct way to handle new requirements.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A new regulatory requirement has been discovered that affects your project's deliverables. The project is halfway through its schedule. What should the project manager do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request to assess the impact on scope, schedule, and cost
D is correct because the PMBOK Guide mandates that any change, including a new regulatory requirement, must first be processed through a formal change request to evaluate its impact on scope, schedule, and cost. Since the project is already halfway through its schedule, the project manager must follow the integrated change control process to ensure the change is assessed before any action is taken. This prevents unauthorized changes that could disrupt project baselines.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ignore the requirement because the project is already underway
Why it's wrong here
Ignoring regulatory requirements can lead to non-compliance.
- ✗
Inform the team to start incorporating the new requirement immediately
Why it's wrong here
Implementing changes without approval bypasses change control.
- ✗
Update the project management plan directly to include the change
Why it's wrong here
Changes must be approved before updating the plan.
- ✓
Submit a change request to assess the impact on scope, schedule, and cost
Why this is correct
The change control process is the correct way to handle new requirements.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may think a regulatory requirement is mandatory and must be implemented immediately, but the PMP exam tests that even mandatory changes must go through the formal change control process to assess and manage impacts properly.
Detailed technical explanation
How to think about this question
In the PMBOK Guide, the Perform Integrated Change Control process is the only authorized path for changes to baselines. A change request must document the proposed change, its rationale, and a preliminary impact analysis on the triple constraint (scope, schedule, cost). The project manager then submits it to the CCB for approval or rejection. In real-world scenarios, regulatory changes often have strict deadlines, so the impact analysis must also consider legal compliance timelines and potential rework costs.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request to assess the impact on scope, schedule, and cost — D is correct because the PMBOK Guide mandates that any change, including a new regulatory requirement, must first be processed through a formal change request to evaluate its impact on scope, schedule, and cost. Since the project is already halfway through its schedule, the project manager must follow the integrated change control process to ensure the change is assessed before any action is taken. This prevents unauthorized changes that could disrupt project baselines.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.