PMP People — Leading Projects Practice Question

A key vendor informs you that they cannot deliver a critical component on time, which will delay the project. You need to decide on next steps. Which THREE actions are most appropriate?

⚠ Common exam trap

The trap here is that candidates mistakenly treat 'asking the team to work overtime' as a valid corrective action without recognizing it requires a formal change request and impact analysis, or they assume terminating the vendor contract is the first step instead of evaluating the schedule impact first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan with the new delivery date

Updating the project management plan with the new delivery date is correct because it formally documents the revised schedule baseline, which is a key output of the integrated change control process. This ensures all project artifacts reflect the current reality, enabling accurate tracking and communication. Without this update, the plan becomes obsolete and misaligns with actual project execution.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the project management plan with the new delivery date

    Why this is correct

    After evaluating the impact of the vendor delay on the project schedule and critical path, and communicating with stakeholders, updating the project management plan is a critical step. This formalizes the approved change, incorporating the new delivery date and any resulting adjustments to subsequent activities or resource allocations. It ensures all project documentation reflects the current, agreed-upon baseline, maintaining project control and providing a revised roadmap for the team. This action is part of the Integrated Change Control process.

  • Ask the team to work overtime to compensate for the delay

    Why it's wrong here

    Asking the team to work overtime is generally an ineffective and potentially detrimental first response to a vendor delay, especially when a critical component is unavailable. Overtime cannot magically produce a missing component and can lead to burnout, decreased morale, and increased costs without addressing the root cause of the schedule variance. This action fails to consider the actual constraint and may exacerbate project risks rather than mitigate them.

  • Notify the project sponsor and other key stakeholders of the delay and potential impacts

    Why this is correct

    Promptly notifying the project sponsor and other key stakeholders about a significant vendor delay is a fundamental responsibility of a project manager. This ensures transparency, manages expectations, and allows stakeholders to understand the potential impacts on project objectives, budget, and scope. Early communication facilitates collaborative decision-making and allows for timely adjustments to business strategies or related projects, preventing surprises and maintaining trust.

  • Immediately terminate the vendor contract

    Why it's wrong here

    Immediately terminating a vendor contract without prior investigation, negotiation, or exploring alternative solutions is an extreme and premature action. Such a decision could incur significant legal and financial penalties, further delay the project while a new vendor is sourced, and potentially damage future business relationships. Contract termination should only be considered after exhausting other mitigation strategies and a thorough legal and financial review, typically as a last resort.

  • Evaluate the impact on the project schedule and critical path

    Why this is correct

    Before taking any corrective action, it is imperative to evaluate the precise impact of the vendor delay on the project schedule, particularly the critical path. This analysis determines whether the delay affects the project's overall completion date, identifies dependent activities, and quantifies the extent of the variance. Understanding the true impact is foundational for developing effective mitigation strategies, informing stakeholders accurately, and making data-driven decisions regarding schedule adjustments or resource reallocations.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.