Courseiva
People — Leading ProjectshardMultiple SelectObjective-mapped

Which Three Actions Should You Take When Sponsor Asks to Skip Testing in Hybrid Project?

Your project is using a hybrid approach. Mid-project, the sponsor asks you to skip the testing phase to save time and meet the deadline. The team is concerned about quality. Which THREE actions should you take?

Quick Answer

Proposing an alternative such as reducing the scope of testing or applying risk-based testing is the right response because it reframes a demand to cut a quality safeguard entirely into a negotiation over how testing effort gets allocated, which preserves the sponsor's goal of saving time without abandoning quality altogether. Risk-based testing works by concentrating testing effort on the highest-risk or highest-value areas of the deliverable, so the team still catches the defects most likely to cause serious problems even though they're not testing everything with equal depth. This is a meaningfully different response than simply agreeing to skip testing outright, which would satisfy the schedule pressure but expose the project to defects that testing exists to catch, or than flatly refusing the sponsor's request, which ignores the legitimate deadline pressure the sponsor is under. By consulting the team to identify which tests matter most, the project manager turns a binary yes-or-no decision into a scoped, defensible compromise that both sides can live with. Whenever a sponsor or stakeholder pushes to cut a process step entirely for the sake of schedule, the strongest response on these exams is rarely full compliance or flat refusal; it's proposing a scaled-down or risk-prioritized version of that step that protects the intent behind it while still respecting the real-world constraint driving the request.

⚠ Common exam trap

It's easy for candidates to choose to escalate immediately (Option B) thinking it's a formal risk response, but the hybrid approach requires first engaging the sponsor and team to find a negotiated solution before escalating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Consult with the team to identify the most critical tests that can be performed within the remaining time

Consulting with the team to identify the most critical tests aligns with the hybrid approach's principle of balancing agility with quality. By focusing on high-risk or high-value test cases, you can reduce testing time while still mitigating key defects, preserving the project's quality standards within the sponsor's deadline constraint.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Consult with the team to identify the most critical tests that can be performed within the remaining time

    Why this is correct

    Involving the team leverages their expertise to find a balanced solution.

  • Escalate the issue to the PMO or steering committee without further discussion

    Why it's wrong here

    Should first discuss with the sponsor directly.

  • Agree to skip testing to meet the sponsor's request

    Why it's wrong here

    Agreeing to skip testing compromises quality and is not professional.

  • Explain to the sponsor the risks of skipping testing, including potential rework and quality issues

    Why this is correct

    Educating stakeholders on risks is a PM responsibility.

  • Propose an alternative, such as reducing the scope of testing or using risk-based testing

    Why this is correct

    Offering alternatives demonstrates flexibility while maintaining quality.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. You are managing a construction project using a traditional approach. The sponsor asks you to skip the quality inspection phase to save two weeks and meet an aggressive deadline. What should you do FIRST?

medium
  • A.Agree to skip the inspections to satisfy the sponsor's request
  • B.Refuse outright because quality cannot be compromised
  • C.Explain the risks of skipping quality inspections and discuss alternatives to meet the deadline
  • D.Proceed with inspections but report that they were completed

Why C: As a project manager, your first responsibility is to address the sponsor's request professionally by communicating the risks of skipping quality inspections—such as potential rework, safety failures, and cost overruns—and then collaboratively exploring alternatives (e.g., parallel testing, reduced sampling) to meet the deadline without compromising quality. This aligns with the PMP's emphasis on stakeholder engagement and proactive risk management, not blind compliance or refusal.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.