- A
Agree to reduce testing, as the sponsor has authority over the budget
Why wrong: Even sponsors must follow the change control process for changes affecting the project.
- B
Refuse the request, stating that testing is essential for quality
Why wrong: Refusing without analysis is not collaborative; the PM should assess the impact and present options.
- C
Submit a change request to reduce testing and analyze the impact on quality and risks
This follows the formal change control process, evaluating impacts before making a decision.
- D
Implement the reduction immediately to save costs, then document it later
Why wrong: Implementing changes without approval violates project governance and change control.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is running 15% over budget at the midpoint. The sponsor asks you to reduce costs by cutting the testing phase from three weeks to one week. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request to reduce testing and analyze the impact on quality and risks
Option C is correct because the PMBOK Guide requires that any change to the project baseline, including scope, schedule, or budget, must follow the formal integrated change control process. The first step is to submit a change request to analyze the impact on quality, risks, and other constraints before making a decision. This ensures that the sponsor and stakeholders understand the trade-offs, such as increased defect risk or rework costs, before approving the reduction.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Agree to reduce testing, as the sponsor has authority over the budget
Why it's wrong here
Even sponsors must follow the change control process for changes affecting the project.
- ✗
Refuse the request, stating that testing is essential for quality
Why it's wrong here
Refusing without analysis is not collaborative; the PM should assess the impact and present options.
- ✓
Submit a change request to reduce testing and analyze the impact on quality and risks
Why this is correct
This follows the formal change control process, evaluating impacts before making a decision.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Implement the reduction immediately to save costs, then document it later
Why it's wrong here
Implementing changes without approval violates project governance and change control.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the misconception that the sponsor's authority allows direct changes without formal process, or that the project manager should immediately reject changes without analysis, when the correct first step is always to submit a change request and analyze the impact.
Detailed technical explanation
How to think about this question
In the context of the PMP exam, the change control process is governed by the Perform Integrated Change Control process (PMBOK Guide 6th Edition, Section 4.6). A change request must be documented and assessed for impacts on the triple constraint (scope, schedule, cost) and quality, often using tools like a cost-benefit analysis or risk assessment matrix. In real-world projects, cutting testing from three weeks to one week typically increases the probability of undetected defects, which can lead to higher cost of quality (COQ) due to rework or warranty claims, a trade-off that must be formally evaluated and approved by the change control board (CCB).
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request to reduce testing and analyze the impact on quality and risks — Option C is correct because the PMBOK Guide requires that any change to the project baseline, including scope, schedule, or budget, must follow the formal integrated change control process. The first step is to submit a change request to analyze the impact on quality, risks, and other constraints before making a decision. This ensures that the sponsor and stakeholders understand the trade-offs, such as increased defect risk or rework costs, before approving the reduction.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.