Courseiva
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

You are the project manager for a software development project using a hybrid approach. Two senior developers have a heated disagreement about the best technical solution for a critical feature. The disagreement is causing delays and affecting team morale. What should you do first?

⚠ Common exam trap

It's easy for candidates to confuse the project manager's role in a hybrid approach with a traditional predictive approach, where the manager might be expected to make technical decisions or escalate quickly, rather than facilitating team collaboration.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a meeting with both developers to listen to their perspectives and facilitate a resolution

As a project manager using a hybrid approach, your first responsibility is to facilitate conflict resolution among team members. By scheduling a meeting to listen to both developers' perspectives, you demonstrate servant leadership, encourage collaborative problem-solving, and leverage their technical expertise to reach a consensus, which aligns with the PMI Talent Triangle's leadership and team management skills.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the project sponsor for a final decision

    Why it's wrong here

    Escalating the issue directly to the project sponsor is premature and bypasses the project manager's primary responsibility to manage team conflicts effectively. This approach violates the principle of resolving issues at the lowest appropriate level, disempowering the team and undermining their ability to find a collaborative solution. It should only be considered as a last resort if all attempts at team-level resolution have failed.

  • Ignore the conflict and hope it resolves on its own

    Why it's wrong here

    Ignoring the conflict and hoping it resolves independently is a passive and irresponsible approach for a project manager. Unaddressed conflicts rarely disappear; instead, they tend to fester, escalate, and negatively impact team morale, productivity, and overall project performance. A proactive project manager must address disagreements directly to prevent further dysfunction and ensure a healthy working environment.

  • Make a decision yourself and tell the developers to implement that solution

    Why it's wrong here

    Making an autocratic decision and imposing it on the developers is a "forcing" conflict resolution technique that can be detrimental to team dynamics. This approach undermines team ownership, stifles creativity, and fails to address the root causes of the disagreement, potentially leading to resentment, reduced commitment, and recurring conflicts. It prioritizes a quick resolution over a sustainable, collaborative one.

  • Schedule a meeting with both developers to listen to their perspectives and facilitate a resolution

    Why this is correct

    Scheduling a meeting to listen and facilitate a resolution exemplifies the "collaborating" or "problem-solving" approach to conflict management, which is highly effective. This method allows the project manager to understand both perspectives, foster open communication, and guide the developers toward a mutually acceptable solution. It empowers the team, builds consensus, and strengthens working relationships for long-term project success.

Go deeper

Related to this question

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.