Question 189 of 892
People — Leading ProjectshardMultiple ChoiceObjective-mapped

Quick Answer

The correct first step is to speak privately with the executive to explain the change control process and request they route requests through you. This is the right action because, as the project manager, you are the guardian of the project’s scope and the formal change control system; allowing an executive to bypass the project manager directly to a team member creates unauthorized scope creep and undermines the entire project governance structure. On the PMP exam, this scenario tests your understanding of the Manage Communications and Perform Integrated Change Control processes, specifically how to handle an executive bypassing project manager change control without escalating conflict or embarrassing the stakeholder publicly. A common trap is to immediately tell the team member to ignore the executive or to confront the executive in front of others, both of which damage relationships and violate professional responsibility. Instead, remember the memory tip: “Private praise, private redirect”—always address process violations one-on-one with the bypassing stakeholder to preserve trust while reinforcing the proper escalation path.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

An executive stakeholder bypasses you and gives direct instructions to a team member to add a new feature immediately. The team member is confused and asks you what to do. What should you do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

  • Clue: "immediately / without restart"

    Why it matters: Time or reboot constraint — the correct answer must take effect right away without requiring a reboot or reload.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Speak privately with the executive to explain the change control process and request they route requests through you

Option B is correct because as the project manager, you are responsible for maintaining the change control process and protecting the team from scope creep. Speaking privately with the executive allows you to professionally reinforce the proper escalation path and ensure all changes are evaluated for impact on cost, schedule, and quality before implementation.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Tell the team member to follow the executive's instructions to avoid conflict

    Why it's wrong here

    This undermines the project's governance and the PM's authority.

  • Speak privately with the executive to explain the change control process and request they route requests through you

    Why this is correct

    Direct communication with the stakeholder to reinforce proper channels is proactive and aligns with PMI principles.

    Clue confirmation

    The clue words "first", "immediately / without restart" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Ask the team member to ignore the executive's instructions

    Why it's wrong here

    Ignoring a stakeholder can damage relationships; the PM should handle it diplomatically.

  • Submit a change request for the new feature without further discussion

    Why it's wrong here

    While a change request is needed, the first step should be to address the bypassing behavior.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may choose Option A (appease the executive) or Option D (submit a change request immediately) because they seem proactive, but the PMP exam emphasizes that the FIRST action must be to address the communication breakdown with the stakeholder, not to bypass or formalize the unauthorized change.

Detailed technical explanation

How to think about this question

In the PMBOK Guide, the project manager acts as the single point of contact for scope changes to maintain the integrity of the change control system (CCS). The executive's direct instruction represents a classic example of a 'scope creep' risk that must be managed through the Perform Integrated Change Control process, which requires formal documentation, impact analysis, and approval before any work begins. Real-world scenarios often involve senior stakeholders who are unaware of the formal process, so a private, respectful conversation is the most effective first step to realign expectations without escalating conflict.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Speak privately with the executive to explain the change control process and request they route requests through you — Option B is correct because as the project manager, you are responsible for maintaining the change control process and protecting the team from scope creep. Speaking privately with the executive allows you to professionally reinforce the proper escalation path and ensure all changes are evaluated for impact on cost, schedule, and quality before implementation.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first", "immediately / without restart". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

5 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. You are managing a project where a key executive stakeholder bypasses you and gives direct orders to the development team. The team is confused about priorities. What should you do first?

easy
  • A.Tell the team to follow the executive's orders to avoid conflict
  • B.Report the executive's behavior to the project sponsor
  • C.Schedule a meeting with the executive to discuss the impact of bypassing the PM and reinforce the communication plan
  • D.Update the communication plan to include the executive's approach

Why C: Option C is correct because the first action should be to address the root cause of the confusion—the executive's bypassing behavior—by scheduling a private meeting to discuss its impact on project priorities and team morale, and to reinforce the established communication plan. This aligns with the PMP's focus on proactive stakeholder management and conflict resolution, ensuring the project manager maintains authority and clarity without escalating prematurely.

Variation 2. During a hybrid project, an executive stakeholder bypasses you and directly instructs a team member to add a new feature. The team member is now confused about priorities. What should you do first?

hard
  • A.Meet with the executive stakeholder to explain the project's change control process and the importance of proper communication channels
  • B.Ignore the issue and allow the feature to be added to maintain stakeholder satisfaction
  • C.Reprimand the team member for accepting instructions without your approval
  • D.Add the feature to the backlog and treat it as a priority

Why A: Option A is correct because, as the project manager, you must first address the root cause of the confusion—the executive stakeholder's bypass of the formal change control process. By meeting with the executive, you reinforce the importance of proper communication channels and the change control board (CCB) process, which protects the project from scope creep and ensures all changes are evaluated for impact on cost, schedule, and quality. This aligns with the PMBOK Guide's principle of managing stakeholder engagement and maintaining a single point of accountability for project decisions.

Variation 3. During a project status meeting, an executive stakeholder bypasses you and directly instructs a team member to add a new feature to the current sprint. The team member looks confused. What should you do FIRST?

medium
  • A.After the meeting, privately remind the executive about the change control process and offer to submit a change request
  • B.Ignore the situation and continue the meeting
  • C.Tell the team member to add the feature as requested to satisfy the stakeholder
  • D.Immediately interrupt the executive and explain that all changes must go through you

Why A: Option B is correct: PMI recommends addressing such issues privately to maintain respect. The PM should clarify the change control process with the executive. Option A is confrontational and could damage relationships. Option C allows scope creep without governance. Option D undermines the team's trust.

Variation 4. An executive stakeholder bypasses the project manager and directly instructs a team member to work on a new feature not in the project scope. The team member is confused. What should the project manager do FIRST?

hard
  • A.Reprimand the team member for following instructions without consulting the PM
  • B.Instruct the team member to ignore the executive's request
  • C.Tell the executive stakeholder that they must go through the PM for all requests
  • D.Submit a change request for the new feature

Why C: Option C is correct because the project manager must first address the governance breach by directly communicating with the executive stakeholder to reinforce the established communication management plan. This aligns with the PMBOK Guide's principle that all formal requests should flow through the project manager to maintain scope control and prevent unauthorized work. The immediate action is to clarify the process, not to escalate or submit a change request without understanding the stakeholder's intent.

Variation 5. During a hybrid project, the product owner frequently bypasses you and gives direct instructions to the development team. The team is confused about priorities, and scope creep is occurring. What should you do FIRST?

medium
  • A.Speak privately with the product owner to explain the impact on the team and request that instructions go through you
  • B.Tell the team to ignore instructions from the product owner
  • C.Escalate to the project sponsor for resolution
  • D.Update the team charter to include a communication protocol

Why A: Option A is correct because the first step in resolving a conflict between the product owner and the development team is to have a private, respectful conversation with the product owner. This allows you to explain the negative impact of bypassing you—such as team confusion, priority misalignment, and scope creep—and request that all instructions be routed through you to maintain the agreed-upon workflow and protect the team's focus.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.