Question 263 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is running 15% over budget at the midpoint. The sponsor is concerned and asks the PM to reduce costs by cutting team training and team-building activities. What should the PM do?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the importance of these activities and propose other cost-saving measures

Option C is correct because the PM should protect the project's long-term success by explaining the critical role of team training and team-building in maintaining performance and morale, especially when the project is under budget pressure. Cutting these activities can lead to decreased productivity, higher turnover, and ultimately greater cost overruns. The PM should propose alternative cost-saving measures that do not compromise the team's capability or the project's quality.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Agree to cut training and team-building to meet the sponsor's request

    Why it's wrong here

    Cutting these activities may harm long-term team performance and morale.

  • Reduce the project scope to cut costs

    Why it's wrong here

    Scope changes require formal change control; this may not be the best first step.

  • Explain the importance of these activities and propose other cost-saving measures

    Why this is correct

    The PM should advocate for the team and find alternative savings that don't negatively impact performance.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate to the PMO for a decision

    Why it's wrong here

    The PM should first analyze and propose alternatives before escalating.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may assume the sponsor's request must be followed without question, but the PM must balance stakeholder demands with the project's long-term health and use their expertise to propose better alternatives.

Detailed technical explanation

How to think about this question

In project management, team training and team-building are investments in the project's 'human capital' that directly affect the team's learning curve, collaboration efficiency, and motivation. The PMBOK Guide emphasizes that the Develop Team process includes training to enhance competencies and team-building to improve interpersonal relationships, both of which reduce rework and increase productivity. A real-world scenario: a software development project that cut training to save costs saw a 30% increase in bug rates and a 20% drop in velocity, ultimately costing more than the training would have.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Explain the importance of these activities and propose other cost-saving measures — Option C is correct because the PM should protect the project's long-term success by explaining the critical role of team training and team-building in maintaining performance and morale, especially when the project is under budget pressure. Cutting these activities can lead to decreased productivity, higher turnover, and ultimately greater cost overruns. The PM should propose alternative cost-saving measures that do not compromise the team's capability or the project's quality.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.