Question 292 of 892
People — Leading ProjectsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is to assess the impact of the change on the project schedule and budget, and then submit a formal change request to the Change Control Board. This is correct because any last-minute scope change request from a stakeholder, even on a project that is on track and within budget, must follow the formal integrated change control process as defined in the PMBOK Guide. The project manager’s first duty is to evaluate the implications of the change on the triple constraint—time, cost, and scope—before escalating it for a decision. On the PMP exam, this scenario tests your understanding of change control governance and the project manager’s role as a facilitator, not a decision-maker. A common trap is to assume that because the project is performing well, you can approve the change directly; instead, remember that scope creep is prevented only through disciplined process adherence. Memory tip: “Assess, then request—never approve a scope change on your chest.”

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are leading a project to develop a new product. The marketing department requests a last-minute change that would increase the project's scope significantly. The project is on track and within budget. Which TWO actions should the project manager take?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board

Option C is correct because any change that significantly increases scope must go through the formal change control process, even if the project is on track. The project manager must submit a change request to the Change Control Board (CCB) for evaluation and approval, ensuring proper governance and alignment with project objectives.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reject the change because the project is on track

    Why it's wrong here

    Changes should be evaluated, not automatically rejected.

  • Escalate the issue to the project sponsor

    Why it's wrong here

    The PM should first assess and submit a change request.

  • Submit a change request to the change control board

    Why this is correct

    Formal change control is required.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Incorporate the change to satisfy the marketing department

    Why it's wrong here

    Implementing changes without approval bypasses change control.

  • Assess the impact of the change on the project schedule and budget

    Why this is correct

    Impact analysis is needed before any decision.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the misconception that a project manager can reject or approve changes based on project performance alone, rather than following the formal change control process and assessing impact first.

Detailed technical explanation

How to think about this question

In project management, the change control system is a documented process that defines how to manage changes to project baselines. The project manager's role is to analyze the change's impact on scope, schedule, cost, quality, and risk, then submit a formal change request to the CCB for decision. This ensures that all changes are evaluated against project objectives and approved before implementation, preventing unauthorized scope creep and maintaining stakeholder alignment.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request to the change control board — Option C is correct because any change that significantly increases scope must go through the formal change control process, even if the project is on track. The project manager must submit a change request to the Change Control Board (CCB) for evaluation and approval, ensuring proper governance and alignment with project objectives.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.