Courseiva
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

In the middle of a project, a new regulation is introduced that impacts your project's deliverables. The team needs to make adjustments, but the change will affect the critical path. What should you do first?

⚠ Common exam trap

A common mix-up: candidates confuse the immediate need to assess impact (Option A) with the formal first step of submitting a change request, failing to recognize that the change control process must be initiated before any analysis or action is taken.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to formally assess the impact on scope, schedule, and cost

When a new regulation impacts project deliverables and the critical path, the first step is to submit a formal change request. This initiates the integrated change control process, ensuring that the impact on scope, schedule, and cost is assessed through a structured review before any action is taken. Bypassing this formal process risks uncontrolled changes and non-compliance with project governance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the risk register and assess the impact on the critical path

    Why it's wrong here

    This is part of the analysis, but the first step should be initiating a change request.

  • Submit a change request to formally assess the impact on scope, schedule, and cost

    Why this is correct

    Following the change control process ensures proper evaluation and approval.

  • Direct the team to immediately implement the changes to ensure compliance

    Why it's wrong here

    Changes should go through formal assessment and approval first.

  • Inform the team to continue working as planned since the regulation may not be enforced

    Why it's wrong here

    Ignoring regulatory changes can expose the project to legal risks.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.