Arrange the steps for controlling project changes.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Receive change request, Log change request, Evaluate change request, Submit to CCB, Implement if approved
Change control process: receive, log, evaluate, submit to CCB, and implement if approved.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Receive change request, Log change request, Evaluate change request, Submit to CCB, Implement if approved
Why this is correct
This sequence accurately reflects the structured change control process. A change request must first be formally received to initiate the process. It is then logged into a change management system for tracking and historical record-keeping. Subsequent evaluation assesses its impact on scope, schedule, cost, and quality before presentation to the Change Control Board (CCB) for a formal decision. Implementation only occurs upon explicit approval, ensuring controlled execution.
- ✗
Log change request, Receive change request, Evaluate change request, Submit to CCB, Implement if approved
Why it's wrong here
This order is fundamentally flawed because a change request cannot be logged or formally recorded before it has been officially received. The act of logging presupposes the existence of a tangible request document or communication. Attempting to log a non-existent or unreceived request violates basic data entry and process initiation principles, rendering the tracking system ineffective from the outset.
- ✗
Receive change request, Evaluate change request, Log change request, Submit to CCB, Implement if approved
Why it's wrong here
This sequence is incorrect because it places evaluation before logging. While a request is received, it must be formally logged into the change management system prior to any detailed evaluation. Logging ensures that every request is documented, assigned a unique identifier, and becomes part of the project's official record, providing traceability and preventing loss of critical information during the subsequent impact analysis.
- ✗
Receive change request, Log change request, Submit to CCB, Evaluate change request, Implement if approved
Why it's wrong here
This order is incorrect because it prematurely submits the change request to the Change Control Board (CCB) before a thorough evaluation has been conducted. The CCB relies on the detailed impact analysis, including assessments of scope, schedule, cost, and risk, to make an informed decision. Presenting a request without this crucial evaluation data prevents the CCB from properly understanding the implications and making a responsible approval or rejection.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Change Control Process
A formal, structured procedure used to manage any changes to a project's scope, schedule, budget, or requirements, ensuring every modification is reviewed, approved, tested, and documented before implementation.
About these practice questions
One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.