Question 532 of 892
People — Leading ProjectshardMultiple SelectObjective-mapped

Quick Answer

The correct answer is that the product owner adds the new work to the product backlog and prioritizes it for the next sprint. This aligns with the Scrum framework because the sprint backlog is a frozen commitment for the current time-box; introducing a mid-sprint change would disrupt the team’s focus and jeopardize the sprint goal. The other valid option is canceling the sprint only if the sprint goal becomes obsolete, which is a rare, deliberate action. On the PMP exam, this question tests your understanding of the Product Owner’s role in balancing emergent value with sprint stability—a common trap is assuming the team must accept the change immediately. Remember the key principle: the sprint is a shield, not a sponge. For a quick memory tip, think “New work waits; only obsolete goals cancel.”

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

An agile project team is in the middle of a sprint when the product owner introduces a high-priority change that was not part of the sprint backlog. The team is concerned about their ability to deliver the sprint goal. Which TWO options align with the Scrum framework? (Choose two.)

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The product owner cancels the current sprint and starts a new sprint with the revised backlog

Option A is correct because the Scrum framework explicitly allows the Product Owner to cancel a sprint if the Sprint Goal becomes obsolete, such as when a high-priority change emerges that invalidates the current goal. Cancelling the sprint and starting a new one with the revised backlog ensures the team focuses on the highest-value work without disrupting the sprint's time-box or overloading the team. Option E is correct because the Product Owner can add the new work to the Product Backlog and prioritize it for the next sprint, which respects the current Sprint's commitment and allows the team to complete the Sprint Goal without interruption.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The product owner cancels the current sprint and starts a new sprint with the revised backlog

    Why this is correct

    Cancelling a sprint is allowed in Scrum when the sprint goal becomes obsolete.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Replace the least important sprint backlog item with the new work and adjust the sprint goal accordingly

    Why it's wrong here

    Swapping items mid-sprint undermines the team's commitment and may cause rework.

  • Instruct the team to include the new work in the current sprint and extend the sprint duration

    Why it's wrong here

    Extending sprint length is not a standard Scrum practice; it violates time-boxing.

  • Add the new work to the sprint backlog and ask the team to work overtime

    Why it's wrong here

    Adding work mid-sprint is not recommended; it compromises the sprint goal and team commitment.

  • The product owner adds the new work to the product backlog and prioritizes it for the next sprint

    Why this is correct

    This maintains the integrity of the current sprint and allows proper prioritization.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the Product Owner's authority to re-prioritize the Product Backlog with the ability to change the Sprint Backlog mid-sprint, leading them to select options like B or D that violate the Sprint's immutability and the team's commitment to the Sprint Goal.

Detailed technical explanation

How to think about this question

Under the Scrum Guide, the Sprint Backlog is a plan made visible and is considered frozen during the Sprint to protect the team from scope creep and to maintain focus on the Sprint Goal. The Product Owner has the authority to cancel a Sprint only if the Sprint Goal becomes obsolete, which is a rare event typically driven by a major market shift or critical defect. In practice, cancellation is disruptive and should be used sparingly; the preferred approach is to defer the new work to the next Sprint via Product Backlog refinement, as in Option E, which aligns with the empirical process control of Scrum.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The product owner cancels the current sprint and starts a new sprint with the revised backlog — Option A is correct because the Scrum framework explicitly allows the Product Owner to cancel a sprint if the Sprint Goal becomes obsolete, such as when a high-priority change emerges that invalidates the current goal. Cancelling the sprint and starting a new one with the revised backlog ensures the team focuses on the highest-value work without disrupting the sprint's time-box or overloading the team. Option E is correct because the Product Owner can add the new work to the Product Backlog and prioritize it for the next sprint, which respects the current Sprint's commitment and allows the team to complete the Sprint Goal without interruption.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.