Question 535 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is using a hybrid approach. A key stakeholder requests a significant scope change that would affect the critical path. The change request has been submitted and approved. What should the project manager do next?

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan and baselines to reflect the approved change

In a hybrid project, once a scope change is approved, the project manager must update the project management plan and baselines (scope, schedule, cost) to formally integrate the change. This ensures all future work aligns with the new approved scope and maintains traceability. Option D is correct because it follows the Perform Integrated Change Control process, which requires updating the plan and baselines before implementation.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Wait until the next sprint planning to introduce the change to the team

    Why it's wrong here

    Delaying the update can cause confusion and misalignment.

  • Notify the sponsor and update the risk register

    Why it's wrong here

    Updating the risk register is good, but the primary action is to update the project management plan.

  • Inform the team about the change and ask them to adjust their work accordingly

    Why it's wrong here

    While communication is important, the PM must first formally update the project management plan and baselines.

  • Update the project management plan and baselines to reflect the approved change

    Why this is correct

    After change approval, the PM must update all relevant project documents to maintain a single source of truth.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse 'informing the team' (Option C) as the immediate next step, but PMI emphasizes that updating the plan and baselines is the formal, required action before any implementation or communication to the team.

Trap categories for this question

  • Similar concept trap

    Delaying the update can cause confusion and misalignment.

Detailed technical explanation

How to think about this question

Under the hood, the Perform Integrated Change Control process (PMBOK Guide 4.6) requires that all approved changes be reflected in the project management plan and project documents before execution. In a hybrid model, this often involves updating the product backlog, sprint backlog, and the project schedule baseline to account for the critical path impact. A real-world scenario: if a stakeholder approves adding a new feature that extends the critical path by 2 weeks, the project manager must update the schedule baseline and communicate the new timeline to the team before any work begins.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Update the project management plan and baselines to reflect the approved change — In a hybrid project, once a scope change is approved, the project manager must update the project management plan and baselines (scope, schedule, cost) to formally integrate the change. This ensures all future work aligns with the new approved scope and maintains traceability. Option D is correct because it follows the Perform Integrated Change Control process, which requires updating the plan and baselines before implementation.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.