Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

Your project is using a hybrid approach. A key stakeholder requests a significant scope change that would affect the critical path. The change request has been submitted and approved. What should the project manager do next?

⚠ Common exam trap

Test-takers frequently confuse 'informing the team' (Option C) as the immediate next step, but PMI emphasizes that updating the plan and baselines is the formal, required action before any implementation or communication to the team.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan and baselines to reflect the approved change

In a hybrid project, once a scope change is approved, the project manager must update the project management plan and baselines (scope, schedule, cost) to formally integrate the change. This ensures all future work aligns with the new approved scope and maintains traceability. Option D is correct because it follows the Perform Integrated Change Control process, which requires updating the plan and baselines before implementation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Wait until the next sprint planning to introduce the change to the team

    Why it's wrong here

    This option is incorrect because delaying communication of an approved change until the next sprint planning session violates the principle of timely information dissemination. Approved changes impact ongoing work and future planning, and immediate updates are crucial to prevent team members from working on outdated requirements or plans, leading to rework, wasted effort, and potential misalignment with project objectives.

  • Notify the sponsor and update the risk register

    Why it's wrong here

    While notifying the sponsor and updating the risk register might be subsequent or related actions, they are not the primary and most immediate step after a change has been formally approved. The core requirement for an approved change is to formally integrate it into the project's governing documents. Updating only the risk register without updating the foundational project management plan and baselines leaves the project without an accurate, single source of truth for the approved scope, schedule, or cost.

  • Inform the team about the change and ask them to adjust their work accordingly

    Why it's wrong here

    Directly informing the team to adjust their work without first formally updating the project management plan and baselines is a critical oversight. While team communication is essential, it must follow the formal documentation of the approved change. Without updated baselines and plans, the team lacks official guidance, and their adjustments would be based on informal instructions rather than controlled, approved project documentation, potentially leading to scope creep or unapproved deviations.

  • Update the project management plan and baselines to reflect the approved change

    Why this is correct

    This is the correct action because, following formal approval by the Change Control Board (CCB), the project management plan and its subsidiary baselines (scope, schedule, cost) must be immediately updated. This ensures that all project documentation reflects the current, approved state of the project, maintaining a single source of truth. This formal update is crucial for controlling the project, communicating accurate information, and preventing future discrepancies or unauthorized work.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.