Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

During a sprint retrospective, the team expresses frustration that they are frequently interrupted by unplanned support requests from the operations department. The product owner agrees this is impacting velocity. What should the project manager do FIRST?

⚠ Common exam trap

Candidates often choose to escalate (Option B) or defer action (Option C) instead of recognizing that the product owner is the correct stakeholder to collaborate with for immediate prioritization and capacity planning.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work with the product owner to prioritize support requests and allocate a dedicated buffer for them.

The immediate priority is to manage the unplanned work that is disrupting the sprint. By working with the product owner to prioritize support requests and allocate a dedicated buffer (e.g., a fixed capacity within the sprint backlog), the project manager ensures that the team can handle operational interruptions without derailing planned work. This aligns with the Agile principle of protecting the team's focus and using empirical data to adjust the process, rather than escalating or deferring action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Work with the product owner to prioritize support requests and allocate a dedicated buffer for them.

    Why this is correct

    This is the most effective agile approach because it involves the Product Owner (PO) in managing the product backlog, which encompasses all work, including support. By prioritizing support requests and allocating a dedicated buffer (e.g., a percentage of sprint capacity or a rotating team member), the team can proactively manage interruptions without derailing sprint goals. This strategy protects the team's focus and morale while ensuring critical support needs are addressed in a structured manner.

  • Escalate the issue to the project sponsor to negotiate with operations.

    Why it's wrong here

    Escalating the issue directly to the project sponsor is premature and bypasses the Scrum Master's (or PMP's) responsibility to facilitate resolution at a lower level first. Such an action suggests a failure to leverage team-level problem-solving or collaboration with the Product Owner, which are fundamental agile practices. Escalation should be reserved for intractable impediments that cannot be resolved within the team's immediate sphere of influence, not as a first response to a common operational challenge.

  • Ask the team to track the time spent on support requests and report it at the next retrospective.

    Why it's wrong here

    While data collection can be valuable for long-term analysis, simply asking the team to track time without an immediate plan for action defers resolution and prolongs the team's frustration. The retrospective has already identified the problem, indicating a need for immediate intervention rather than just more data. This approach fails to provide any immediate relief or a concrete path forward to address the ongoing interruptions and their impact on sprint commitments.

  • Instruct the team to handle support requests as they come to maintain stakeholder satisfaction.

    Why it's wrong here

    Instructing the team to handle support requests as they come directly contradicts agile principles of focused work and sprint goals, leading to constant context switching and reduced productivity. This reactive approach prioritizes immediate, unmanaged stakeholder satisfaction over planned sprint commitments, ultimately harming the team's ability to deliver on its sprint goals. Uncontrolled interruptions lead to burnout, decreased morale, and an inability to predict or commit to future work effectively.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.