Question 327 of 892
People — Leading ProjectshardMultiple SelectObjective-mapped

Quick Answer

The answer is to initiate a change request through the Integrated Change Control process, communicate the requirement to stakeholders, and assess the impact on the project constraints. This trio of actions is correct because a new mandatory regulatory requirement constitutes a formal change to the project’s scope baseline, and in a hybrid project, the Integrated Change Control process ensures that all changes are evaluated for their effect on cost, schedule, and quality before approval. On the PMP exam, this scenario tests your understanding of how to handle compliance-driven changes within a hybrid framework, where both predictive and adaptive practices apply. A common trap is to assume that mandatory requirements bypass change control; in reality, even regulatory mandates must follow the formal process to document the impact and secure authorization. Remember the mnemonic “CIA” for this situation: Communicate the change, Initiate the change request, and Assess the impact analysis.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is leading a complex software development project using a hybrid approach. A new regulatory requirement has been discovered that affects the project's scope. The requirement is mandatory and must be implemented before the project can close. Which THREE actions should the project manager take? (Choose three.)

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Communicate the new requirement to the project team and relevant stakeholders

Option B is correct because in a hybrid project, the project manager must first communicate the new mandatory regulatory requirement to the project team and relevant stakeholders to ensure awareness and alignment before any action is taken. This aligns with the PMBOK Guide's emphasis on stakeholder engagement and transparent communication when scope changes are discovered, especially for compliance-driven mandates.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately adjust the project budget and schedule to accommodate the requirement

    Why it's wrong here

    Adjustments must be approved through change control first.

  • Communicate the new requirement to the project team and relevant stakeholders

    Why this is correct

    Transparent communication keeps everyone informed.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Assign the new requirement to the development team to start work immediately

    Why it's wrong here

    Work should not start without approved change request.

  • Analyze the impact of the new requirement on the project schedule, budget, and resources

    Why this is correct

    Impact analysis is necessary to inform decisions.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Initiate a change request through the Integrated Change Control process

    Why this is correct

    All scope changes require formal change control.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may assume a mandatory requirement can be implemented immediately without formal change control, confusing urgency with the need for proper impact analysis and stakeholder communication.

Detailed technical explanation

How to think about this question

In a hybrid approach, the project manager must balance predictive controls (like formal change requests) with agile flexibility. The mandatory regulatory requirement triggers a change request that must be evaluated for its effect on the project's baseline—schedule, cost, and scope—before implementation. This ensures compliance without destabilizing ongoing iterations or violating the project's governance framework.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Communicate the new requirement to the project team and relevant stakeholders — Option B is correct because in a hybrid project, the project manager must first communicate the new mandatory regulatory requirement to the project team and relevant stakeholders to ensure awareness and alignment before any action is taken. This aligns with the PMBOK Guide's emphasis on stakeholder engagement and transparent communication when scope changes are discovered, especially for compliance-driven mandates.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.