Question 109 of 892
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In a Scrum team, the product owner frequently changes priorities within a sprint, causing the team to abandon work mid-task. The team is becoming demotivated. What should the scrum master do?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Coach the product owner on the impact of changing priorities mid-sprint and reinforce the sprint backlog agreement

Option D is correct because the Scrum Master's primary role is to coach the Product Owner and the team on Scrum principles, including the importance of a stable Sprint Backlog. Changing priorities mid-sprint violates the Sprint Goal and undermines team focus, leading to demotivation. By reinforcing the Sprint Backlog agreement, the Scrum Master protects the team from disruption while respecting the Product Owner's authority outside the sprint.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the project sponsor to overrule the product owner

    Why it's wrong here

    Escalation should be after coaching and within the Scrum framework.

  • Shorten the sprint length to two or three days to accommodate frequent changes

    Why it's wrong here

    Shorter sprints may increase overhead and still not address the root cause.

  • Accept the changes as the product owner has authority over priorities

    Why it's wrong here

    The scrum master should protect the sprint goal and ensure stability.

  • Coach the product owner on the impact of changing priorities mid-sprint and reinforce the sprint backlog agreement

    Why this is correct

    Coaching aligns with the scrum master's role as a servant leader and process guardian.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may confuse the Product Owner's authority over the Product Backlog with the ability to change the Sprint Backlog mid-sprint, leading them to incorrectly accept the changes (Option C) instead of recognizing the Scrum Master's duty to enforce the sprint boundary.

Detailed technical explanation

How to think about this question

In Scrum, the Sprint Backlog is a plan made by the Development Team to achieve the Sprint Goal, and it is considered frozen once the sprint starts. The Product Owner can reorder the Product Backlog at any time, but cannot force changes to the Sprint Backlog without canceling the sprint entirely. The Scrum Master acts as a servant leader to ensure the team adheres to this agreement, preventing the 'churn' that destroys velocity and morale.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Coach the product owner on the impact of changing priorities mid-sprint and reinforce the sprint backlog agreement — Option D is correct because the Scrum Master's primary role is to coach the Product Owner and the team on Scrum principles, including the importance of a stable Sprint Backlog. Changing priorities mid-sprint violates the Sprint Goal and undermines team focus, leading to demotivation. By reinforcing the Sprint Backlog agreement, the Scrum Master protects the team from disruption while respecting the Product Owner's authority outside the sprint.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.