Question 503 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are the project manager for a construction project. A key vendor notifies you that they cannot deliver a critical component on time, which will delay the project by at least two weeks. The vendor was already on the risk register with a contingency plan. What should you do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

  • Clue: "least"

    Why it matters: You want the option with minimum overhead, fewest steps, or lowest impact — not the most feature-rich or comprehensive answer.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Activate the contingency plan outlined in the risk register

D is correct because the risk was already identified and documented in the risk register with a pre-defined contingency plan. According to the PMBOK Guide, when a risk occurs, the first action is to implement the contingency plan if one exists, as it is the planned response to the specific risk event. This ensures a structured, pre-approved approach without unnecessary delays or escalation.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately contact alternative vendors to find a replacement

    Why it's wrong here

    You should first check the contingency plan before taking new actions.

  • Update the project schedule to reflect the delay and notify stakeholders

    Why it's wrong here

    Updating the schedule is a later step; first implement the contingency plan.

  • Inform the project sponsor of the delay and ask for guidance

    Why it's wrong here

    The PM should act on the planned response before escalating.

  • Activate the contingency plan outlined in the risk register

    Why this is correct

    The risk was identified and planned for; the PM should implement the contingency plan.

    Clue confirmation

    The clue words "first", "least" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often jump to reactive actions like finding a new vendor or updating the schedule, forgetting that the risk register already contains a pre-approved response that should be executed first.

Detailed technical explanation

How to think about this question

In risk management, a contingency plan is a specific set of actions to be taken if a risk occurs, often including pre-identified triggers and resources. The risk register documents the risk, its probability, impact, and the planned response, which may involve a fallback plan, workaround, or alternative vendor. Activating the contingency plan first ensures alignment with the project's risk management strategy and avoids ad-hoc decisions that could introduce new risks or violate procurement agreements.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Activate the contingency plan outlined in the risk register — D is correct because the risk was already identified and documented in the risk register with a pre-defined contingency plan. According to the PMBOK Guide, when a risk occurs, the first action is to implement the contingency plan if one exists, as it is the planned response to the specific risk event. This ensures a structured, pre-approved approach without unnecessary delays or escalation.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first", "least". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.