- A
Immediately contact alternative vendors to find a replacement
Why wrong: You should first check the contingency plan before taking new actions.
- B
Update the project schedule to reflect the delay and notify stakeholders
Why wrong: Updating the schedule is a later step; first implement the contingency plan.
- C
Inform the project sponsor of the delay and ask for guidance
Why wrong: The PM should act on the planned response before escalating.
- D
Activate the contingency plan outlined in the risk register
The risk was identified and planned for; the PM should implement the contingency plan.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are the project manager for a construction project. A key vendor notifies you that they cannot deliver a critical component on time, which will delay the project by at least two weeks. The vendor was already on the risk register with a contingency plan. What should you do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Clue:
"least"Why it matters: You want the option with minimum overhead, fewest steps, or lowest impact — not the most feature-rich or comprehensive answer.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Activate the contingency plan outlined in the risk register
D is correct because the risk was already identified and documented in the risk register with a pre-defined contingency plan. According to the PMBOK Guide, when a risk occurs, the first action is to implement the contingency plan if one exists, as it is the planned response to the specific risk event. This ensures a structured, pre-approved approach without unnecessary delays or escalation.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Immediately contact alternative vendors to find a replacement
Why it's wrong here
You should first check the contingency plan before taking new actions.
- ✗
Update the project schedule to reflect the delay and notify stakeholders
Why it's wrong here
Updating the schedule is a later step; first implement the contingency plan.
- ✗
Inform the project sponsor of the delay and ask for guidance
Why it's wrong here
The PM should act on the planned response before escalating.
- ✓
Activate the contingency plan outlined in the risk register
Why this is correct
The risk was identified and planned for; the PM should implement the contingency plan.
Clue confirmation
The clue words "first", "least" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often jump to reactive actions like finding a new vendor or updating the schedule, forgetting that the risk register already contains a pre-approved response that should be executed first.
Detailed technical explanation
How to think about this question
In risk management, a contingency plan is a specific set of actions to be taken if a risk occurs, often including pre-identified triggers and resources. The risk register documents the risk, its probability, impact, and the planned response, which may involve a fallback plan, workaround, or alternative vendor. Activating the contingency plan first ensures alignment with the project's risk management strategy and avoids ad-hoc decisions that could introduce new risks or violate procurement agreements.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Activate the contingency plan outlined in the risk register — D is correct because the risk was already identified and documented in the risk register with a pre-defined contingency plan. According to the PMBOK Guide, when a risk occurs, the first action is to implement the contingency plan if one exists, as it is the planned response to the specific risk event. This ensures a structured, pre-approved approach without unnecessary delays or escalation.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first", "least". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.