Courseiva
People — Leading ProjectshardMultiple SelectObjective-mapped

PMP People — Leading Projects Practice Question

Your project is using a hybrid approach. The client has requested a change that would significantly alter the product's core functionality. The change is not aligned with the project's business case. Which TWO actions should the project manager take?

⚠ Common exam trap

PMI often tests the misconception that the project manager should immediately submit a change request to the CCB (Option A) without first consulting stakeholders or understanding the business impact, leading candidates to overlook the need for escalation and discussion.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Consult with the project sponsor or steering committee for guidance.

When a proposed change conflicts with the project's business case, the project manager should escalate to the project sponsor or steering committee, who have the authority to approve deviations from the business case. Option D is correct because the project manager must first discuss the impact of the change with the client to ensure they understand the implications on business objectives before any formal action is taken. This aligns with the PMI's emphasis on stakeholder engagement and maintaining alignment with the business case in a hybrid approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request to the CCB and let them decide.

    Why it's wrong here

    Submitting a change request directly to the Change Control Board (CCB) without prior analysis and stakeholder consultation is premature. The Project Manager (PM) is responsible for assessing the impact on the business case, project objectives, and strategic alignment, and then discussing these implications with key stakeholders like the client and sponsor. The CCB's role is to review well-vetted proposals, not to initiate the strategic assessment of a significant change.

  • Consult with the project sponsor or steering committee for guidance.

    Why this is correct

    Consulting with the project sponsor or steering committee is a critical first step when a proposed change significantly impacts the project's business case or strategic objectives. These stakeholders possess the organizational authority and strategic perspective to evaluate the change's alignment with broader organizational goals and provide guidance on whether to proceed with further analysis or formal change control processes. Their input ensures the project remains aligned with strategic intent.

  • Reject the change outright because it is not in the business case.

    Why it's wrong here

    Rejecting a client's proposed change outright, simply because it deviates from the original business case, is an uncollaborative approach that can severely damage client relationships and project goodwill. A Project Manager (PM) should always engage in discussion to understand the client's underlying need, assess the potential value, and explore alternative solutions or the implications of incorporating such a change before making any definitive decision. This fosters trust and allows for informed strategic choices.

  • Discuss with the client the impact of the change on the business case and project objectives.

    Why this is correct

    Discussing the proposed change's impact on the business case and project objectives directly with the client is fundamental for effective stakeholder management and informed decision-making. This conversation allows the Project Manager (PM) to ensure the client fully understands the potential implications, such as cost increases, schedule delays, or scope adjustments, and helps to collaboratively determine if the change's value outweighs its impact. This proactive communication aligns expectations and fosters a shared understanding of project direction.

  • Update the business case to reflect the change and proceed.

    Why it's wrong here

    Unilaterally updating the business case and proceeding with a significant change is a severe breach of project governance and control. The business case is a foundational document that justifies the project's existence and requires formal approval from the project sponsor, steering committee, or other relevant organizational authorities before any substantive modifications can be implemented. A Project Manager (PM) does not have the authority to make such strategic decisions independently.

Go deeper

Related to this question

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.