PMP People — Leading Projects Practice Question

An executive stakeholder has been directly assigning tasks to your agile team members without going through you or the product owner. Team members are confused about priorities and the sprint goal is at risk. What is the best first step?

⚠ Common exam trap

Many exam-takers choose to escalate immediately (Option C) or update a plan (Option D) instead of directly engaging the stakeholder, failing to recognize that the PMP emphasizes proactive communication and conflict resolution at the lowest level first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request a meeting with the executive to clarify roles and the importance of adhering to the prioritization process

The first step in resolving a stakeholder bypassing the agile process is to directly address the root cause—misunderstanding of roles. Requesting a meeting with the executive allows you to clarify the prioritization process, reinforce the product owner's authority over the backlog, and protect the sprint goal without escalating prematurely. This aligns with the PMP's focus on stakeholder engagement and conflict resolution at the lowest appropriate level.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request a meeting with the executive to clarify roles and the importance of adhering to the prioritization process

    Why this is correct

    This is the most appropriate first step as it demonstrates proactive communication and conflict resolution. The project manager (PM) should directly engage the executive to explain the established project governance, the impact of bypassing the prioritization process on project objectives, and the importance of maintaining team focus and morale. This approach seeks to educate and align the stakeholder with project protocols, preventing future recurrences and protecting project integrity.

  • Tell the team members to ignore the stakeholder's requests

    Why it's wrong here

    Instructing team members to ignore an executive stakeholder's direct requests is highly unprofessional and politically dangerous. This action undermines the executive's authority, creates potential conflict, and could lead to a breakdown in trust and communication within the organization. The project manager's role is to facilitate collaboration and manage stakeholder expectations, not to create an adversarial environment with senior leadership.

  • Escalate to the project sponsor immediately

    Why it's wrong here

    Immediate escalation to the project sponsor without first attempting direct resolution with the executive stakeholder is premature and bypasses a critical step in conflict management. The project manager should always attempt to resolve issues at the lowest possible level of authority through direct communication. Escalation should be reserved for situations where direct communication has failed, or the issue's impact is severe enough to warrant immediate higher-level intervention.

  • Update the stakeholder management plan to classify the executive as 'keep satisfied'

    Why it's wrong here

    While regularly updating the stakeholder management plan is a good practice, merely reclassifying the executive as 'keep satisfied' does not address the immediate operational problem of direct task assignments. This action is a documentation update, not a proactive solution to the behavioral issue impacting project execution and team workflow. The plan needs to reflect reality, but the PM's priority is to actively manage the situation and prevent further disruption.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.