Courseiva
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

A project manager is leading a Scrum team. The product owner frequently changes priorities mid-sprint, causing the team to lose focus and miss sprint goals. The team is frustrated. What should the project manager do?

⚠ Common exam trap

Watch out — candidates often choose Option A (adding a buffer) because it seems pragmatic, but it violates Scrum's time-boxing and fails to address the underlying stakeholder behavior, which is a key agile coaching responsibility.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Coach the product owner on Scrum rules and the impact of mid-sprint changes on team focus

In Scrum, the product owner should not change priorities during a sprint; the sprint backlog is frozen once the sprint starts. The project manager, acting as a servant leader, should coach the product owner on Scrum rules and explain how mid-sprint changes disrupt team focus and jeopardize sprint goals. This aligns with the PMP's emphasis on stakeholder management and agile principles.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add a buffer in the sprint to accommodate potential changes

    Why it's wrong here

    Adding a buffer to the sprint to accommodate potential changes is a reactive measure that normalizes undesirable behavior rather than addressing its root cause. This approach undermines the core Scrum principle of sprint stability and the team's commitment to a sprint goal, encouraging the Product Owner to continue introducing mid-sprint changes. It ultimately reduces predictability, obscures true velocity, and prevents the team from focusing on delivering a defined increment.

  • Coach the product owner on Scrum rules and the impact of mid-sprint changes on team focus

    Why this is correct

    Coaching the Product Owner on Scrum rules and the detrimental impact of mid-sprint changes on team focus is the most appropriate initial action. As a Project Manager or Scrum Master, it is crucial to educate stakeholders about the importance of sprint commitment, the disruption caused by scope creep, and how it affects team morale, predictability, and the ability to achieve the sprint goal. This proactive communication fosters understanding and adherence to agile principles.

  • Ask the team to accommodate the changes since the product owner has authority

    Why it's wrong here

    Asking the team to accommodate changes simply because the Product Owner has authority misinterprets Scrum roles and violates the team's sprint commitment. While the Product Owner manages the Product Backlog, the Development Team commits to the Sprint Backlog, and mid-sprint changes disrupt their self-organization and focus. Forcing such accommodations demotivates the team, undermines their autonomy, and can lead to burnout and decreased quality.

  • Escalate the issue to the project sponsor to intervene

    Why it's wrong here

    Escalating the issue to the project sponsor to intervene is a premature step and should be reserved as a last resort. The Project Manager's primary responsibility in an agile environment is to facilitate communication and resolve impediments at the team level first. Bypassing direct coaching and conflict resolution opportunities undermines the team's ability to self-manage and learn, indicating a failure to exhaust internal solutions before involving higher authority.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.