Question 62 of 892
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is to empower the team to make decisions within agreed boundaries and check in periodically. This is correct because a team in the performing stage of Tuckman’s model operates with high trust, autonomy, and self-organization, so micromanagement would disrupt their flow and damage morale. Empowering them leverages their maturity, while periodic check-ins provide necessary oversight without undermining their independence, aligning with servant leadership principles. On the Project Management Professional PMP exam, this scenario tests your understanding of situational leadership and the Tuckman ladder—specifically, that performing-stage teams require delegation, not direction. A common trap is choosing “assign a temporary leader,” which implies a regression to the storming stage. To ensure team productivity when the project manager is on vacation, remember the memory tip: “Performing teams need permission, not protection.”

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project team is in the performing stage of development. The project manager is leaving for a two-week vacation. What is the best way to ensure the team remains productive?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Empower the team to make decisions within agreed boundaries and check in periodically.

Option D is correct because the team is in the performing stage, characterized by high autonomy, trust, and self-organization. Empowering the team to make decisions within agreed boundaries leverages their maturity and maintains productivity, while periodic check-ins provide necessary oversight without micromanagement. This approach aligns with the Tuckman model and servant leadership principles, ensuring the team remains effective in the project manager's absence.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Appoint a temporary project manager to oversee the team.

    Why it's wrong here

    The team is capable of self-management; a new manager may reduce efficiency.

  • Ask the team to pause all non-urgent decisions until your return.

    Why it's wrong here

    May cause unnecessary delays and reduce team autonomy.

  • Schedule daily status calls to monitor progress.

    Why it's wrong here

    Too intrusive and may undermine team's self-sufficiency.

  • Empower the team to make decisions within agreed boundaries and check in periodically.

    Why this is correct

    Leverages the performing stage's maturity and maintains productivity.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the misconception that a performing team still requires direct oversight or a formal leader replacement, when in fact the correct approach is to empower the team and trust their established processes.

Detailed technical explanation

How to think about this question

In the performing stage of Tuckman's model, team members are highly competent, collaborative, and capable of resolving conflicts independently. The project manager should transition from a directing role to a supporting role, using delegation and empowerment to maintain high performance. Real-world application includes setting clear decision-making boundaries (e.g., budget limits, scope constraints) and using periodic check-ins (e.g., weekly stand-ups) to monitor progress without stifling autonomy, which is critical for sustaining velocity in agile or hybrid environments.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Empower the team to make decisions within agreed boundaries and check in periodically. — Option D is correct because the team is in the performing stage, characterized by high autonomy, trust, and self-organization. Empowering the team to make decisions within agreed boundaries leverages their maturity and maintains productivity, while periodic check-ins provide necessary oversight without micromanagement. This approach aligns with the Tuckman model and servant leadership principles, ensuring the team remains effective in the project manager's absence.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.