Question 508 of 892
People — Leading ProjectshardMultiple SelectObjective-mapped

Quick Answer

The answer is to provide the stakeholder with early access to project dashboards and reports, invite them to relevant meetings and decision points, and establish a tailored communication schedule. This trio of actions directly addresses the core of dissatisfied stakeholder communication by ensuring the stakeholder is no longer left out of decisions and receives timely information, which aligns with the PMP focus on stakeholder engagement and the Communications Management Plan. On the Project Management Professional PMP exam, this scenario tests your ability to apply proactive stakeholder analysis and the Plan Communications Management process, often appearing as a situational question where the trap is choosing a generic “update the communications plan” without specific, actionable steps. A common memory tip is the “3 I’s” for stakeholder dissatisfaction: Include them in meetings, Inform them early with dashboards, and Individualize the communication schedule.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a project manager discovers that a key stakeholder is dissatisfied with the team's communication. The stakeholder feels left out of decisions and receives information too late. Which THREE actions should the project manager take to address this?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Invite the stakeholder to relevant project meetings and decision points.

Option A is correct because inviting the stakeholder to relevant meetings and decision points directly addresses their feeling of being left out. This action ensures the stakeholder is included in the communication loop and can participate in decisions that affect them, which is a key aspect of stakeholder engagement in project management.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Invite the stakeholder to relevant project meetings and decision points.

    Why this is correct

    Increases engagement and transparency.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Update the communications management plan to include the stakeholder's preferred frequency and channels.

    Why this is correct

    Tailors communication to stakeholder needs.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Wait until the next stakeholder feedback cycle to address concerns.

    Why it's wrong here

    Delays resolution and risks escalation.

  • Reduce the number of status meetings to avoid information overload.

    Why it's wrong here

    May further alienate the stakeholder.

  • Provide the stakeholder with early access to project dashboards and reports.

    Why this is correct

    Empowers the stakeholder with timely information.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think waiting for the next feedback cycle (Option C) is a standard process, but in reality, urgent stakeholder concerns require immediate action to prevent escalation.

Detailed technical explanation

How to think about this question

In project management, the Communications Management Plan should be a living document that is updated as stakeholder needs change. Proactively adjusting the plan to include the stakeholder's preferred frequency and channels (Option B) ensures that communication is tailored to their expectations, which is a core principle of the PMBOK Guide's Stakeholder Engagement process. Providing early access to dashboards and reports (Option E) empowers the stakeholder with timely information, reducing the lag that caused their dissatisfaction.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Invite the stakeholder to relevant project meetings and decision points. — Option A is correct because inviting the stakeholder to relevant meetings and decision points directly addresses their feeling of being left out. This action ensures the stakeholder is included in the communication loop and can participate in decisions that affect them, which is a key aspect of stakeholder engagement in project management.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.