Process — Managing Technical Aspects

Practise Project Management Professional PMP Process — Managing Technical Aspects practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

389 questions84 easy201 medium104 hard

Focused practice

Practice Process — Managing Technical Aspects questions

Scored sessions drawing only from this domain — pick a length below.

Start 20-question practice test →

What this domain covers

What to know about Process — Managing Technical Aspects

Process — Managing Technical Aspects questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Process — Managing Technical Aspects exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Question index

All Process — Managing Technical Aspects questions (389)

Click any question to see the full explanation, or start a practice session above.

1

During project execution, a key executive stakeholder bypasses you and gives direct instructions to the development team, causing confusion about priorities. What should you do FIRST?

Medium
2

During a daily standup, a developer mentions a technical issue that will likely delay a user story by three days. What is the BEST action for the Scrum Master to take?

Easy
3

An executive stakeholder bypasses you and directly gives instructions to the development team to add a new report. The team starts working on it. What should you do?

Medium
4

You are managing a software development project using a hybrid approach. The project has a fixed price contract with a strict deadline. Midway through, the customer requests a significant change that would increase the scope by 20%. You have already used all management reserve. What should you do FIRST?

Medium
5

You are managing a software development project using a hybrid approach. In the middle of a sprint, you discover that a team member has been working on a feature that was de-scoped in the last sprint review. The team member claims the product owner informally agreed to add it back. What should you do FIRST?

Medium
6

You are managing a software upgrade project. During a team meeting, two senior developers get into a heated argument over the best technical approach for a critical component. The disagreement is delaying progress. As the project manager, what should you do FIRST?

Medium
7

In a hybrid project, the development team is self-organizing but a senior developer consistently misses sprint commitments. The product owner is frustrated. What should the project manager do first?

Medium
8

Your construction project is 40% complete. The Earned Value Analysis shows CPI = 0.85 and SPI = 0.90. The project budget is $5M. A key vendor just informed you they cannot deliver a critical component on time, causing a 3-week delay. The component is on the critical path. What is the BEST action?

Hard
9

You are the project manager for a large infrastructure upgrade project. The project involves deploying new servers across multiple data centers. During the execution phase, you receive a report that one of the critical servers has failed a security compliance test. The security team states that the server must be reconfigured and retested, which will take two days. However, this server is on the critical path and any delay will push the project completion date. Your sponsor is pressing you to meet the original deadline. The project has a contingency reserve for schedule risks. What is the best course of action?

Hard
10

You are the project manager for a marketing campaign. During the planning phase, you identify a risk that a key graphic designer may leave the company. You decide to cross-train another team member as a backup. This is an example of which risk response?

Easy
11

You are managing a construction project. The sponsor has requested that you skip the testing phase to save time and meet an aggressive deadline. What should you do FIRST?

Medium
12

During the closure phase of a project, the customer is satisfied with the deliverables but refuses to sign the formal acceptance document, citing minor issues that were not part of the original scope. What should the project manager do FIRST?

Medium
13

You are a project manager for a construction project that is experiencing delays due to unexpected soil conditions. The risk was identified and a contingency plan exists. Which TWO actions should you take?

Medium
14

You are managing a project to build a new office building. During excavation, the team discovers an unexpected archaeological site. This is a risk that was identified in the risk register with a low probability and high impact. The mitigation plan was to contact local authorities. What should you do FIRST?

Medium
15

You are managing a project using a hybrid approach. During a sprint, the development team discovers a critical security vulnerability that was not identified during risk planning. The fix will require significant rework and will cause the sprint goal to be missed. What should the project manager do FIRST?

Hard
16

A project manager is using earned value management. At month 6 of a 12-month project, the EV is $50,000, PV is $60,000, and AC is $55,000. What is the cost performance index (CPI)?

Hard
17

Your project is being executed, and a risk event occurs that was identified and planned for. Which THREE actions should you take?

Hard
18

Your agile project has a stable velocity of 30 story points per sprint. In the last three sprints, velocity dropped to 25, 22, and 20. The team cites increased complexity in user stories. What should you do first as the Scrum Master?

Medium
19

You are the project manager for a software development project using a hybrid approach. During the sprint review, the product owner is satisfied with the deliverables, but one key stakeholder requests a significant change that would add a new feature. The team has already started planning the next sprint. What should you do FIRST?

Medium
20

You are the project manager for a large infrastructure project. The project's CPI is 0.85 and SPI is 0.9. The team is working hard, but the project manager suspects that the cost performance is due to inaccurate estimates rather than inefficiency. The project sponsor is concerned about the budget overrun and asks you to cut costs by reducing quality inspections. What should you do?

Hard
21

A project team is transitioning from a predictive to an agile approach. One team member is resistant to change and insists on detailed upfront planning. What is the best way for the project manager to address this resistance?

Easy
22

A project manager is closing a project that was delivered on time and within budget. The customer has accepted the final deliverable. Which THREE activities should the project manager complete during project closure?

Medium
23

Your project is developing a new mobile app using Scrum. The team has consistently delivered 30 story points per sprint for the last three sprints. Suddenly, velocity drops to 20 story points in the current sprint. The team members report that they are spending extra time fixing defects from previous sprints. What should you do FIRST?

Medium
24

You are managing a project to develop a new mobile application. During a risk review meeting, the team identifies that a key third-party API may be deprecated before the project completes, which could cause significant rework. The probability is assessed as medium, and the impact is high. The team has identified alternative APIs. What is the BEST risk response strategy?

Medium
25

A new regulatory requirement has been announced that will affect your pharmaceutical project's deliverables. The requirement will take effect before your project's planned completion date. What should the project manager do FIRST?

Medium
26

A project is running over budget due to underestimation of effort. The project manager wants to bring costs under control. Which THREE actions are MOST appropriate?

Hard
27

As a project manager in a hybrid project, you notice that the team's sprint velocity has dropped for three consecutive sprints. The team is demotivated, and stakeholders are becoming concerned about the delivery date. Which TWO actions should you take to address this situation?

Medium
28

You are managing a large, complex project with multiple vendors. A critical vendor is consistently late on deliveries, impacting the project's critical path. The vendor contract includes penalties for delays. Which TWO actions should the project manager take FIRST?

Hard
29

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that was not in the backlog. The team estimates it will take 5 days to implement. What is the BEST action to take?

Medium
30

Your agile team is consistently completing 30 story points per sprint. In the next sprint planning, the product owner wants to commit to 40 points. The team feels this is too ambitious. Which THREE actions should you take?

Easy
31

During project execution, a team member reports that a deliverable may not meet the quality standards due to a shortcut taken earlier. What should the project manager do?

Easy
32

Your project is using a predictive approach. The schedule baseline shows that the project should be 50% complete by now, but only 40% of the work is done. The critical path has been impacted. Several team members are idle because of a dependency conflict. What is the BEST scheduling technique to address this?

Hard
33

You are managing a hybrid project that uses both predictive and agile approaches. The team has been delivering consistently, but recently the customer requested a critical feature that was not in the original scope. The feature is high value but will require rework of a completed component. What should the project manager do first?

Medium
34

You are managing a project to develop a mobile app. During the testing phase, a critical defect is found that could cause data loss. The team estimates it will take one week to fix, but the project is already two weeks behind schedule. What is the BEST course of action?

Medium
35

Your project is using a Kanban approach. The team's lead time has increased over the last two weeks, and work items are piling up in the 'In Progress' column. What is the BEST action for the project manager to take?

Easy
36

During a project's execution phase, the sponsor asks you to skip the user acceptance testing (UAT) phase to expedite delivery, stating that the client is eager to use the system. What should you do?

Medium
37

You are managing a software upgrade project using a hybrid approach. During execution, the team discovers a critical security vulnerability that was not identified during risk planning. The vulnerability requires immediate patching to avoid a potential data breach. Which TWO actions should you take NEXT?

Medium
38

You are the project manager for a 9-month product launch. At the midpoint review, the earned value analysis shows: EV = $450,000, PV = $500,000, AC = $550,000. The project is underperforming. The sponsor asks for a recovery plan. Which metric should you use to estimate the new total cost at completion assuming no change in cost performance?

Hard
39

During a project, a new regulation is introduced that will affect the project's deliverables. The regulation is mandatory and will require changes to the scope. What should the project manager do first?

Medium
40

Your agile team has been using Scrum for six months, but the product owner is not consistently available for sprint planning and reviews. The team is frustrated and the last two sprints did not meet the definition of done. Which THREE actions should you take to address this?

Hard
41

Your project is running 15% over budget at the midpoint. Earned value analysis shows CPI = 0.87 and SPI = 1.02. The project is ahead of schedule but over budget. Which THREE actions should you take?

Medium
42

During a daily standup, a developer mentions that a critical integration task will take longer than expected because of a technical dependency on another team. The project is on a tight schedule. Which THREE actions should you take?

Easy
43

During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?

Medium
44

You are managing a marketing campaign project using an agile approach. During the daily standup, a developer mentions they have started working on a feature that was not agreed upon in sprint planning. The product owner is not aware of this work. What should you do as the Scrum Master?

Medium
45

You are the project manager for a large infrastructure project. Midway through, a new regulatory requirement is introduced that mandates additional environmental testing, which could delay the project by one month and increase costs by 5%. The change control board (CCB) is scheduled to meet in two weeks. What should you do FIRST?

Hard
46

You are managing a pharmaceutical research project using a hybrid approach. Midway through, a new regulatory requirement is announced that will affect your project's deliverables. The compliance deadline is before your planned project completion. What should you do first?

Hard
47

Your project is in the execution phase. A team member reports that a supplier delivered a batch of raw materials that do not meet the quality specifications. The supplier insists the materials are acceptable and offers a discount. The project sponsor wants to accept the discount to save costs. What should the project manager do?

Hard
48

A team member consistently misses deadlines, causing delays in dependent tasks. During a one-on-one meeting, the team member admits to feeling overwhelmed and unsure how to prioritize work. What should the project manager do FIRST?

Easy
49

Your project is running 15% over budget at the midpoint. The earned value (EV) is $500,000, actual cost (AC) is $575,000, and planned value (PV) is $550,000. The project sponsor is concerned and asks for an estimate at completion (EAC). Assuming the cost performance index (CPI) will continue as is, what is the EAC?

Medium
50

Your project is halfway through its schedule. Earned value analysis shows: EV = $120,000, PV = $150,000, AC = $140,000. What is the best interpretation of the project's performance?

Medium
51

Your project is a traditional waterfall project. You are creating the work breakdown structure (WBS) for a new software development project. The team is having difficulty decomposing a complex deliverable. What is the BEST action to take?

Medium
52

During a project status meeting, a key stakeholder expresses dissatisfaction with the quality of deliverables. The team believes they have met all acceptance criteria. What should the project manager do?

Easy
53

A project manager is planning stakeholder engagement for a complex project with many interested parties. Which THREE techniques are MOST effective for analyzing stakeholders?

Medium
54

Your project is using a predictive approach. A key vendor notifies you that they will be unable to deliver a critical component for another four weeks. This component is on the critical path, and you have no schedule reserve left. You have identified that a different vendor can deliver in two weeks at a 20% higher cost. What should you do FIRST?

Hard
55

A project manager is reviewing the earned value report. The SPI is 0.85 and the CPI is 0.90. The project is behind schedule and over budget. Several team members are working overtime to catch up. What should the PM do FIRST?

Medium
56

Two senior developers on your Scrum team have a disagreement about the technical approach for a user story. The disagreement is causing delays in sprint execution. As the Scrum Master, what should you do FIRST?

Easy
57

Your project's Earned Value (EV) is $45,000, Planned Value (PV) is $50,000, and Actual Cost (AC) is $55,000. The project is at the midpoint. What is the most accurate assessment of the project's status?

Medium
58

A project manager is leading a construction project. The critical path has a total float of zero. A key supplier notifies you that a critical component will be delayed by two weeks, which will push the project beyond its deadline. The risk was identified and a mitigation plan exists. What should the PM do NEXT?

Hard
59

In a Scrum project, the product owner asks the team to add a new user story during the sprint. The team is currently working on committed stories. What should the Scrum Master do?

Easy
60

A key stakeholder on your project has been sending emails directly to team members, bypassing you as the project manager. This has caused confusion, as team members are receiving conflicting instructions. What should you do FIRST?

Medium
61

You are the PM for a highway construction project. A key vendor informs you that they cannot deliver the steel beams on time due to a factory fire. This risk was identified in the risk register with a mitigation plan to have a backup supplier. However, the backup supplier's price is 20% higher. Which TWO actions should you take?

Medium
62

A team member consistently misses deadlines, causing delays in the project. The project manager has had informal conversations with the team member, but the issue persists. What is the BEST next step?

Medium
63

During a construction project, you discover that a subcontractor has delivered materials that do not meet the quality specifications outlined in the contract. The project is already behind schedule, and replacing the materials will cause further delays. You have a good relationship with the subcontractor, who offers a discount on future work if you accept the materials as-is. What should you do FIRST?

Hard
64

You are the project manager for a marketing campaign launch. The project has a tight deadline. During a status meeting, a team member announces that they have completed a task two days early. However, you notice that the quality of the deliverable is below the acceptance criteria. What should you do?

Medium
65

Your project's earned value analysis shows CPI = 0.85 and SPI = 0.90. The project is behind schedule and over budget. Several stakeholders are concerned about the viability of the project. What is the BEST course of action?

Medium
66

Your project is experiencing scope creep due to informal requests from stakeholders. The project manager wants to establish better control. Which TWO actions should the project manager take?

Medium
67

You are managing a software development project using a hybrid approach. During a sprint review, the customer expresses dissatisfaction with a recently delivered feature and requests a significant redesign. This change will impact the critical path and increase costs. What should you do FIRST?

Medium
68

During a sprint retrospective, a team member complains that the daily standups are too long and unproductive. Several others agree. What is the BEST action for the Scrum Master to take?

Medium
69

In a Scrum project, the development team is consistently missing sprint commitments. The daily standup reveals that they are blocked by unclear acceptance criteria. What should the scrum master do?

Medium
70

Order the steps for closing a project or phase.

Medium
71

During a project audit, it is discovered that the quality management plan has not been followed, leading to defects. The project manager needs to address this issue. Which THREE actions should the project manager take?

Hard
72

You are managing a project to implement a new customer relationship management (CRM) system. During a status meeting, the IT director (a key stakeholder) announces that the team must use a different database platform than planned, citing corporate policy. This change will require significant rework. What should you do FIRST?

Medium
73

Your construction project is 60% complete. Due to a material shortage, the critical path extended by 10 days. You have float on some non-critical tasks. The sponsor is concerned about the project finishing on time. What should you do FIRST?

Hard
74

You are managing a project that is running 15% over budget at the midpoint. The variance is due to higher-than-expected material costs. The sponsor is concerned about cost overruns. What should you do FIRST?

Medium
75

A key vendor notifies you that they cannot deliver a critical component on time due to raw material shortages. This component is on the critical path and has no float. The vendor suggests using a substitute material that meets specifications but costs 20% more. What should the project manager do FIRST?

Hard
76

Your project is using a hybrid approach. An executive stakeholder has been bypassing you and giving direct instructions to the development team. The team is confused about priorities. What should the project manager do first?

Hard
77

You are managing a project using a hybrid approach. The project has a fixed-price contract with a customer. Midway through, the customer requests a significant scope change that would increase the contract value. The change request is approved by the CCB. What must the project manager do NEXT?

Hard
78

Your agile team has been consistently delivering high-quality increments. However, the product owner has been absent from the last two sprint reviews, and stakeholders are losing interest. What should you do as the scrum master?

Medium
79

Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the team identifies that they are spending too much time on unplanned work and technical debt. The product owner wants to maintain the current scope. Which THREE actions should the project manager take? (Choose three.)

Hard
80

A team member has been consistently late completing tasks. When you discuss this, they mention personal issues affecting their work. What should you do FIRST?

Easy
81

You are managing a software upgrade project. The team has identified a critical defect that requires immediate fixing, but the fix will delay the next release by one week. The product owner wants to release on time with the defect. Which THREE factors should you consider when advising the product owner?

Medium
82

During project execution, the quality assurance team finds that a deliverable does not meet the specified requirements. What should the project manager do FIRST?

Easy
83

You are managing a project that is 15% over budget at the midpoint. The earned value (EV) is $100,000, actual cost (AC) is $115,000, and planned value (PV) is $110,000. What is the most likely reason for the cost variance?

Medium
84

You are closing a project that has delivered all scope successfully. Which THREE activities are essential to complete during the project closure phase?

Easy
85

During a project, two senior developers have a conflict regarding the technical approach. As project manager, which TWO actions should you take?

Easy
86

Your project has multiple stakeholders with conflicting interests. The project sponsor wants to prioritize speed, while the quality assurance manager insists on thorough testing. The product owner wants to add more features. Which THREE techniques can help manage these conflicting stakeholder expectations?

Hard
87

Your project is in the execution phase and you discover that a key vendor will not deliver a critical component on time due to production issues. This risk was identified and documented in the risk register with a response plan to mitigate by having a backup vendor. However, the backup vendor requires a contract amendment that will take two weeks to approve. What should you do FIRST?

Medium
88

During a complex construction project, a key vendor notifies you that they cannot deliver a critical component for another 4 weeks. This component is on the critical path and has no float. You have identified this risk in the risk register with a planned response of 'mitigate' by having a backup vendor. However, the backup vendor also cannot deliver on time. What should you do first?

Hard
89

During a project, the sponsor asks you to skip the user acceptance testing (UAT) phase to save two weeks and meet an accelerated deadline. What should you do?

Medium
90

A project manager is planning a hybrid project. The team is new to agile and there is resistance to adopting agile ceremonies. Which TWO actions should the PM take to address this?

Medium
91

In a project closure phase, you are preparing the lessons learned report. The project performed well, but some stakeholders were dissatisfied with the communication frequency. What should you do?

Medium
92

You are the project manager for a large infrastructure project. The sponsor has requested that the team skip the quality assurance review for the next deliverable to save two weeks and meet an aggressive deadline. The deliverable is critical to the next phase. What should you do?

Medium
93

During a daily standup, a team member mentions that a task is taking longer than expected and will likely miss the deadline. The task is on the critical path. What should the project manager do FIRST?

Easy
94

Your project is using a critical chain method. You have identified that the project buffer is being consumed faster than planned due to delays in several tasks. What should you do?

Medium
95

During a sprint review, the product owner is dissatisfied with the increment and wants to revert to a previous version of a feature. The development team believes the current version meets the acceptance criteria. As Scrum Master, what should you do FIRST?

Hard
96

You are managing a construction project that is behind schedule. The project has non-critical activities with significant float. A key supplier has informed you that a critical component will be delayed by two weeks, impacting the critical path. You have already used up all schedule contingency. What should you do NEXT?

Hard
97

A project manager is closing a phase of a large project. What is the most important activity to perform during phase closure?

Easy
98

Your construction project is in the execution phase. A key vendor informs you that a critical material will be delayed by 3 weeks due to a strike at their factory. This delay will push the project beyond the required completion date. The risk was identified and documented in the risk register with a planned response. What should you do FIRST?

Medium
99

Which THREE of the following are key inputs to the Develop Schedule process?

Hard
100

During a project, the team identifies a risk that could cause a major delay. The probability is high and the impact is high. The project manager decides to hire an external expert to manage the risk. Which risk response strategy is being used?

Hard
101

Your agile team's velocity has dropped over the last three sprints. During the retrospective, the team cites increasing technical debt and lack of automated testing. Which TWO actions should you take to address this?

Medium
102

You are the project manager for a hybrid project. Midway through, you discover that a key stakeholder has been giving direct instructions to the development team, causing confusion and rework. What should you do first?

Medium
103

You are managing a project using a hybrid approach. During the execution phase, one of your key team members, a senior engineer, resigns unexpectedly. This engineer was responsible for critical path tasks. What is the FIRST thing you should do?

Medium
104

Your project is using a predictive approach, and you have just completed the work breakdown structure (WBS). What is the NEXT step in project planning?

Easy
105

You are the project manager for a large infrastructure project. During a routine check, you discover that the project's SPI is 0.85 and the CPI is 0.90. The project sponsor is concerned about the schedule delay and asks you to compress the schedule without increasing costs. Which technique is BEST suited for this situation?

Hard
106

A project manager is developing the project schedule and wants to determine the critical path. The activity network diagram shows multiple paths. Which technique should the project manager use?

Medium
107

Your project is a software implementation using a hybrid approach. The team has been facing scope creep due to informal change requests from stakeholders. Which TWO actions should you take to address this issue?

Medium
108

A project manager is managing a hybrid project. The team is two weeks into a four-week iteration when the product owner asks to reprioritize the backlog to include a critical regulatory requirement that was just announced. The change will impact the current iteration goal. What should the PM do FIRST?

Hard
109

A team member reports that a task is 50% complete but has consumed 70% of the budget. Which metric indicates that the project is over budget?

Easy
110

Your project is 40% complete and the earned value metrics show: PV = $500,000, EV = $450,000, AC = $520,000. What is the most accurate interpretation of the project's performance?

Medium
111

During a sprint retrospective, the team identifies that the daily standups are taking too long and are not productive. Several team members suggest canceling them to save time. As the scrum master, what is the best course of action?

Medium
112

You are managing a marketing campaign project. The sponsor asks you to skip the quality review of the final deliverables to meet the deadline. What should you do?

Easy
113

A project manager is developing a process improvement plan to reduce waste in a manufacturing project. The team has identified several non-value-added activities. Which technique should the project manager use to systematically analyze and improve the process?

Medium
114

During project closure, the project manager is conducting lessons learned. The team identifies that poor communication with a remote team caused rework. Which THREE actions should the project manager take to ensure continuous improvement?

Hard
115

A project manager is reviewing the schedule performance index (SPI) and cost performance index (CPI). The current values are SPI = 0.85 and CPI = 1.10. What is the most likely conclusion about the project?

Hard
116

Your project is in the planning phase, and you are developing the risk management plan. Which THREE tools or techniques should you use to identify risks?

Medium
117

Your project is 60% complete. The CPI is 1.05 and SPI is 0.92. You have received a change request from the customer that would add scope but also increase the budget. The change request is currently under review. What should you do while the change request is being evaluated?

Medium
118

During a project, a risk you identified in the risk register occurs. Your response plan was to mitigate by purchasing backup equipment. However, you discover the backup equipment is not available due to a supplier issue. What should you do first?

Easy
119

Your agile team has been experiencing conflicts between two senior developers over technical approaches during sprint planning. The conflicts are causing delays and affecting team morale. As the project manager, what is the BEST course of action?

Medium
120

During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteria. The developer argues that the story is functionally complete and the product owner is being too strict. What should the scrum master do?

Easy
121

You are managing a project to upgrade a company's network infrastructure. The project is on schedule, but you discover that the network cables purchased do not meet the required specifications. The procurement team bought a cheaper alternative without your knowledge. What should you do FIRST?

Easy
122

Your project is using a hybrid approach. A new regulatory requirement has been discovered that will affect the project scope. Which THREE actions should you take?

Hard
123

Your construction project is 40% complete, and you have just learned that a key supplier will be unable to deliver critical steel beams for another six weeks due to a factory fire. The beams are on the critical path, and the project has zero float. The risk register had identified a potential supplier delay, with a planned response to use an alternative supplier. What should you do NEXT?

Hard
124

You are the project manager for a large-scale data migration project from on-premises servers to AWS. The project involves migrating 50 terabytes of sensitive customer data. The team has completed the initial assessment and is now in the planning phase. The Chief Information Security Officer (CISO) has mandated that all data must be encrypted in transit and at rest. Additionally, the migration must minimize downtime and ensure data integrity. The project has a tight budget and schedule. During a planning meeting, the lead architect proposes using AWS Snowball Edge devices for the initial bulk transfer, followed by AWS DataSync for ongoing replication. However, the CISO is concerned about encryption key management and audit trails. As the project manager, what should you do first to address the CISO's concerns?

Hard
125

In your agile project, the team's velocity has been declining over the past three sprints from 30 to 25 to 20 story points. The team members report feeling overworked and demotivated. The daily standup meetings are running long, and the product owner is adding too many stories each sprint. What should the project manager do FIRST?

Medium
126

A project manager is closing a project. Several lessons learned were documented throughout the project. What should the PM do with the lessons learned?

Medium
127

During a sprint retrospective, the team identifies that they are consistently overcommitting during sprint planning, leading to incomplete work. Which action should the project manager take to address this issue?

Easy
128

At the midpoint of your 18-month project, the earned value analysis shows: EV = $450,000, PV = $500,000, AC = $550,000. What should you be most concerned about?

Medium
129

You are the project manager for a complex IT infrastructure project. Two senior developers have a conflict regarding the technical approach to a critical component. The conflict is causing delays and affecting team morale. Both approaches are valid but have different resource and schedule implications. What should you do first?

Hard
130

During a sprint retrospective, several team members express frustration that the daily stand-ups are too long and not focused. As the Scrum Master, what is the BEST action to take?

Easy
131

During project closure, which THREE documents should be updated or finalized as part of the lessons learned process?

Medium
132

You are managing a marketing campaign project. Midway, you discover that the team has been working on additional features requested by the sales director without formal approval. The project is now 10% over budget. Which TWO actions should you take FIRST?

Medium
133

A project is halfway through its schedule. The earned value (EV) is $50,000, planned value (PV) is $60,000, and actual cost (AC) is $70,000. The project manager calculates the cost performance index (CPI) and schedule performance index (SPI). Based on these metrics, what is the most likely situation?

Medium
134

During project execution, a key stakeholder requests a new feature that is not in the scope. The project manager determines that the change will impact the schedule by 3 weeks and increase costs by $50,000. What should the project manager do first?

Hard
135

Your construction project is in the execution phase. You discover that a critical supplier will be unable to deliver steel beams for another three weeks due to a strike at their factory. This risk was identified and recorded in the risk register with a mitigation plan. What should you do next?

Medium
136

During a construction project, a key vendor informs you that a critical component will be delayed by three weeks due to a raw material shortage. The component is on the project's critical path. What should you do FIRST?

Medium
137

In a Scrum project, the development team consistently fails to complete all committed stories in each sprint. The daily stand-up meetings are running long and often devolve into problem-solving sessions. As the Scrum Master, what should you do?

Easy
138

A project manager is informed that a new government regulation will affect the project deliverables. The regulation is mandatory and must be implemented before the project can close. What should the project manager do FIRST?

Medium
139

During a project's execution phase, a new regulatory requirement is discovered that will impact the project scope. The requirement is mandatory and must be implemented. What is the first action the project manager should take?

Medium
140

You are managing a software development project that uses an agile methodology. The team has been working on a critical feature for the past two weeks. During the daily standup, a developer mentions that they discovered a significant technical debt in the codebase that will require refactoring before the feature can be completed. The product owner is not present at the standup. The developer estimates that the refactoring will take an additional three days, which will delay the current sprint's delivery. The sprint ends in five days. The team is already at full capacity. As the project manager, what should you do first?

Medium
141

You are managing a software development project using a hybrid approach. During sprint planning, the product owner requests adding a new feature that was not in the project scope. The team estimates it will take two additional sprints. What should you do FIRST?

Medium
142

You are managing a project to develop a new mobile application using an agile approach. During the third sprint, two senior developers have a disagreement about the technical architecture to use for a feature. The disagreement is slowing down progress. Which TWO actions should you take?

Medium
143

In a hybrid project, the team is struggling with unclear requirements. The project manager wants to improve the situation. Which THREE actions should the project manager take?

Hard
144

A project manager is closing a project. Which THREE activities are essential to perform during project closure?

Medium
145

During a sprint review, stakeholders express dissatisfaction with the functionality delivered. The product owner insists the team met the acceptance criteria defined in the sprint. The team feels demotivated. As the project manager, what should you do first?

Medium
146

In a Kanban project, the team notices that the work-in-progress (WIP) limit is frequently exceeded, causing bottlenecks. What is the BEST action for the project manager to take?

Easy
147

You are managing a project where a risk identified in the risk register has occurred. The risk response plan calls for mitigation, but the mitigation action will delay the critical path by 2 weeks. The project has no schedule reserve. What should the project manager do FIRST?

Hard
148

During a quality audit, it is discovered that a deliverable does not meet the specified quality standards. What should the project manager do first?

Easy
149

You are the project manager for a large infrastructure project. The sponsor frequently bypasses you and gives direct instructions to the team leads. This has caused confusion and conflicting priorities. What is the BEST action to take?

Hard
150

Your project uses a hybrid methodology. An executive stakeholder emails the development team directly requesting a new feature without going through the product owner. The team starts working on it. What should you do FIRST?

Hard
151

Your project is running behind schedule. You need to compress the schedule without significantly increasing cost. Which TWO techniques should you consider?

Medium
152

A critical vendor informs you that they cannot deliver a key component on time due to a raw material shortage. The component is on the critical path. You have identified this risk in the risk register with a medium probability and high impact. The planned response was to accept the risk. What should you do first?

Hard
153

During a project audit, you discover that the quality assurance (QA) team has not been conducting planned inspections, but the quality control (QC) logs show no major defects. What should you do FIRST?

Medium
154

Match each knowledge area to its primary focus.

Medium
155

During project execution, a key stakeholder requests that the project manager bypass the formal change control process to expedite a change. The stakeholder argues that the change is minor and will not affect the budget or schedule. What should the project manager do?

Medium
156

Your project is using a hybrid approach. During a sprint review, the customer is unhappy with the progress and requests a major change in direction. This change will require significant rework and affect the project's critical path. Which THREE actions should you take?

Hard
157

During project execution, a risk event that was identified and listed in the risk register occurs. The risk response plan includes a mitigation strategy. What should the project manager do FIRST?

Medium
158

During a sprint retrospective, the team identifies that the daily standups are taking too long and are not focused. Several team members suggest canceling them to save time. What should the scrum master do?

Medium
159

You are managing a project that involves a high-risk activity that was identified in the risk register. A risk response plan was created to mitigate the risk. During execution, a risk event occurs that was not fully mitigated. The risk impact is now threatening the project schedule. What should you do FIRST?

Hard
160

Your agile team has experienced a drop in velocity for the past three sprints. During the retrospective, team members mention that they are spending too much time on unplanned work and context switching. As the project manager, what should you do FIRST?

Medium
161

Your agile team has been experiencing a decrease in velocity over the last three sprints. During the daily standup, team members seem disengaged and mention they are unsure of the sprint goals. As the scrum master, what should you do FIRST?

Easy
162

You are managing a software development project using a hybrid approach. During sprint planning, the product owner insists on adding a feature that was not in the approved product backlog. The team estimates it will take 3 additional days. What should you do FIRST?

Medium
163

Your project is using a hybrid approach with both predictive and agile elements. The team is working on a critical feature that has a high degree of uncertainty. The product owner wants to use a time-boxed sprint to explore the feature. However, the sponsor insists on a detailed upfront plan. What should the project manager do?

Medium
164

Refer to the exhibit. The project team uses Git for version control. The lead developer accidentally committed a bug fix directly to the main branch instead of the feature branch. What is the best course of action to maintain a clean history?

Medium
165

Your IT infrastructure project is being audited for compliance. The auditor finds that several change requests were approved verbally but not documented. The project is in the execution phase. Which TWO actions should you take?

Medium
166

During a sprint retrospective, the team identifies that the daily standup meetings are not effective because they are too long and lack focus. Which THREE actions should the Scrum Master take to improve the standup?

Medium
167

During project execution, a key vendor notifies you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The vendor suggests using a substitute material that is not yet approved by your quality team. What should the project manager do FIRST?

Hard
168

You are managing a software development project using a hybrid approach. During a sprint review, the customer requests a major feature addition that would extend the timeline by two weeks. The team is already working at capacity. What should you do FIRST?

Medium
169

Your project is using a hybrid approach with both predictive and agile elements. The team is struggling with the daily standup because some members treat it as a status report for management. Which THREE actions should you take to improve the standup?

Medium
170

You are the project manager for a software development project using Scrum. During the daily standup, a developer mentions that they are blocked by a dependency on another team's API that is delayed. The developer has already tried contacting the other team but received no response. What should the scrum master do?

Easy
171

Your project is behind schedule due to underestimated task durations. The critical path has been identified. Which TWO schedule compression techniques are MOST appropriate to get the project back on track?

Medium
172

Your agile project has been experiencing decreasing velocity over the last three sprints. The team is frustrated and morale is low. The product owner is pressuring for more features. What is the BEST action for the project manager to take?

Medium
173

You are managing a project using a hybrid approach. Midway through, a new regulatory requirement is introduced that will affect the project scope. The change is mandatory and must be implemented. What is the FIRST step?

Hard
174

During a sprint review, the customer expresses dissatisfaction with the user interface, stating it does not meet their expectations. The team followed the specifications agreed upon during sprint planning. What should the project manager do NEXT?

Medium
175

Your project is 40% complete, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. The project sponsor is concerned about the cost overrun. The original budget at completion (BAC) is $1,000,000. What is the Estimate at Completion (EAC) using the typical cost performance index (CPI) assumption?

Medium
176

A team member consistently misses deadlines, causing delays for the rest of the team. You have already spoken to the team member informally, but the behavior continues. What is the BEST next step?

Easy
177

During a sprint retrospective, the team identifies that the daily standup meetings are taking too long and not focusing on impediments. Which TWO actions would help improve the effectiveness of the daily standup?

Easy
178

You are managing a pharmaceutical research project using a predictive approach. A new regulation requires additional clinical trials that will extend the project by 6 months. The sponsor wants to know how this affects the business case. Which THREE documents should you review to provide an informed response?

Hard
179

During a sprint retrospective, the team identifies that the daily standups are too long and not adding value. They suggest implementing a timebox of 15 minutes and a strict 'three questions' format. What should the scrum master do?

Easy
180

You are managing a project to build a new mobile application. An executive stakeholder has been bypassing you and giving direct instructions to team members, causing rework and confusion. What should you do first?

Medium
181

Your construction project is experiencing resource levelling issues because a key piece of equipment is shared between two critical path activities. What is the best approach to resolve this?

Medium
182

A project manager is working on a predictive project. A team member identifies a risk that was not previously identified. The risk has a low probability but high impact. What should the PM do FIRST?

Easy
183

In an agile project, the product owner frequently changes priorities within a sprint, causing the team to lose focus and velocity to drop. What should the project manager do first?

Hard
184

You are managing a project that is currently in the execution phase. A risk event that was identified and included in the risk register has occurred. The planned response is to mitigate the risk. Which TWO documents should you update to reflect the occurrence and response? (Choose two.)

Easy
185

You are managing a project that is currently in the execution phase. The project has a cost baseline of $500,000. At the end of month 3, the planned value (PV) is $150,000, the actual cost is $150,000 and the earned value is $120,000. The project manager calculates the cost variance (CV) and schedule variance (SV). What do the results indicate?

Medium
186

A new regulatory requirement has been introduced that affects your project's deliverables. The requirement must be implemented within the current timeline. What should the project manager do first?

Easy
187

During a project audit, you discover that a team member has been gold-plating the deliverables by adding extra features not requested. What is the BEST action to take?

Medium
188

The sponsor asks you to skip the final round of user acceptance testing (UAT) to meet the deadline, stating that earlier tests were sufficient. What should the project manager do first?

Medium
189

You are managing a hybrid project where the team uses Scrum for development but follows a traditional approach for reporting. The project is behind schedule because the development team is spending too much time on documentation for status reports. The product owner is concerned about the lack of progress. What should you do?

Hard
190

During project closure, what is the most important activity the project manager should perform?

Easy
191

During a sprint planning meeting, the product owner proposes a user story that the team feels is too large to complete in one sprint. What is the best approach?

Medium
192

Your project is halfway through its schedule, and you are performing a variance analysis. You find that the cost performance index (CPI) is 0.85 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

Medium
193

During project execution, a key stakeholder repeatedly bypasses the formal communication channels and directly contacts team members for status updates. This is causing confusion and rework. Which TWO actions should you take?

Medium
194

Your construction project is halfway through the schedule. Earned value analysis shows EV = $500,000, PV = $600,000, AC = $550,000. The original budget (BAC) is $1,200,000. What is the most appropriate action considering the project's performance?

Hard
195

Order the steps for creating a Work Breakdown Structure (WBS).

Medium
196

Your construction project is halfway through the schedule. The earned value analysis shows: EV = $500,000, PV = $600,000, AC = $550,000. The sponsor is concerned about the schedule delay. You need to present recovery options. Which THREE actions should you recommend?

Hard
197

Your project is using a hybrid approach with a fixed-price contract for the predictive portion and a time-and-materials contract for the agile portion. A change request from a stakeholder would affect both portions. The change control board (CCB) has approved the change for the predictive portion but deferred the agile portion to the product owner. How should you proceed?

Hard
198

During an agile project, the product owner frequently changes priorities during the sprint, causing the team to lose focus and miss sprint goals. The team expresses frustration in the retrospective. As the project manager, what should you do?

Medium
199

You are the project manager for a large construction project. Midway through, a key supplier informs you that a critical component will be delayed by 6 weeks due to raw material shortages. The component is on the critical path and has zero float. What should you do FIRST?

Hard
200

During project execution, a team member reports that a critical path activity is delayed by two days because a required component failed quality inspection. The project has no schedule contingency. What is the BEST course of action for the project manager?

Easy
201

In the middle of a project, new government regulations are introduced that affect your deliverables. Compliance is mandatory. The project is currently on schedule and on budget. What should the project manager do FIRST?

Easy
202

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that was not in the backlog. The team estimates it will require 5 additional days. The project is currently on schedule and within budget. Which TWO actions should you take NEXT?

Medium
203

In a project using a hybrid approach, the team is developing a new product. During sprint planning, the product owner wants to add several new user stories that were not in the release plan. The team is concerned that adding these stories will overload the sprint. What should the scrum master do?

Medium
204

You are a project manager overseeing a 12-month ERP implementation. During sprint 6 of 20, the product owner informs you that a key stakeholder wants to add a new reporting module that was not in the original scope. The team estimates this would add 3 weeks to the schedule. What should you do FIRST?

Medium
205

Your project is a construction project with a fixed price contract. At the 40% progress point, earned value (EV) is $400,000, actual cost (AC) is $480,000, and planned value (PV) is $500,000. What does this indicate?

Medium
206

You are managing a project where the team is experiencing conflict between two senior developers over technical approach. The conflict is affecting team morale and productivity. Which TWO actions should you take? (Select exactly two.)

Medium
207

Your project is using a predictive lifecycle. The team has identified a potential risk that could cause a two-week delay. The risk has a probability of 30% and an impact of $50,000. The project has a contingency reserve of $100,000. What is the most appropriate risk response?

Medium
208

A project is behind schedule due to a key vendor delivering late. The contract includes penalties for late delivery. The project manager is considering options. Which THREE actions are most appropriate per PMI?

Hard
209

During a sprint retrospective, the team identifies that their velocity has been declining over the last three sprints. They attribute it to increasing technical debt and lack of automated testing. As the Scrum Master, what is the BEST action to take?

Easy
210

Your project is using a hybrid approach. During a sprint, the team realizes that a critical dependency from another project will not be ready on time, impacting the critical path. The dependency was not identified in the risk register. What is the BEST action?

Hard
211

A project manager is leading a global team with members in different time zones. The team is experiencing delays because some members are not responding to emails promptly. What is the best course of action to improve communication?

Hard
212

You are the project manager for a software development project using Scrum. For the past three sprints, the team's velocity has dropped from 30 story points to 20. The team cites increasing technical debt and unclear requirements. What should you do FIRST?

Medium
213

During the execution phase of a construction project, you discover that a key vendor will not deliver steel beams on time, threatening the critical path. The risk was identified and the response plan was to use an approved backup supplier. What should you do NEXT?

Easy
214

A project is in the execution phase and the project manager notices that the project's cost performance index (CPI) is 0.85 and the schedule performance index (SPI) is 0.90. The project sponsor is concerned and wants to get back on track. Which THREE actions should the project manager consider to improve performance?

Hard
215

Your project sponsor asks you to skip the testing phase of a software release to meet a tight deadline. What is the best response?

Easy
216

You are managing a large infrastructure project. At the midpoint, earned value analysis shows CPI = 0.85 and SPI = 0.90. The project budget is $10 million, and the schedule is tight. Several stakeholders are concerned about cost overruns. What should you do FIRST?

Hard
217

A project manager is leading a cross-functional team that includes members from different departments. Two senior developers have a conflict about the technical approach for a critical component. The conflict is causing delays. What should the project manager do FIRST?

Hard
218

You are a project manager for a software implementation. The testing team reports that they have found several defects, but the project sponsor insists on releasing the product on the original date to meet a market opportunity. The product is not fully tested. What is the BEST response?

Easy
219

Midway through your project, a key vendor informs you that they cannot deliver a critical component on time, which will impact the critical path. The risk was identified in the risk register with a 'mitigate' response. What should you do FIRST?

Medium
220

You are managing a hybrid project. The team is reporting that sprint velocity has been decreasing for the last three sprints. During the retrospective, the team attributes this to technical debt and unclear requirements. What should you do FIRST?

Medium
221

During a sprint retrospective, the team identifies that the daily standups have become too long (45 minutes instead of 15). Several team members feel the standups are unproductive. As the Scrum Master, what should you do?

Easy
222

In a daily standup, a developer mentions that a task is taking longer than expected due to an unfamiliar technology. The sprint goal may be at risk. As a Scrum Master, what should you do FIRST?

Easy
223

You are the project manager for a marketing campaign. A new regulation is announced that affects your project's deliverables. The regulation requires additional compliance steps that were not in the original scope. What should you do FIRST?

Easy
224

During a project's execution phase, a key vendor notifies you that they cannot deliver a critical component on time due to raw material shortages. The component is on the critical path, and any delay will impact the project completion date. The risk was identified and listed in the risk register with a planned response to accept. What should the project manager do first?

Hard
225

During project execution, a team member discovers a defect in a deliverable that was completed two weeks ago. The defect is minor and can be fixed quickly, but fixing it will require rework that is not in the current sprint. What should you do?

Hard
226

Your project is in the execution phase, and you discover that a key vendor will deliver a critical component two weeks late, impacting the critical path. The contract does not include penalties for late delivery. What should you do first?

Medium
227

Your project is in execution phase. The earned value metrics show: EV = $400,000, PV = $500,000, AC = $450,000, BAC = $1,000,000. Which THREE actions should you take to address the project's performance?

Hard
228

You are managing a project using a predictive approach. A key stakeholder requests a minor change that does not affect the critical path but will add two days to the schedule. The team has some idle time. What should you do?

Medium
229

A project manager discovers that a team member has been working on a feature that was not approved. The feature is not in the scope statement. What should the PM do FIRST?

Easy
230

You are managing a software development project using Scrum. During the sprint review, the product owner praises the team's work but mentions that a key stakeholder is unhappy because an expected feature was delivered with limited functionality. The feature was completed according to the sprint backlog, but the stakeholder had not communicated their detailed expectations. What should you do FIRST?

Medium
231

Your project is in the execution phase. An executive stakeholder has been directly assigning tasks to team members without going through you. Several team members are confused about priorities. What should you do FIRST?

Medium
232

In a Scrum project, the team's velocity has been declining over the last three sprints. The project manager (also the Scrum Master) notices that team morale seems low. What should the project manager do FIRST?

Medium
233

Your project is executing a fixed-price contract with a vendor to develop a key module. The vendor has delivered a module that does not meet the agreed-upon quality standards. The contract includes penalty clauses for non-compliance. What is the BEST action?

Hard
234

A key stakeholder on your agile project frequently attends the daily standup and redirects team members to work on tasks that are not part of the sprint backlog. This is causing confusion and reducing the team's velocity. As the project manager, what should you do first?

Medium
235

Which TWO are key components of a project management plan? (Choose two.)

Medium
236

Your project is 40% complete, and the earned value analysis shows CPI = 0.8 and SPI = 0.9. The project sponsor is concerned about the cost overrun and asks you to reduce costs by skipping quality assurance activities. What should you do?

Medium
237

A project is nearing completion. The project manager is preparing for project closure. Which of the following is the most important activity to complete during project closure?

Easy
238

A project manager is using a RACI chart to assign responsibilities for key deliverables. Which TWO statements about a RACI chart are true? (Choose two.)

Medium
239

You are the project manager for a software upgrade project. The team is using a hybrid approach with two-week sprints. During sprint planning, the product owner wants to include a user story that the team believes is too large to complete in one sprint. Which TWO actions should you take?

Medium
240

Your project's sponsor requests that you skip user acceptance testing (UAT) to recover schedule delays. The team has already performed thorough internal testing. What should you do FIRST?

Medium
241

During a project retrospective, the team identifies several process improvements that could increase efficiency. What is the BEST way to ensure these improvements are implemented?

Easy
242

During a project's execution phase, you discover that a team member has been delivering work that does not meet the quality standards defined in the quality management plan. What should you do FIRST?

Easy
243

During a project, a risk event occurs that was not identified in the risk register. The project manager needs to respond. Which THREE actions should the project manager take?

Medium
244

You are managing a software development project using a hybrid approach. Midway through, the customer requests a new feature that was not in the original scope. The team estimates it will add two weeks to the schedule. What should you do FIRST?

Medium
245

Your project is using a hybrid approach. During the execution phase, you notice that the cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.1. What does this indicate?

Easy
246

During project execution, a key stakeholder requests a change that will increase the scope. The project manager follows the formal change control process. What is the first step the project manager should take?

Easy
247

During a project's execution phase, you receive a change request from a stakeholder that would improve the product's performance but is not required by the original specifications. The change is estimated to add 2 weeks to the schedule and $10,000 to the budget. The project is currently on schedule and under budget. What should you do FIRST?

Medium
248

Your project is in execution phase. An executive stakeholder bypasses you and directly instructs a team member to add a new feature. The team member complies and completes the work. You discover this during a status review. What should you do FIRST?

Hard
249

In an agile project, the team's velocity has dropped for three consecutive sprints. The daily standup meetings are rushed, and team members often work in silos. What should the project manager do first?

Hard
250

Your multinational project has team members in three time zones. The daily standup is held at 9 AM EST, but the Asia team complains it is 9 PM for them. The standup is becoming ineffective. Which TWO actions should you take to improve the situation?

Hard
251

Your project is using a hybrid approach. At the end of the first iteration, the customer provides feedback that significantly changes the priority of features. The team has already started work on the next iteration's backlog. As the project manager, which THREE actions should you take? (Select exactly three.)

Hard
252

During a daily standup meeting, a team member mentions that they are blocked because a dependency on another team's work is not yet complete. The Scrum Master is present. What should the Scrum Master do FIRST?

Easy
253

Your project is facing significant schedule delays due to unforeseen regulatory changes. You need to compress the schedule. Which TWO techniques are appropriate for schedule compression?

Medium
254

A project manager notices that the project's cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

Medium
255

In an agile project, the team's velocity has decreased over the last three sprints from 30 story points to 22. During the retrospective, the team cites increasing technical debt as the cause. What should the scrum master do FIRST?

Medium
256

During project execution, you receive a change request from a key stakeholder to add a new deliverable. The change would require additional resources and extend the schedule by two months. The project is currently on track. Which THREE actions should you take?

Hard
257

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that was not in the backlog. The team estimates it will take 5 additional days. What should you do first?

Medium
258

Your agile team has noticed that sprint velocity has dropped from 30 to 20 story points over the last three sprints. During the retrospective, team members mention unclear requirements and frequent interruptions. As the project manager, what should you do first?

Medium
259

During a project closure phase, you realize that several deliverables were completed but not formally accepted by the customer. The contract requires signed acceptance for each deliverable. What should you do first?

Hard
260

During a sprint planning meeting, the product owner wants to add a high-priority user story that the team believes is too large to complete in one sprint. What should the team do?

Medium
261

Your agile team has been consistently delivering in each sprint, but the product owner is concerned because the customer's needs have changed and some completed features may no longer be valuable. The project uses fixed-price contract. What should you do?

Hard
262

During a project, a new regulation is enacted that requires additional compliance testing. The project is in the execution phase. Which THREE actions should the project manager take?

Medium
263

A new regulatory requirement has been introduced that affects your project's deliverables. The requirement must be implemented within two months. Your project is currently in the execution phase. Which THREE actions should you take?

Medium
264

During project execution, you discover that a key vendor will not be able to deliver a critical component on time, which will delay the project by two weeks. The vendor was selected based on the procurement plan. What should you do FIRST?

Easy
265

You are managing a software development project using a hybrid approach. During a sprint review, the customer expresses satisfaction but requests a small additional feature that was not in the original backlog. The team believes it can be completed in two days without affecting the critical path. What should you do first?

Easy
266

Your project is using a predictive approach. A key vendor has informed you that they will be unable to deliver a critical component on time, which could delay the project by three weeks. You have identified this risk in the risk register. What should you do first?

Easy
267

Your project is using a predictive approach to build a mobile app. During testing, the team discovers a critical security vulnerability that was not identified during planning. Fixing it will require two additional weeks and $50,000, which is within the contingency reserve. What should you do NEXT?

Medium
268

You are managing a pharmaceutical research project that is subject to strict regulatory compliance. Mid-project, a new regulation requires additional testing that will add 4 weeks to the schedule and $50,000 in costs. The sponsor is anxious about the delay. What should you do FIRST?

Hard
269

You are managing a project to deploy a new customer relationship management (CRM) system. During user acceptance testing, the quality assurance team identifies several critical defects that must be fixed before go-live. The project is already behind schedule. What should the project manager do NEXT?

Medium
270

During a sprint retrospective, the team identifies that the daily standup meetings are running too long and are not focused. They want to improve the effectiveness of the standups. What should the scrum master do?

Easy
271

You are managing a software development project using a hybrid approach. During a sprint review, the customer is delighted with the progress but requests a new feature that would require significant rework of the current sprint's deliverable. The feature is not in the backlog. What should you do FIRST?

Medium
272

During a project, an executive stakeholder bypasses the project manager and directly instructs a team member to add a new feature. The team member is already overloaded. What should the project manager do FIRST?

Medium
273

In an agile project, the team has been working on the same product backlog for several sprints. During sprint planning, the product owner introduces a new high-priority user story that will require the team to reprioritize existing work. What is the BEST approach?

Medium
274

You are the project manager for a large construction project. An executive stakeholder has been bypassing you and directly giving instructions to the site supervisor to add extra features. The supervisor complied, and now the project is experiencing scope creep. The changes have not been formally approved. What should the project manager do first?

Hard
275

You are a project manager overseeing a 12-month ERP implementation. During sprint 6 of 20, the product owner informs you that a key stakeholder wants to add a new reporting module that was not in the original scope. The team estimates this would add 3 weeks to the schedule. What should you do FIRST?

Medium
276

During a daily standup, a developer mentions she is blocked because two senior engineers are in a heated argument about the technical approach for a critical feature. The disagreement has been ongoing for two days and is affecting the team's velocity. As the Scrum Master, what should you do?

Medium
277

You are managing a project where a team member consistently misses deadlines. This has caused frustration among other team members and is affecting the project schedule. What should you do FIRST?

Easy
278

Your hybrid project uses a fixed-price contract with a vendor. The vendor notifies you that they cannot deliver a critical component on time due to a labor shortage. What should you do FIRST?

Hard
279

During a construction project, you discover that a critical supplier will not be able to deliver steel beams on time due to a labor strike. This risk was identified and listed in the risk register with a planned response of 'accept.' However, the delay will cause a 2-week slip in the critical path. What should you do?

Medium
280

A project is using a predictive approach. The project manager discovers that a team member has been gold-plating by adding extra features to a deliverable without authorization. What should the project manager do FIRST?

Hard
281

Your project is in the planning phase, and you need to develop the schedule. You have identified the activities and their dependencies. The team estimates that the project will take 12 months. However, the sponsor requires completion in 10 months. The project has a fixed deadline. What should you do FIRST?

Medium
282

A project team is using a deployment tool to release an application. The deployment failed with an error indicating that a required component is missing from the target environment. What is the most likely cause?

Medium
283

A project is in the planning phase. The project manager wants to ensure that all stakeholders have a common understanding of the project scope. Which document should be used as the primary reference?

Medium
284

You are managing a software development project using a hybrid approach. Midway through the project, the product owner requests a new feature that requires changing the scope and schedule. The team is currently working on a critical path activity. What should you do first?

Medium
285

Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on you to start construction before all approvals are obtained. The schedule is tight, and any delay could result in penalties. What should the project manager do?

Hard
286

During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previously identified. As the project manager, what is the BEST action?

Easy
287

You are the project manager for a software development project using a hybrid approach. During a sprint review, the product owner requests a change that would add a new feature to the current release. The team estimates it will take two additional sprints. What should you do first?

Medium
288

Your project is experiencing scope creep due to informal change requests from stakeholders. Which TWO actions should you take to address this?

Medium
289

You are a project manager for a software development project using Scrum. The product owner has been pressuring the team to increase velocity and deliver more features per sprint. The team feels overwhelmed and quality has started to suffer. Which TWO actions should the project manager take to address this situation?

Medium
290

You are managing a project that is using a hybrid approach. An executive stakeholder has requested a significant change to the project scope. The change has been approved by the change control board (CCB). Which THREE actions should you take next?

Medium
291

Two senior developers have a conflict over which technical approach to use for a module. The disagreement is delaying the sprint. What should the project manager do FIRST?

Easy
292

A project manager is reviewing a project plan that must comply with an industry standard. The compliance review fails. What is the most likely cause of this failure?

Hard
293

During a daily standup, a developer mentions they found a way to improve the code's performance but it will add two extra days of work. What should the scrum master do?

Easy
294

During a quality audit, it is discovered that the team has been using outdated templates for test cases, resulting in some defects that were not caught. What should the project manager do first?

Easy
295

A project manager is leading a software development project. During a sprint review, the product owner rejects a feature because it does not meet the acceptance criteria. The development team claims they followed the design documents. What should the project manager do first?

Medium
296

In a hybrid project, the team uses Scrum but the organization requires detailed phase-gate reviews. During the gate review, the steering committee asks for a Gantt chart showing all tasks until project completion. The Scrum team only maintains a product backlog and sprint backlogs. Which THREE actions should you take?

Hard
297

Your IT infrastructure project is running 15% over budget at the midpoint. After analyzing the variance, you find that the cost overrun is due to a one-time increase in licensing fees that will not recur. The project is on schedule. What is the BEST estimate for the Estimate at Completion (EAC)?

Hard
298

Two senior developers on your agile team have a conflict about the technical approach for a user story. This conflict is causing delays. What should the project manager do?

Hard
299

You are managing a project that is experiencing scope creep. Several stakeholders have been requesting additional features informally. You want to bring the project under control. Which TWO actions should you take?

Medium
300

Your agile team is experiencing a drop in velocity over the last three sprints. During the retrospective, team members mention that they are spending too much time on unplanned work and context switching. As the project manager, what should you do?

Easy
301

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that would add significant value but was not in the product backlog. The team estimates it will take two additional sprints. What should you do FIRST?

Medium
302

You are managing a project where a key team member has been consistently missing deadlines. This has caused delays in dependent tasks. The team member has good technical skills but seems overloaded. What is the best course of action for the project manager?

Hard
303

A project has a critical path of 120 days with a standard deviation of 5 days. The project sponsor wants to know the probability of completing the project within 130 days. Using the normal distribution, what is the approximate probability?

Medium
304

A project team is developing a new software feature. During a sprint review, the product owner requests a change that would increase the scope significantly. The team has already committed to the current sprint backlog. What is the BEST course of action for the project manager?

Easy
305

Your project is using a predictive lifecycle. A team member notices that a task on the critical path is taking longer than estimated, threatening the project completion date. What is the BEST action to take?

Easy
306

Your agile team is working on a mobile app. The product owner wants to add a new feature that was not in the original backlog. Which TWO actions should you take?

Medium
307

A key vendor informs you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The vendor has a history of poor performance. What should the project manager do FIRST?

Medium
308

During a project to implement a new CRM system, the sponsor asks you to skip the user acceptance testing (UAT) phase to meet the go-live date, stating that the system has been thoroughly tested by the IT team. What should you do FIRST?

Medium
309

Your project is 50% complete, and your earned value analysis shows: EV = $200,000, PV = $220,000, AC = $240,000. Based on this data, what is the most accurate assessment of the project's performance?

Hard
310

You are managing a hybrid project with both predictive and agile components. A key risk from the risk register materializes: a critical vendor may go bankrupt, threatening delivery of a hardware component needed for the predictive phase. The risk response plan includes 'mitigate by identifying alternative vendors.' However, the only alternative vendor quotes a price that would exceed the project cost baseline by 10%. What should you do NEXT?

Hard
311

During a daily standup, a developer mentions that they are blocked due to a missing API from a third-party vendor. The vendor had promised delivery two days ago. What should the project manager do FIRST?

Easy
312

You are the project manager for a software development project that is using a hybrid approach. A key team member informs you that they have identified a new risk that could cause a two-week delay. The risk is not in the risk register. What should you do FIRST?

Medium
313

Your project's CPI is 0.85 and SPI is 0.90 at the midpoint. The project sponsor asks for a status update. What should you do?

Medium
314

Your project is running 15% over budget at the midpoint. The cost variance is due to higher-than-expected material costs. What is the BEST action?

Medium
315

You are managing a software development project using a hybrid approach. During a daily standup, one developer mentions he has identified a potential security flaw in the current build that could significantly impact the release. The fix will require at least two days of additional work. What should you do FIRST?

Medium
316

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that was not in the backlog. The team estimates it will take one week. The project is on schedule and budget. What should you do FIRST?

Medium
317

Sequence the steps for conducting a procurement process.

Medium
318

A project is in the planning phase. The team has identified 50 risks. The project manager wants to prioritize risks for further analysis. Which tool or technique is BEST suited for this?

Medium
319

In your Scrum project, the development team has been consistently missing sprint commitments. During the retrospective, the team identifies that scope is often added during the sprint by the product owner without consulting the team. What should you do as the Scrum Master?

Easy
320

You are managing a project that is behind schedule. The project sponsor has asked you to explore schedule compression techniques. Which TWO options are valid schedule compression techniques that can be applied without changing scope? (Choose two.)

Medium
321

During a sprint review, a key stakeholder expresses dissatisfaction with the product increment, stating that it does not meet their expectations. The team followed the acceptance criteria defined in the user stories. What should the project manager do NEXT?

Easy
322

A project manager is leading a global team with members in three different time zones. The team is experiencing communication delays and misunderstandings. Which of the following is the BEST way to improve project communication?

Hard
323

During a daily standup meeting, a team member mentions that they encountered a technical issue that will delay their task by two days. The project is time-sensitive. What should the scrum master do FIRST?

Easy
324

Two senior developers on your hybrid project have a conflict over the technical approach for a critical feature. The conflict is causing delays. What should the project manager do first?

Medium
325

Your project is using a predictive approach. A team member reports that a key deliverable is behind schedule due to an unexpected technical issue. What should the project manager do first?

Easy
326

In an agile project, the team has missed their sprint commitment for the third consecutive sprint. During the retrospective, team members cite unclear requirements and frequent interruptions from stakeholders. As the project manager, what is the BEST action to take?

Medium
327

You are managing a marketing campaign project. A key stakeholder, the VP of Marketing, frequently bypasses you and gives direct instructions to team members. This has caused confusion and rework. What should you do FIRST?

Medium
328

A project manager is reviewing the project's risk register and identifies several risks that could impact the project. According to PMBOK Guide, which THREE of the following are strategies for negative risks or threats? (Choose three.)

Hard
329

In a hybrid project, the team is experiencing frequent interruptions from support requests that are not part of the project scope. The project manager wants to protect the team's focus. Which THREE actions should the project manager take?

Medium
330

During project closure, the customer is satisfied with the deliverables and has signed off. However, the project team has not completed the lessons learned documentation. Which TWO actions should you take?

Easy
331

You are managing a software development project using a hybrid approach. During a sprint review, the product owner demonstrates a completed feature to key stakeholders. One stakeholder is impressed and requests an additional functionality that was not in the original scope. The team estimates it would take two additional sprints. What should the project manager do FIRST?

Medium
332

You are managing a large-scale construction project. A critical vendor has informed you that they will be delayed by two months due to a raw material shortage. This risk was identified and recorded in the risk register with a contingency plan to use an alternative vendor. However, the alternative vendor's materials are more expensive and will increase project costs by 10%. Which THREE actions should you take?

Hard
333

A project manager is managing a construction project and notices that the actual cost for concrete work is consistently 15% above budget. The earned value (EV) is $100,000, and the actual cost (AC) is $115,000. The project manager wants to estimate the cost at completion (EAC) if this trend continues. Which formula should the project manager use?

Hard
334

During a daily standup, a developer mentions that a third-party API integration is more complex than anticipated and will take an extra two days. The sprint ends in four days. The product owner is not in the meeting. What should the scrum master do FIRST?

Easy
335

A project manager is developing the project schedule and needs to account for a resource that is only available 50% of the time. Which technique should be used to adjust the schedule?

Medium
336

Your project is in the executing phase, and you receive a formal complaint from a team member that another team member is consistently late to daily standups and not completing tasks on time. This is causing friction in the team. You have discussed this with both individuals, but the behavior continues. What should you do NEXT?

Hard
337

A project manager is leading a software development project using agile methodology. The team has completed 3 sprints, but the product owner is dissatisfied because the delivered features do not meet the expected business value. The team claims they followed the prioritized backlog. What should the project manager do?

Hard
338

During project execution, a key supplier notifies you that they will be unable to deliver a critical component on time. This component is on the critical path. The risk was identified, and the response strategy was to accept the risk. Which THREE actions should you take? (Select exactly three.)

Medium
339

Your project is in the execution phase. The earned value metrics are: EV=$200,000, PV=$250,000, AC=$220,000. The project is behind schedule and over budget. You need to present a recovery plan to the steering committee. Which combination of actions is BEST aligned with PMI best practices?

Hard
340

During a daily standup, a developer mentions that a critical integration task is blocked because the API documentation from an external vendor is incomplete. The sprint ends in three days, and this task is on the critical path. What should the scrum master do FIRST?

Medium
341

Two senior developers on your agile team have a disagreement about the best technical approach for a user story. The disagreement is causing delays and tension in the team. What should the scrum master do?

Easy
342

During project execution, you notice that the project's cost performance index (CPI) is 0.9 and schedule performance index (SPI) is 0.95. The project is currently 50% complete. Which THREE actions should you take?

Hard
343

Your project team is using a hybrid approach. During a sprint, an executive stakeholder contacts a developer directly and asks them to add a new feature without going through the product owner. The developer is confused about what to do. What should you, as the project manager, do to address this?

Medium
344

Your project's cost performance index (CPI) is 0.8, and the schedule performance index (SPI) is 1.1. The project is in the execution phase. What is the most likely reason for these indices?

Easy
345

Your project is using a predictive approach, and you are at the midpoint. The earned value analysis shows: EV = $450,000, PV = $500,000, AC = $550,000. The CPI is 0.82 and SPI is 0.90. The sponsor asks for a forecast of the total cost at completion. What is the best estimate for EAC assuming the current cost performance is typical of future performance?

Hard
346

You are managing a project with a fixed-price contract. Midway, a new regulation requires additional compliance testing that was not in the original scope. The cost of this testing is significant. The project has no contingency reserve left. What is the best course of action?

Hard
347

Your project is 80% complete, and the sponsor asks you to skip the final testing phase to release the product early and capture market share. The testing phase is critical for quality. What is the BEST response?

Hard
348

You are the project manager for a software development project using a hybrid approach. During a sprint review, the product owner requests a significant change to a feature that has already been accepted in a previous sprint. The change would require rework and impact the critical path. What should you do FIRST?

Medium
349

Your project is behind schedule due to an unexpected delay from a key supplier. The critical path analysis shows that the total float is now negative. What is the BEST course of action?

Hard
350

A project manager is developing the project schedule. After defining activities and sequencing them, what is the next step in the schedule development process?

Easy
351

A project manager is developing the schedule for a new product development project. Which TWO techniques can be used to compress the schedule?

Medium
352

A stakeholder bypasses you and gives direct instructions to a team member to add a new report. The team member has already started working on it. What should the project manager do first?

Easy
353

In a hybrid project, the development team is using Scrum, and the project manager is responsible for overall coordination. During a sprint, the product owner asks the team to add a high-priority user story that was not included in the sprint planning. The team is concerned about overcommitment. What should the project manager do?

Hard
354

Which THREE of the following are common causes of project change requests?

Hard
355

A project team is implementing a new software feature. During testing, a critical defect is found that could delay the release. The project manager needs to determine the root cause. Which tool or technique should be used?

Medium
356

Your agile project is experiencing a drop in velocity for the third consecutive sprint. The team reports that they are spending too much time in unplanned meetings and dealing with frequent requirement changes. Which TWO actions should you take to address this?

Medium
357

During a sprint retrospective, the team identifies that velocity has dropped due to too many interruptions. What agile technique should the Scrum Master recommend to address this?

Easy
358

A project using a predictive approach is 40% complete. The earned value (EV) is $200,000, the planned value (PV) is $250,000, and the actual cost (AC) is $230,000. What should the project manager do NEXT?

Medium
359

You are managing a project that is experiencing scope creep. Several stakeholders have been informally requesting additional features directly from team members. Which TWO actions should you take to address this?

Medium
360

A project is 60% complete. The earned value (EV) is $120,000, the planned value (PV) is $150,000, and the actual cost (AC) is $130,000. What is the cost performance index (CPI) and what does it indicate?

Medium
361

Your agile team is struggling with consistently low velocity. The team is demotivated. Which THREE actions should the project manager take to address this?

Medium
362

You are managing a software upgrade project. A senior executive bypasses you and directly instructs a team member to include a new feature in the release. The team member is confused and asks for your direction. What should you do FIRST?

Medium
363

During a sprint retrospective, the team identifies that their velocity has dropped significantly in the last two sprints. What should the scrum master do FIRST?

Medium
364

During a project, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will add two weeks to the schedule but no additional cost. The change request is approved by the change control board (CCB). What should the project manager do next?

Hard
365

In a hybrid project, the team has been using both Kanban and traditional planning. The product owner requests that the team focus on completing all work in the current iteration before taking on new tasks. However, the team has been pulling new work as capacity allows. What is the BEST action for the project manager?

Medium
366

A project is falling behind schedule, and the project manager wants to get it back on track. Which TWO schedule compression techniques are most appropriate?

Medium
367

In an agile project, the team's velocity has been declining over the last three sprints. The team is delivering fewer story points each sprint. The product owner is concerned about the release date. What should the Scrum Master do first?

Medium
368

Your project is using a hybrid approach with both predictive and agile elements. Mid-project, a key stakeholder requests a significant scope change that would affect the critical path. Which THREE actions should you take?

Hard
369

During a project status meeting, an executive stakeholder informs the team that they have instructed a developer to add a new feature to the product without going through the change control process. The developer has already completed the work. What should the project manager do NEXT?

Medium
370

Your project is 60% complete. The cost performance index (CPI) is 1.1, and the schedule performance index (SPI) is 0.85. The project sponsor is concerned about the schedule delay. Which of the following is the BEST action to take?

Medium
371

During project execution, a key stakeholder requests a change that will increase project scope by 15% but will also reduce operational costs by 20% after deployment. The project is currently on schedule and under budget. The project manager should FIRST:

Hard
372

You are the project manager for a large IT infrastructure upgrade. An executive stakeholder has been bypassing you and directly assigning tasks to team members. This has caused confusion and rework. What should you do FIRST?

Hard
373

During a daily standup, a developer mentions that they have started working on an additional feature requested by the product owner, which was not in the sprint backlog. What should the scrum master do?

Easy
374

A new government regulation is announced that will impact your project's deliverables. The regulation requires additional compliance testing that was not in the original scope. The project is currently on schedule and within budget. What should you do FIRST?

Hard
375

You are managing a software development project using an Agile approach. The team consists of 8 developers and 2 testers. During the last three sprints, the team has consistently delivered about 70% of planned story points. The product owner is frustrated because key features are being delayed. The team reports that they are spending too much time fixing defects found during testing, and that the testers are a bottleneck. Upon reviewing the definition of done, you notice that unit tests are required but not always written, and integration tests are done only at the end of the sprint. What is the BEST course of action to address the root cause?

Medium
376

You are managing a project to develop a new mobile app. During the testing phase, the quality assurance team discovers a critical bug that could delay the release by two weeks. The product owner insists on releasing on the original date to meet a market opportunity. What should you do?

Medium
377

You are managing a construction project. During a quality audit, you find that the concrete used in the foundation does not meet the specified strength requirements. The team has already poured the concrete. The project is on a tight schedule, and rework will delay the project by three weeks. What should you do NEXT?

Hard
378

During the execution phase of a road construction project, the team discovers an unmarked underground utility line that was not shown on any plans. Working near it poses a safety risk, and the project must halt until the utility is identified and mapped. The risk register did not include this specific risk. What should the project manager do FIRST?

Medium
379

During a daily standup, a developer mentions that a risk identified in the risk register has occurred and is causing a one-day delay. The risk response plan includes a mitigation strategy that can be implemented immediately. What should the project manager do FIRST?

Easy
380

Your project is behind schedule, and you need to compress the schedule. The critical path has been identified. What is the BEST schedule compression technique to use if you have additional budget available?

Medium
381

Your project is using a predictive approach, and you are in the execution phase. A key stakeholder requests a minor change that you believe will improve the product but is not in the scope. What should you do?

Medium
382

The project team is in the process of identifying risks. Which tool or technique should the project manager use to identify risks?

Easy
383

A project manager is reviewing the quality metrics of a software development project. The testing team has found that the defect rate has increased significantly in the last two builds. What is the first action the project manager should take?

Easy
384

Refer to the exhibit. The project's access control policy allows read access only from the internal network (10.0.0.0/8) and denies access if not using an encrypted connection. A developer reports that they can access the repository from a machine with IP 10.0.0.5 using an encrypted connection. However, they cannot access it from a machine with IP 10.0.0.6 using an unencrypted connection. What is the most likely reason?

Hard
385

A critical risk identified in the risk register has occurred. The planned response was to mitigate, but the impact is higher than anticipated. What should the project manager do FIRST?

Medium
386

Your construction project is ahead of schedule but over budget. The earned value metrics are: EV = $500,000, PV = $450,000, AC = $550,000. What is the cost performance index (CPI) and schedule performance index (SPI)?

Medium
387

You are closing a project phase. Which THREE activities should be performed during the project closure process?

Easy
388

During project execution, a key team member resigns. The project manager needs to fill the position quickly. What is the FIRST step the project manager should take?

Easy
389

A change request that affects the critical path has been approved. What is the NEXT step for the project manager?

Easy

Frequently asked questions

What does the Process — Managing Technical Aspects domain cover on the PMP exam?
Process — Managing Technical Aspects questions test whether you can apply the concept in context, not just recognise a definition.
How many questions are in this domain?
This page lists all 389 Process — Managing Technical Aspects questions in the PMP question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
What is the best way to practise this domain?
Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.