Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

Your project is halfway through its planned 18-month schedule. The sponsor has asked you to skip the final testing phase to meet a regulatory deadline, citing that the team is experienced and testing is unnecessary. What should you do FIRST?

⚠ Common exam trap

PMI often tests the misconception that the sponsor's authority should be followed without question, but the correct response is to first analyze and communicate risks before making a decision.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests

As a project manager, your first responsibility is to assess and communicate the impact of a requested change. Skipping the final testing phase introduces significant quality and compliance risks, especially given the regulatory deadline. By explaining these risks and proposing a reduced but critical test scope, you demonstrate proactive risk management and stakeholder negotiation, which aligns with the PMI's focus on balancing constraints.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate to the PMO for a decision

    Why it's wrong here

    Escalating directly to the PMO without first engaging the sponsor to understand their concerns and explore potential solutions is premature. A project manager is expected to attempt resolution at the lowest possible level, leveraging direct communication and negotiation skills. Bypassing the primary stakeholder for an issue that falls within the project manager's purview demonstrates a lack of initiative in problem-solving and can undermine the PM's authority and relationship with the sponsor.

  • Refuse to skip testing and insist on the original plan

    Why it's wrong here

    A flat refusal to consider the sponsor's request, insisting rigidly on the original plan, demonstrates a lack of flexibility and collaborative spirit. While maintaining quality is crucial, a project manager should engage in constructive dialogue, exploring the sponsor's motivations and the implications of their request. Such an unyielding stance can damage the vital sponsor relationship, hindering future cooperation and potentially leading to project roadblocks or lack of support.

  • Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests

    Why this is correct

    This option exemplifies proactive risk management and effective stakeholder communication. By clearly articulating the potential negative consequences of skipping testing, the project manager fulfills their professional responsibility to protect project quality and value. Furthermore, proposing viable alternatives, like optimizing test scope to focus on critical areas, demonstrates a solution-oriented approach that balances schedule constraints with essential quality assurance, fostering collaboration and trust with the sponsor.

  • Agree to skip testing to maintain the deadline, as the sponsor has authority

    Why it's wrong here

    Agreeing to skip testing solely to meet a deadline, even at the sponsor's request, represents a significant compromise of project quality and an abdication of professional responsibility. While the sponsor holds authority, a project manager has an ethical obligation to advise on risks and protect the integrity of the deliverables. Sacrificing essential quality assurance activities can lead to increased defects, rework, and ultimately, a failed product or service, despite meeting the initial schedule.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.