- A
Escalate to the PMO for a decision
Why wrong: While escalation may be needed, first attempt to resolve with sponsor directly.
- B
Refuse to skip testing and insist on the original plan
Why wrong: A flat refusal without discussion may damage sponsor relationship; collaboration is better.
- C
Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests
Communicating risks and proposing alternatives demonstrates proactive problem-solving while still meeting the deadline.
- D
Agree to skip testing to maintain the deadline, as the sponsor has authority
Why wrong: Skipping testing is gold-plating avoidance but actually it's compromising quality; sponsor's request does not override professional ethics.
Quick Answer
The correct first step is to explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests. This response is correct because it directly addresses the sponsor’s request by applying the PMI principle of proactive risk communication and stakeholder negotiation. As a project manager, your primary duty is to assess the impact of any requested change on the triple constraint—scope, schedule, and quality—and to articulate those risks before any decision is made. Skipping final testing introduces significant quality and compliance vulnerabilities, especially when a regulatory deadline is involved, so proposing a reduced but critical test scope balances the sponsor’s urgency with responsible risk management. On the PMP exam, this scenario tests your ability to navigate scope creep and stakeholder pressure without compromising project integrity; a common trap is to immediately accept the request or escalate without first analyzing alternatives. Remember the mnemonic “RAP” for this situation: Recognize the risk, Articulate the impact, Propose a compromise.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is halfway through its planned 18-month schedule. The sponsor has asked you to skip the final testing phase to meet a regulatory deadline, citing that the team is experienced and testing is unnecessary. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests
Option C is correct because, as a project manager, your first responsibility is to assess and communicate the impact of a requested change. Skipping the final testing phase introduces significant quality and compliance risks, especially given the regulatory deadline. By explaining these risks and proposing a reduced but critical test scope, you demonstrate proactive risk management and stakeholder negotiation, which aligns with the PMI's focus on balancing constraints.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Escalate to the PMO for a decision
Why it's wrong here
While escalation may be needed, first attempt to resolve with sponsor directly.
- ✗
Refuse to skip testing and insist on the original plan
Why it's wrong here
A flat refusal without discussion may damage sponsor relationship; collaboration is better.
- ✓
Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests
Why this is correct
Communicating risks and proposing alternatives demonstrates proactive problem-solving while still meeting the deadline.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Agree to skip testing to maintain the deadline, as the sponsor has authority
Why it's wrong here
Skipping testing is gold-plating avoidance but actually it's compromising quality; sponsor's request does not override professional ethics.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the misconception that the sponsor's authority should be followed without question, but the correct response is to first analyze and communicate risks before making a decision.
Detailed technical explanation
How to think about this question
In project management, the testing phase is a critical quality control gate that validates the product against requirements and regulatory standards. Skipping it entirely can lead to undetected defects, rework costs, and potential legal penalties if the product fails compliance audits. A reduced test scope, such as risk-based testing, focuses on high-priority functions and regulatory-critical paths, balancing schedule pressure with acceptable risk levels.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Explain the risks of skipping testing and propose alternatives such as reducing test scope while maintaining critical tests — Option C is correct because, as a project manager, your first responsibility is to assess and communicate the impact of a requested change. Skipping the final testing phase introduces significant quality and compliance risks, especially given the regulatory deadline. By explaining these risks and proposing a reduced but critical test scope, you demonstrate proactive risk management and stakeholder negotiation, which aligns with the PMI's focus on balancing constraints.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.