Question 577 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a sprint review, the product owner requests a significant change to a feature that was just completed. The change would improve user experience but would require reworking two sprints' worth of work. The project is already behind schedule. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the change request and assess its impact on the project constraints before submitting for approval

Option B is correct because the project manager must first follow the formal change control process by documenting the change request and assessing its impact on the triple constraints (scope, schedule, cost) before any approval or rejection. This aligns with the PMBOK Guide's Integrated Change Control process, which ensures that changes are evaluated systematically to avoid uncontrolled scope creep, especially when the project is already behind schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Agree to the change since it improves user experience and ask the team to start rework

    Why it's wrong here

    Implementing changes without formal approval bypasses change control.

  • Document the change request and assess its impact on the project constraints before submitting for approval

    Why this is correct

    This follows the Integrated Change Control process.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Reject the change because the project is already behind schedule

    Why it's wrong here

    Rejecting without proper evaluation is not the PMI approach.

  • Add the change to the product backlog for a future release without adjusting the current sprint

    Why it's wrong here

    Adding to backlog without formal change control may be acceptable in agile, but the PM should still document and assess impact before prioritizing.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think the product owner's request should be immediately accommodated or rejected based on schedule pressure, but the PMP exam emphasizes that the first step is always to document and assess the change through the formal change control process, regardless of the project's status.

Detailed technical explanation

How to think about this question

In Agile frameworks, the product owner can request changes at any time, but the project manager (or Scrum Master) must ensure that changes are evaluated through the product backlog refinement process. The change control board (CCB) or product owner, depending on the governance model, reviews the impact analysis before approving changes. In this scenario, the project manager should perform a cost-benefit analysis and schedule impact assessment, potentially using earned value management (EVM) metrics like schedule performance index (SPI) to quantify the delay before deciding to rework or defer.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Document the change request and assess its impact on the project constraints before submitting for approval — Option B is correct because the project manager must first follow the formal change control process by documenting the change request and assessing its impact on the triple constraints (scope, schedule, cost) before any approval or rejection. This aligns with the PMBOK Guide's Integrated Change Control process, which ensures that changes are evaluated systematically to avoid uncontrolled scope creep, especially when the project is already behind schedule.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.