- A
Pair the new member with a senior team member for mentoring and knowledge sharing
Pairing promotes collaboration and accelerates learning.
- B
Assign less complex tasks to the new member until they catch up
Why wrong: This may isolate the new member and not address integration holistically.
- C
Ask the team to work overtime to compensate
Why wrong: Overtime is unsustainable and may cause burnout.
- D
Extend the sprint duration to give the new member more time
Why wrong: Changing sprint duration for one member disrupts team cadence.
Quick Answer
The answer is to pair the new member with a senior team member for mentoring and knowledge sharing. This is correct because it directly applies the agile principle of collaboration and continuous learning, allowing the new member to ramp up efficiently through real-time guidance on coding standards, architecture, and workflow without disrupting the team’s velocity. On the Project Management Professional PMP exam, this scenario tests your understanding of servant leadership and team development within an agile framework, specifically how to integrate a new team member into a high-performing agile team without sacrificing cohesion. A common trap is choosing to slow the entire team’s pace or reassign tasks, which undermines agile’s focus on self-organization and sustainable flow. Remember the memory tip: “Pair to share, not to compare”—pairing accelerates onboarding through shared knowledge, not by comparing speeds.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A new team member joins a high-performing agile team. The existing team members are concerned that the new member's pace is slower. What should the project manager do to integrate the new member effectively?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Pair the new member with a senior team member for mentoring and knowledge sharing
Pairing the new member with a senior team member leverages mentoring and knowledge sharing, which aligns with agile principles of collaboration and continuous learning. This approach helps the new member ramp up efficiently while maintaining team cohesion and velocity, as the senior member can provide real-time guidance on the team's coding standards, architecture, and workflow.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Pair the new member with a senior team member for mentoring and knowledge sharing
Why this is correct
Pairing promotes collaboration and accelerates learning.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Assign less complex tasks to the new member until they catch up
Why it's wrong here
This may isolate the new member and not address integration holistically.
- ✗
Ask the team to work overtime to compensate
Why it's wrong here
Overtime is unsustainable and may cause burnout.
- ✗
Extend the sprint duration to give the new member more time
Why it's wrong here
Changing sprint duration for one member disrupts team cadence.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may choose Option B (assigning less complex tasks) thinking it protects the sprint goal, but it actually hinders the new member's holistic understanding of the product and team processes, which is a key agile principle.
Detailed technical explanation
How to think about this question
In agile frameworks like Scrum, the sprint duration is a fixed time-box (typically 1-4 weeks) that provides rhythm and predictability; extending it would break the sprint goal and invalidate velocity metrics. Pair programming, a common XP practice, not only transfers tacit knowledge but also improves code quality through continuous code review, reducing defect injection rates by up to 15% in real-world studies. The project manager should facilitate this pairing without micromanaging, trusting the team's self-organization to adjust workload dynamically.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Pair the new member with a senior team member for mentoring and knowledge sharing — Pairing the new member with a senior team member leverages mentoring and knowledge sharing, which aligns with agile principles of collaboration and continuous learning. This approach helps the new member ramp up efficiently while maintaining team cohesion and velocity, as the senior member can provide real-time guidance on the team's coding standards, architecture, and workflow.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A new team member joins your agile project. They have no experience with Scrum and seem overwhelmed. What should you do to onboard them effectively?
easy- A.Pair them with a senior developer only for coding tasks
- ✓ B.Assign them a mentor and provide training on agile principles
- C.Give them the project documentation and ask them to read it
- D.Let them learn by observing the team for the first few sprints
Why B: Option B is correct because onboarding a new team member with no Scrum experience requires a structured approach that combines mentorship with formal training on agile principles. This ensures they understand the Scrum framework, roles, events, and artifacts, which is critical for them to contribute effectively and reduce overwhelm. Simply pairing them for coding tasks (A) or leaving them to observe (D) neglects the foundational knowledge needed to participate in Scrum ceremonies and collaborate with the team.
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.