Courseiva
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

You are the project manager on a large infrastructure project. During execution, a new government regulation is announced that will affect your project's compliance requirements. The change is mandatory and must be implemented within 60 days, or the project will be shut down. What should you do first?

⚠ Common exam trap

Test-takers frequently assume urgent mandatory changes justify skipping the change control process, but PMP best practices require impact analysis and a formal change request before any implementation, even under tight deadlines.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact on the project and submit a change request to incorporate the new requirements

The first step when a mandatory regulation arises is to analyze its impact on the project's scope, schedule, and budget, then submit a formal change request to integrate the new requirements. This aligns with the PMBOK Guide's change control process, ensuring the change is evaluated and approved before implementation, even under urgent compliance deadlines.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Direct the team to immediately implement the changes required by the regulation to avoid shutdown

    Why it's wrong here

    While the urgency of avoiding a shutdown is critical, directing immediate implementation without formal process is a critical governance failure. All changes, especially those with significant project impact, must follow the integrated change control process to assess scope, schedule, cost, and risk implications. Bypassing this process undermines project control, potentially leading to unmanaged scope creep, budget overruns, and unapproved deviations from the project baseline. This approach lacks proper documentation and stakeholder alignment.

  • Inform the sponsor that the project will need to be cancelled due to the new regulation

    Why it's wrong here

    Recommending project cancellation as an initial response to a new regulation is premature and demonstrates a lack of proactive problem-solving. A project manager's responsibility includes analyzing new constraints, assessing their impact, and developing potential mitigation strategies or alternative approaches to achieve project objectives. Only after a thorough analysis reveals no viable path to compliance, or if the cost/schedule impact is prohibitive, should cancellation be considered and presented with supporting data to the sponsor.

  • Ignore the regulation and continue as planned because it is not yet enforced

    Why it's wrong here

    Ignoring a newly announced regulation, even if not immediately enforced, is a severe breach of project governance and risk management principles. Project managers are ethically and legally obligated to ensure project compliance with all relevant laws and regulations. Failing to proactively address this mandatory requirement exposes the project to significant legal penalties, reputational damage, and potentially costly rework or project shutdown once enforcement begins. Proactive assessment and planning are essential to mitigate such risks.

  • Analyze the impact on the project and submit a change request to incorporate the new requirements

    Why this is correct

    This is the correct and most professional approach. The project manager must first conduct a thorough impact analysis to understand how the new regulation affects the project's scope, schedule, cost, quality, resources, and risks. Subsequently, a formal change request must be submitted through the integrated change control process, detailing the proposed adjustments and their implications. This ensures that all changes are properly reviewed, approved by the Change Control Board (CCB), documented, and incorporated into the project baselines in a controlled manner, maintaining project governance and stakeholder alignment.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.