Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

During a project status meeting, the sponsor asks you to skip the final round of testing to meet the original deadline, stating that the product is already 'good enough.' What is your best response?

⚠ Common exam trap

Candidates often choose Option C (refuse outright) because it seems principled, but the PMP exam emphasizes stakeholder collaboration and formal change control over rigid adherence to plans without risk communication.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping testing and propose a formal change request to document the decision

It aligns with the PMP Code of Ethics and Professional Conduct, which requires project managers to provide accurate information and manage risks transparently. By explaining the risks of skipping testing and proposing a formal change request, you ensure that the decision is documented, the sponsor understands the potential impact on quality and schedule, and the project remains compliant with organizational processes. This approach balances stakeholder expectations with professional responsibility.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Agree to skip testing to maintain the schedule and stakeholder satisfaction

    Why it's wrong here

    Agreeing to skip testing directly compromises the project's quality baseline and introduces significant risks of defects and rework later in the project lifecycle. This decision, driven solely by schedule and satisfaction, neglects the project manager's responsibility to protect product integrity and can lead to increased costs and diminished stakeholder trust in the long run. PMI's ethical guidelines and quality management principles strongly advise against such shortcuts that jeopardize deliverable quality.

  • Secretly continue testing but report that testing is complete

    Why it's wrong here

    Secretly continuing testing while reporting its completion constitutes a severe breach of ethical conduct and transparency, directly violating the PMI Code of Ethics and Professional Conduct. This deceptive practice undermines the trust relationship with the sponsor and other stakeholders, providing inaccurate status information that can lead to misinformed decisions. A project manager has a fundamental responsibility to communicate truthfully and maintain integrity in all project dealings.

  • Refuse outright and insist on completing all testing as planned

    Why it's wrong here

    Refusing the sponsor's request outright without exploring alternatives or understanding their rationale demonstrates poor stakeholder management and a lack of collaborative problem-solving. While quality is paramount, a project manager should engage in constructive dialogue, present data-driven impacts, and work with the sponsor to find mutually agreeable solutions, rather than simply dictating terms. This approach fails to leverage the sponsor's authority and insights, potentially creating unnecessary conflict and resistance.

  • Explain the risks of skipping testing and propose a formal change request to document the decision

    Why this is correct

    Explaining the risks associated with skipping testing provides the sponsor with critical information necessary for an informed decision, upholding the project manager's duty of transparency and risk communication. Proposing a formal change request ensures that any deviation from the approved project baseline is properly documented, reviewed, and formally approved through integrated change control. This approach demonstrates proactive risk management, adheres to governance, and maintains project accountability, aligning with best practices for managing scope and quality changes.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.