PMP People — Leading Projects Practice Question
During a project status meeting, the sponsor asks you to skip the final round of testing to meet the original deadline, stating that the product is already 'good enough.' What is your best response?
⚠ Common exam trap
Candidates often choose Option C (refuse outright) because it seems principled, but the PMP exam emphasizes stakeholder collaboration and formal change control over rigid adherence to plans without risk communication.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Explain the risks of skipping testing and propose a formal change request to document the decision
It aligns with the PMP Code of Ethics and Professional Conduct, which requires project managers to provide accurate information and manage risks transparently. By explaining the risks of skipping testing and proposing a formal change request, you ensure that the decision is documented, the sponsor understands the potential impact on quality and schedule, and the project remains compliant with organizational processes. This approach balances stakeholder expectations with professional responsibility.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Agree to skip testing to maintain the schedule and stakeholder satisfaction
Why it's wrong here
Agreeing to skip testing directly compromises the project's quality baseline and introduces significant risks of defects and rework later in the project lifecycle. This decision, driven solely by schedule and satisfaction, neglects the project manager's responsibility to protect product integrity and can lead to increased costs and diminished stakeholder trust in the long run. PMI's ethical guidelines and quality management principles strongly advise against such shortcuts that jeopardize deliverable quality.
- ✗
Secretly continue testing but report that testing is complete
Why it's wrong here
Secretly continuing testing while reporting its completion constitutes a severe breach of ethical conduct and transparency, directly violating the PMI Code of Ethics and Professional Conduct. This deceptive practice undermines the trust relationship with the sponsor and other stakeholders, providing inaccurate status information that can lead to misinformed decisions. A project manager has a fundamental responsibility to communicate truthfully and maintain integrity in all project dealings.
- ✗
Refuse outright and insist on completing all testing as planned
Why it's wrong here
Refusing the sponsor's request outright without exploring alternatives or understanding their rationale demonstrates poor stakeholder management and a lack of collaborative problem-solving. While quality is paramount, a project manager should engage in constructive dialogue, present data-driven impacts, and work with the sponsor to find mutually agreeable solutions, rather than simply dictating terms. This approach fails to leverage the sponsor's authority and insights, potentially creating unnecessary conflict and resistance.
- ✓
Explain the risks of skipping testing and propose a formal change request to document the decision
Why this is correct
Explaining the risks associated with skipping testing provides the sponsor with critical information necessary for an informed decision, upholding the project manager's duty of transparency and risk communication. Proposing a formal change request ensures that any deviation from the approved project baseline is properly documented, reviewed, and formally approved through integrated change control. This approach demonstrates proactive risk management, adheres to governance, and maintains project accountability, aligning with best practices for managing scope and quality changes.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Project Management Plan
A formal, approved document that defines how a project is executed, monitored, controlled, and closed, serving as the single source of truth for the project team.
Key term
Training and Development
Training and Development is the process of enhancing team members' skills, knowledge, and competencies to improve project performance and achieve career growth.
About these practice questions
One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.