Courseiva
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

A new regulation is announced that will affect your project's deliverables. The compliance team has determined that the project must adapt to the new regulation before completion. What should the project manager do FIRST?

⚠ Common exam trap

Many candidates assume regulatory urgency justifies immediate action (Option C) or an exception (Option D), but the PMP exam emphasizes that the change control process must be followed for all changes, regardless of urgency, to maintain control and documentation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board with an analysis of the impact on scope, schedule, and cost.

The correct first step is to submit a formal change request with an impact analysis because the new regulation represents a change that must be evaluated and approved through the established change control process. This ensures that scope, schedule, and cost impacts are documented and authorized before any work begins, maintaining project governance and compliance with organizational policies.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request to the change control board with an analysis of the impact on scope, schedule, and cost.

    Why this is correct

    This is the correct procedure per PMI.

  • Update the risk register and continue with the original plan until the change request is approved.

    Why it's wrong here

    While updating the risk register is good, the PM must initiate the change process.

  • Instruct the team to implement the necessary changes immediately to ensure compliance.

    Why it's wrong here

    Implementing changes without formal approval bypasses change control.

  • Ask the sponsor to approve an exception to the change control process due to regulatory urgency.

    Why it's wrong here

    Regulatory changes still follow the change control process; no exception is needed.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.