Courseiva
People — Leading ProjectshardMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

In a large-scale digital transformation project, the executive sponsor has been bypassing you and giving direct instructions to the development team. The team is confused about priorities and feels caught between the sponsor's requests and the project plan. What should the project manager do FIRST?

⚠ Common exam trap

Many candidates choose Option C (sending a clarifying email) because it seems direct and authoritative, but PMI emphasizes that the first step in stakeholder conflict is always a private, respectful conversation to avoid public confrontation and preserve relationships.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a private meeting with the sponsor to discuss the issue and agree on a proper communication channel

The first step in resolving a conflict with a powerful stakeholder like an executive sponsor is to address the issue privately and collaboratively. By scheduling a private meeting, the project manager can discuss the impact of the bypassing behavior, clarify the confusion it causes, and agree on a proper communication channel that respects both the sponsor's authority and the project's governance. This aligns with PMI's principle of engaging stakeholders proactively and using conflict resolution techniques like 'confronting' or 'collaborating' to find a mutually acceptable solution.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the stakeholder engagement plan to include a communication protocol and ask the sponsor to review it

    Why it's wrong here

    This action is primarily administrative and reactive, failing to address the immediate behavioral issue of the sponsor bypassing established communication channels. While updating project documentation is a valid process, it is not the most effective first step to resolve an active conflict or deviation. It defers the necessary direct conversation with the sponsor, which is crucial for understanding their motivations and collaboratively re-establishing proper communication protocols. This passive approach risks prolonging the issue and further undermining project governance.

  • Schedule a private meeting with the sponsor to discuss the issue and agree on a proper communication channel

    Why this is correct

    This is the most appropriate and effective first step, demonstrating proactive stakeholder management and conflict resolution. A private meeting allows the project manager to respectfully engage the sponsor, understand their perspective, and reiterate the importance of adhering to established communication protocols. This direct, diplomatic approach facilitates a collaborative discussion to realign expectations and agree on a mutually acceptable communication channel, thereby preserving the professional relationship and maintaining project control.

  • Send an email to the sponsor and the team clarifying that all instructions must go through you

    Why it's wrong here

    This approach is overtly confrontational and public, carrying a high risk of embarrassing the project sponsor and escalating the conflict unnecessarily. A public directive undermines the collaborative spirit essential for effective stakeholder engagement and can severely damage the professional relationship between the project manager and the sponsor. Such a formal, top-down communication should be considered a last resort, not an initial response, when dealing with high-level stakeholders who require diplomatic handling.

  • Advise the team to ignore the sponsor's instructions and follow the project plan

    Why it's wrong here

    Directing the project team to disregard instructions from the project sponsor is highly inappropriate and creates an untenable ethical and operational dilemma for the team members. This action places the team in a direct conflict between two authority figures, which can severely damage team morale, loyalty, and productivity. The project manager's responsibility is to resolve such high-level communication and authority conflicts diplomatically with the sponsor, not to delegate the burden of conflict resolution to the project team.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

Go deeper

Related to this question

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.