Question 603 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor informs you that due to raw material shortages, they cannot deliver a critical component on time. This component is on the critical path. The risk register included this as a high-probability risk with a contingency plan to use an alternative supplier. What should you do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Activate the contingency plan and engage the alternative supplier

D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the project sponsor to approve the alternative supplier

    Why it's wrong here

    The contingency plan should have pre-approved actions; the PM can implement it.

  • Replan the project schedule to accommodate the delay

    Why it's wrong here

    Replanning without using the contingency plan may cause unnecessary delays.

  • Perform a new risk analysis to assess the impact

    Why it's wrong here

    The risk was already identified and planned; re-assessing may delay response.

  • Activate the contingency plan and engage the alternative supplier

    Why this is correct

    Since the risk was identified and a contingency plan exists, the PM should implement it.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse the need for a new risk analysis or approval with the fact that the contingency plan was already approved and documented, leading them to waste time on unnecessary steps instead of executing the pre-planned response.

Detailed technical explanation

How to think about this question

In project risk management, a contingency plan is a pre-defined set of actions to be taken when a specific risk event occurs, and it is typically included in the risk register with a trigger condition. Activating the plan immediately upon trigger avoids schedule slippage on the critical path, as the alternative supplier should have been pre-qualified and ready to step in. This aligns with the PMBOK Guide's 'Implement Risk Responses' process, which emphasizes executing planned responses without delay.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Activate the contingency plan and engage the alternative supplier — D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.