Courseiva
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

A project manager notices that two senior developers have conflicting work styles, causing delays. What is the best approach to resolve this?

⚠ Common exam trap

It's easy for candidates to choose 'assign them to separate tasks' (C) thinking it's a quick fix to avoid conflict, but the PMP exam emphasizes that avoidance is a temporary solution that fails to resolve the root cause, whereas facilitation aligns with the servant leadership mindset.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting to discuss and resolve differences.

Facilitating a meeting to discuss and resolve differences (D) is the best approach because it directly addresses the root cause of the conflict—work style incompatibility—by fostering open communication and collaborative problem-solving. As a project manager, you act as a servant leader, using conflict resolution techniques like 'confronting' or 'problem-solving' to turn the disagreement into a constructive dialogue that aligns the team toward project goals. This approach preserves team cohesion and leverages the developers' expertise without escalating or avoiding the issue.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate to the functional manager for reassignment.

    Why it's wrong here

    Escalation should be a last resort; the PM should attempt resolution first.

  • Ask the team to vote on which style to adopt.

    Why it's wrong here

    Voting is not appropriate for resolving interpersonal conflicts.

  • Assign them to separate tasks to avoid interaction.

    Why it's wrong here

    Avoidance does not resolve the conflict and may cause further issues.

  • Facilitate a meeting to discuss and resolve differences.

    Why this is correct

    Direct conflict resolution is a key PM skill.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.