PMP People — Leading Projects Practice Question

During project execution, the project manager notices that two team members are in frequent conflict, which is affecting the team's overall performance. The project manager wants to resolve the conflict effectively. Which THREE actions align with PMI's recommended approach?

⚠ Common exam trap

Many candidates think addressing conflict publicly in a team meeting demonstrates transparency (Option B), but PMI strictly advises against public confrontation as it damages trust and violates the principle of 'praise in public, criticize in private.'

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a joint meeting to discuss the issue and find common ground

Facilitating a joint meeting aligns with PMI's collaborative conflict resolution approach, where the project manager acts as a neutral facilitator to help conflicting parties discuss issues openly and find common ground. This technique, often called 'confronting' or 'problem-solving,' is the most effective method for resolving interpersonal conflicts and restoring team performance, as it addresses the root cause directly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Facilitate a joint meeting to discuss the issue and find common ground

    Why this is correct

    Facilitating a joint meeting is a highly effective and collaborative conflict resolution technique, often referred to as "confronting the problem" or "problem-solving." The project manager's role is to guide the discussion, ensure all parties have an opportunity to express their views constructively, and help them identify shared interests or mutually acceptable solutions. This approach aims for a win-win outcome, fostering understanding and strengthening team relationships by directly addressing the root cause.

  • Address the conflict in a team meeting to model transparency

    Why it's wrong here

    Addressing a specific interpersonal conflict publicly in a general team meeting is generally counterproductive and often escalates the situation. While transparency is valuable, confronting individuals in front of their peers can lead to embarrassment, defensiveness, and a reluctance to communicate openly, making a constructive resolution difficult. Effective conflict resolution typically requires a more private and controlled environment to protect individual dignity and encourage genuine dialogue.

  • Meet with each team member individually to understand their perspective

    Why this is correct

    Before attempting to mediate a conflict, it is crucial for the project manager to meet individually with each involved team member. These private discussions allow the PM to gather comprehensive information, understand each person's perspective, underlying concerns, and emotional state without the pressure of a joint confrontation. This initial fact-finding and empathy-building step is essential for developing an informed and unbiased strategy for subsequent mediation or problem-solving efforts.

  • Escalate the conflict to the project sponsor for resolution

    Why it's wrong here

    Escalating a conflict directly to the project sponsor for resolution should be considered a last resort, not an initial step. The project manager is primarily responsible for managing team dynamics and resolving conflicts at the lowest possible level. Premature escalation can undermine the PM's authority, demonstrate an inability to manage team issues, and potentially strain relationships with the sponsor, who expects the PM to handle operational challenges.

  • Help the team members agree on a solution and document the resolution

    Why this is correct

    Guiding team members to mutually agree on a solution is a critical step in conflict resolution, ensuring buy-in and commitment to the outcome. Once an agreement is reached, documenting the resolution, including any agreed-upon actions or changes, is equally important. This formalizes the understanding, provides a clear record, and helps prevent the conflict from resurfacing due to misunderstandings or forgotten commitments, thereby ensuring follow-through and accountability.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.