Courseiva
People — Leading ProjectseasyMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

Two senior developers on your project have a heated disagreement about the technical approach for implementing a key feature. They both have strong arguments, and the conflict is delaying the sprint. As the project manager, what is the BEST first step to resolve this conflict?

⚠ Common exam trap

Candidates often choose Option A (escalate) or Option D (decide unilaterally) because they mistake a technical conflict for a decision that requires authority, rather than recognizing that the PM's best first step is to facilitate collaboration and gather information before any decision is made.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Meet with each developer separately to understand their perspectives before facilitating a joint discussion

It follows the PMI conflict resolution principle of 'collaborate/problem-solve' by first gathering individual perspectives privately before facilitating a joint discussion. This approach ensures each developer feels heard, reduces emotional tension, and allows the project manager to identify the underlying technical merits of each argument without group bias. It is the best first step because it addresses the root cause of the conflict—differing technical opinions—before attempting any resolution or escalation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the project sponsor for a decision

    Why it's wrong here

    Escalation should be a last resort after the PM has attempted resolution.

  • Meet with each developer separately to understand their perspectives before facilitating a joint discussion

    Why this is correct

    Gathering information from each party first helps identify the root cause and enables a collaborative solution.

  • Tell the developers to set aside their differences and move forward with the current plan

    Why it's wrong here

    Avoiding the conflict does not address the underlying issue.

  • Choose the approach that aligns with the project's objectives and instruct the team to implement it

    Why it's wrong here

    Imposing a solution without team buy-in may lead to resentment and does not resolve the conflict.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.