Question 692 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to implement the contingency plan defined in the risk register. This is correct because the risk was already identified and documented, meaning the project team had proactively developed a planned response during the Plan Risk Responses process. When a risk occurs, the PMBOK Guide directs you to execute that pre-defined contingency plan first, as it is the most efficient and controlled way to minimize impact on the critical path. On the PMP exam, this scenario tests your understanding of the Implement Risk Responses process, which is often confused with workarounds for unidentified risks. A common trap is to jump into problem-solving or escalate immediately, but the correct first step is always to follow the documented plan. Memory tip: if it’s in the register, use the plan—don’t reinvent the wheel.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor informs you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The risk was identified and documented in the risk register. What should you do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the contingency plan defined in the risk register

Since the risk was already identified and documented in the risk register, the project team should have prepared a contingency plan for this specific scenario. The PMBOK Guide states that when a risk occurs, the first action is to implement the pre-defined contingency plan to minimize impact. This is a proactive, planned response rather than a reactive scramble, and it aligns with the 'Plan Risk Responses' and 'Implement Risk Responses' processes.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the issue to the project sponsor

    Why it's wrong here

    Escalation is not the first step if a risk response plan exists.

  • Implement the contingency plan defined in the risk register

    Why this is correct

    The risk register should contain a response; implementing it is the appropriate action.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Contact the vendor to negotiate a new delivery date

    Why it's wrong here

    This may be part of the response but is not the first step; the PM should follow the risk plan.

  • Immediately look for an alternative vendor

    Why it's wrong here

    This bypasses the planned risk response; the PM should follow the risk management plan.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse 'first action' with 'immediate problem-solving' (like negotiating or finding a new vendor) instead of recognizing that the documented contingency plan is the prescribed first step per PMI's risk response framework.

Detailed technical explanation

How to think about this question

In risk management, a contingency plan is a set of pre-defined actions to be taken if a specific risk event occurs, and it is typically funded by a contingency reserve. The risk register should contain the risk trigger (e.g., 'vendor raw material shortage'), the contingency plan (e.g., 'activate secondary supplier'), and the owner. Implementing this plan first ensures the project stays on track without unnecessary delays or escalation, and it preserves the integrity of the risk management process.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement the contingency plan defined in the risk register — Since the risk was already identified and documented in the risk register, the project team should have prepared a contingency plan for this specific scenario. The PMBOK Guide states that when a risk occurs, the first action is to implement the pre-defined contingency plan to minimize impact. This is a proactive, planned response rather than a reactive scramble, and it aligns with the 'Plan Risk Responses' and 'Implement Risk Responses' processes.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A key vendor has notified you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the project's critical path. What should you do first?

medium
  • A.Initiate legal proceedings against the vendor for breach of contract
  • B.Crash the schedule by adding resources to other tasks to compensate for the delay
  • C.Immediately escalate the issue to the project sponsor
  • D.Evaluate the impact on the project schedule and identify possible alternatives, such as sourcing from another vendor

Why D: Option D is correct because the first step in any project management issue is to analyze the impact and explore alternatives before taking action. Since the component is on the critical path, any delay directly affects the project finish date, so you must evaluate schedule impact and identify options like sourcing from another vendor to mitigate the risk.

Variation 2. A key vendor informs you that due to raw material shortages, they cannot deliver a critical component on time. This component is on the critical path. The risk register included this as a high-probability risk with a contingency plan to use an alternative supplier. What should you do FIRST?

medium
  • A.Ask the project sponsor to approve the alternative supplier
  • B.Replan the project schedule to accommodate the delay
  • C.Perform a new risk analysis to assess the impact
  • D.Activate the contingency plan and engage the alternative supplier

Why D: D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.